babcock brown
play

Babcock & Brown Trans Bay Cable Project General Presentation - PowerPoint PPT Presentation

Babcock & Brown Trans Bay Cable Project General Presentation To San Francisco Port Commission October 11, 2005 Trans Bay Cable Project - Summary The Project will be a new High Voltage Direct Current (HVDC) transmission system that is


  1. Babcock & Brown Trans Bay Cable Project General Presentation To San Francisco Port Commission October 11, 2005

  2. Trans Bay Cable Project - Summary � The Project will be a new High Voltage Direct Current (HVDC) transmission system that is 59-miles long and runs under the Bay from the generation rich East Bay into San Francisco � HVDC technology has been proven reliable and effective � Provides “generator-like” power, exactly what San Francisco needs � Considered “clean power” a more efficient method to transmit energy underground or underwater � Studies have shown that the Project will provide significant benefits for ratepayers � CAISO has determined that a new transmission line or other reinforcements has to be in place following installation of Jefferson-Martin, CCSF Peaker Project and retirement of all older generation in San Francisco � CAISO “approved” TBC’s HVDC Line as the Long Term Electric Infrastructure Project for San Francisco � TBC determined to be the most viable and economical of all options considered for 2011 and beyond � Operation date for the Project is anticipated to be early 2009 � City of Pittsburg municipal utility will eventually own the Project � Babcock & Brown will develop the project and provide the financing � FERC “approved” the Project providing Babcock & Brown and City of Pittsburg the ability to recover their costs 1

  3. Trans Bay Cable Project – Project Benefits � Significant Environmental Benefits � New, “clean” transmission power source, not expected to have significant environmental impacts, EIR analysis to confirm � Project causes a reduction in transmission system losses, and eliminates associated emissions � When SF Peakers are installed with Trans Bay Cable Project, Peakers will likely operate less � Transmits power from existing power generating facilities near and other transmission lines feeding the Pittsburg substation � TBC Project will not disrupt heavily populated areas or sensitive nature areas � Enhanced Reliability � Higher reliability than a generator � Very secure underwater and underground � Not vulnerable to natural disasters on land that would disrupt other transmission systems � Reduces power flow on other transmission, especially the Peninsula, benefiting entire Greater Bay Area � Long term load serving capability � Completes the Greater Bay Area transmission loop, increasing transmission system security 2

  4. Trans Bay Cable Project – Project Benefits Benefits to San Francisco � CAISO selected TBC Project as the critical third component for San Francisco Reliability � Jefferson to Martin Transmission Line: Shut down Hunters Point 1. San Francisco Peaker Project: RMR removed from Potrero 2. TBC HVDC transmission Line from Pittsburg to San Francisco: Post 2011 (possibility 2010) load 3. serving solution No impact on San Francisco or other Community Residences or Business � Local hire Construction Jobs via Project Labor Agreement � When SF Peakers are installed with Trans Bay Cable Project, Peakers will likely operate � less Completes the Greater Bay Area transmission loop, increasing transmission system � security for SF 3

  5. Trans Bay Cable Project – Major Project Milestones � Development Agreements Executed with City of Pittsburg: January, 2004 � Notice of Preparation Issued Under California Environmental Quality Act (CEQA), with City of Pittsburg as Lead Agency: August, 2004 � FERC “Approval” of TBC Rate Principals: July, 2005 � CAISO “Approval” of TBC Project Need: September, 2005 � Draft Environmental Impact Report (EIR) Issuance: [January, 2006] � Final EIR Issuance: [April, 2006] � City of Pittsburg Certification of EIR: [June, 2006] � Discretionary Acts (Permits, State Easements, etc.) Complete: [September, 2006] � Close of Financing: [October, 2006] � Commercial Operation of Line: [January, 2009] 4

  6. Trans Bay Cable Project – CEQA Procedures for the Project � City of Pittsburg is acting as lead agency for CEQA purposes � Notice of Preparation was issued in August, 2004, and broadly circulated to 276 public agencies and environmental groups � Many state and federal agencies are expected to act as responsible agencies under CEQA, including (for example), State Lands Commission and BCDC � URS engaged to prepare environmental documents � City of Pittsburg engaged Lamphier-Gregory for project planning and independent environmental consulting services � Proposed cable route in the Bay will be the subject of comprehensive environmental surveys as part of the EIR process � Public scoping sessions are planned for the East Bay and San Francisco in October and November 2005 � Draft EIR expected to be circulated for public comment in 1 st quarter 2006 � TBC held Public Open House meetings in Potrero Hill and Hunters Point in September 2005 and the City of Pittsburg in October 2005 5

  7. Trans Bay Cable Project – Submarine Cable Route 6

  8. Trans Bay Cable Project – Aerial View of HWC Converter Site near the Potrero Substation in San Francisco 7

  9. Trans Bay Cable Project – Typical DC Converter Station Control Building Valve Hall AC Cable entry Spare DC Hall Transformer DC Cable entry * AC, AIS Switchyard Valve Cooling Converter Transformer Capacitor Bank Busbar AC Filter *The dimension of the Converter Station can be reduced by using a Gas Insulated Switchyard (GIS) instead of the Air Insulated Switchyard (AIS). 8

  10. Trans Bay Cable Project – Proposed Cable Laying Vessel Cableship – Giulio Verne Main features • Length Overall 133 m • Moulded Breadth 30 m • Draft 8.5 m • Gross Tonnage 10,617 tons • Dynamic Positioning Control • Total propulsion Power 5,710 kW • Capstan 6 m diameter, 50 tons pulling tension • Linear laying machine 10 tons pulling tension • Turntable, external dia. 25 m, capacity 7,000 tons 9

  11. Trans Bay Hydroplow DC Cable Underwater Installation � Cable Installation one to two months � The Cable is taken to the trench bottom by a stinger � Simultaneous lay & burial → cable immediately protected (no cable exposure) � Very effective burial method - Jetting power focused on excavation only � “Minimal” Environmental Impacts 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend