www.centennialcoal.com.au
August 2017 Extraordinary CCC Meeting
Springvale Coal Services Operations (SCSO)
Western Coal Services (WCS) Lidsdale Siding (LS)
August 2017 Extraordinary CCC Meeting Springvale Coal Services - - PowerPoint PPT Presentation
August 2017 Extraordinary CCC Meeting Springvale Coal Services Operations (SCSO) Western Coal Services (WCS) Lidsdale Siding (LS) www.centennialcoal.com.au Introduction Reporting Period April August 2017 Site Names = SCSO Sites WCS
www.centennialcoal.com.au
Western Coal Services (WCS) Lidsdale Siding (LS)
Reporting Period
Site Names = SCSO Sites
Consents / Project Approvals
daily maximum)
A.
Prepared in consultation with various regulatory and advisory groups
B.
Describe measures to improve riparian habitat of Wangcol Creek 100m downstream of the proposed Link Haul Bridge crossing
C.
Detail additional compensatory water quality and catchment improvements ($250k) prior to commissioning the SWTP
D.
Make long term arrangements to manage and secure A, B, &C above
Consents / Project Approvals
A.
Establish a GW monitoring network across the SCSS that is adequate to provide an understanding of surface water and GW interactions across the site
B.
Design and install run off diversion works to divert all clean catchment runoff from up gradient areas
C.
Investigate options for long term management of LDP06 discharge / beneficial use options
Licenses
All Other Licences and Approvals = No Changes
Summary of Operational Performance – Reporting Period Tonnes Mined
Tonnes Transported
Surface disturbance limited to management and construction works only
Planned Modifications
Follow up actions since last CCC meeting
5
Noise Monitoring Criteria
Noise Monitoring results
Air Monitoring Criteria
Air Monitoring results
Location Date Start Time Period Relevant WCS LAeq impact assessment criteria Criterion LAeq 15min dB WCS Measured LAeq 15min dB Exceedance of impact assessment criterion dB Source of Noise NM7 04/05/17 12:24 Day 37 41 4 Overland Conveyor NM7 04/05/17 21:07 Evening 37 42 5 Overland Conveyor NM4 13/06/17 23:00 Night 36 38 2 Overland Conveyor NM6 13/06/17 16:50 Day 36 40 4 Overland Conveyor NM6 13/06/17 20:14 Evening 36 42 6 Overland Conveyor NM6 14/06/17 00:17 Night 39 44 5 Overland Conveyor NM7 13/06/17 17:33 Day 37 41 4 Overland Conveyor NM7 13/06/17 18:01 Evening 37 41 4 Overland Conveyor NM6 26/07/17 21:07 Evening 36 41 5 Overland Conveyor NM7 26/07/17 21:27 Evening 37 42 5 Overland Conveyor NM7 27/07/17 17:05 Day 37 41 4 Overland Conveyor Location Date Start Time Period Relevant WCS LAeq impact assessment criteria Criterion LA1,1min dB WCS Measured LA1,1min dB Exceedance of impact assessment criterion dB Source of Noise NM6 14/06/17 00:17 Night 45 46 1 Overland Conveyor
Water Monitoring Criteria
Water Monitoring results
Subsidence Monitoring
monitoring and reporting requirements
Cultural Heritage
and Stemlar feeder site with representatives from the Registered Aboriginal Parties undertaken on 03/05/2017.
Rehabilitation
Land Management
WCS
LS
WCS
water management for LDP006 discharge long term solutions
LS
gum management initiatives
WCS
LS
WCS
supporting studies and commitments as outlined in SEE’s and revised consents (on approval)
LS
16
www.centennialcoal.com.au
1. Site Update 2. Operations Summary 3. Environmental Performance 4. Community 5. Upcoming Activities
18
19
Satellite Sites.
2 June. The visiting officers requested work be done to improve sediment and erosion controls at the Ventilation Facility and for maintenance of rehabilitation sites on the Newnes Plateau to be conducted.
The position has been filled by Devon Roberts from 7 July.
control structures.
20
ceased in February 2015.
August.
21
August.
22
23
Dust
Water
limits.
pH of the discharge water at the LDP002 monitoring location. Noise
monitoring on 2 May complied with all Project Approval limits.
Subsidence
Wolgan Swamps in June. No additional cracking identified and some existing cracks appear to filling with sediment.
24
25
Dust (Ivanhoe North)
complied with EPL limits in the period April to July. Water (Ivanhoe North and Ivanhoe No2)
period April to July, and subsequently no sampling was required.
26
27
capping design and structural assessment of the drift structure.
Facility Substation.
28
the Angus Place and Ivanhoe Colliery Annual Reviews (AR) and the Ivanhoe North and Blue Mountains Colliery Annual Environmental Management Reports (AEMR).
the Ivanhoe Colliery AEMR.
www.centennialcoal.com.au
30
31 Modification No. Details of Modification Date of Application /Exhibition Period Status Mod 1 Increase of the approved workforce (including contractors) from 310 full time equivalent (FTE) to 450; Increase in ROM coal production from the approved 4.5 Mtpa to 5.5 Mtpa; and Increase in the existing stockpile capacity at the Springvale pit top from 85,000 tonnes to 200,000 tonnes capacity and an increase in the coal stockpile footprint by 0.3ha northeast of the stockpile area. 23/07/2016 / 02/08/2016 – 23/08/2016 Approved April 2017 Mod 2* To remove the requirement to Meet limits for salinity of 700 (50th percentile), 900 (90th percentile) and 1000 (100th percentile) uS/cm by 30 June 2017; and To defer to 30 June 2019 the requirement to Eliminate acute and chronic toxicity from LDP009 discharges to aquatic species by 30 June 2017, with acute toxicity defined as >10% effect relative to the control group and chronic toxicity defined as >20% effect relative to the control group. 22/12/2016 / 24/01/2017 – 28/02/2017 Approved June 2017
*Mod 2 approval links with the Springvale Water Treatment Plant and Western Coal Services approvals.
Centennial are implementing options to ensure operations are not disrupted.
32
33
Material Approved Limit (and source) YTD July 2017 ROM Coal 5.5 million tonnes per calendar year (Source: SSD_5594 S2 C6) 2,452,456 Transport (road) 50,000 tonnes of ROM Coal per calendar year (Source: SSD_5594 S2 C8) 13,666 t
34
Relevant Approval Condition # Condition summary Comment Actions EPL 3607 L2.4 Water and Land Concentration Limits pH limit exceeded Investigation undertaken Contingency assessment underway EPL 3607 L2.4 Water and Land Concentration Limits EC limit exceeded Implementing UCRAMP EPL 3607 / SSD_5594 L4.4 / S4, C2 Noise Limits Exceedance at S2 receptor in Q2 monitoring Investigation and management options assessment underway
35
Four complaints year to date.
Springvale has completed the following actions in relation to noise management:
Springvale are investigating further opportunities to manage/mitigate noise. Additional actions underway include:
sources at high risk times.
* ROM Haulage ^ Stockpile dozer operations
^
*
^ ^
36
www.centennialcoal.com.au
The output of the research is valuable for reasons including but not limited to:
assessment (SIA) elements of future consent applications for the Western
such as Lithgow, rather than applying state and national level metrics in the assessment;
mining on regional communities such as Lithgow.
43
www.centennialcoal.com.au
45
catchment
Springvale Mine’s consent SSD 5594 (Schedule 4 Condition 12)
the environment
Station (MPPS) cooling water system
Lyell) and other sources (Fish River Scheme) to meet the power station make- up water requirements.
46
water treatment plant (WTP) at MPPS
Creek Reservoir
mine water
management
MPPS bine management system
47
48
49
energy demand:
mines shows an average peak mine inflow of 36 ML/day.
redundancy is incorporated into the project to ensure reliable treatment
MPPS.
extracting water from Lake Lyell and Fish River.
Creek Reservoir for subsequent reuse at MPPS, no discharge of treated water.
50
required in the Springvale Mine’s consent SSD 5594 given nil discharge development
–
The Project allows continued operation of Springvale Mine:
–
will provide a reliable supply of coal to MPPS
–
critical to ensuring secure and reliable electricity supply to NSW 15% - 20%
–
Estimated Capex in excess of $100 Million
–
Creation ~ 25 FTE operational workforce
–
Supports the ongoing viability of existing MPPS and Centennial (Springvale, Angus Place, Western Coal Services) operations and continued employment of >660 FTE personnel. 51
52
53 DUKETON
2.0 Moz RESERVE 5.4 Moz RESOURCE 3 OPERATING MINES
McPHILLAMYS
2.2 Moz RESOURCE
Perth Canberra Sydney
54
1. Mount Piper Power Station (MPPS) – Blow Down Ponds 2. Springvale Coal Services - LDP006 3. Angus Place – LDP001
55
56
57
Angus Place Springvale Coal Services Mount Piper Power Station
3 2 1
To McPhillamys
58
Optional Pipeline
Centennial Coal Services Energy Australia Mount Piper Power Station (MPPS) Centennial Angus Place Newnes Plateau (State Forrest)
Water Transfer Flow Diagram for Regis Mining
Springvale Bore 6, Bore 8, Shaft 3, Angus Place Surface Tanks Angus Place 940 Bore Springvale Water Transfer System New pipeline to MPPS Buffer Dam Buffer Dam New Water Treatment Plant Pre-treatment Coal Services Cooks Dam MPPS Regis Transfer Tank New Water Treatment Plant Reverse Osmosis Power Station Cooling Tower Forebay Backwash residual to Coal Services REA Regis Mining McPhillamys Gold Mine Brine Concentration / Management System Ash/Brine Emplacement Angus Place Regis Transfer Tank Coal Services Regis Transfer Tank Coal Services Runoff from surface and
Coal Services LDP006 Coal Services Coal Prep Plant 13ML/D
Drinking Water Catchment)
–
The Project allows continued operation of Springvale Coal Services and redundancy for new WTP
–
Creation of new gold mine near Blayney and pipeline / pump stations from Lithgow
–
Creation of 200 jobs during construction.
–
Creation of 150 full time jobs
–
Injection of approx $80m per annum into local community 59
60
www.centennialcoal.com.au
61
Project from Springvale Mine from the approved 4.5 Mtpa to up to 5.5 Mtpa on the overland conveyor
capacity in the vicinity of the coal preparation plant
FTE personnel
Condition 9) to the Project components.
62
at Springvale Coal Services Site over a two year period
at Lidsdale
Services Site and the private Haul roads
to manage noise, especially under adverse weather conditions
63
64
Wallerawang Haul Road Mt Piper Haul Road Overland Conveyor
65
66
67
68
69
70
71
72