August 12, 2019 1:30 pm McLeod County North Complex Redetermination - - PowerPoint PPT Presentation

august 12 2019 1 30 pm mcleod county north complex
SMART_READER_LITE
LIVE PREVIEW

August 12, 2019 1:30 pm McLeod County North Complex Redetermination - - PowerPoint PPT Presentation

COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65 August 12, 2019 1:30 pm McLeod County North Complex Redetermination Background JD 18 SM completed redetermination in November of 2016 Concerns with Outlet fee


slide-1
SLIDE 1

COMBINED DITCH MEETING

JD 18 SM JD 17 MS JD 32 SM Sibley CD 65

August 12, 2019 1:30 pm McLeod County North Complex

slide-2
SLIDE 2

Redetermination

  • Background
  • JD 18 SM completed redetermination in November of 2016
  • Concerns with
  • Outlet fee for JD 17 MS, paying over 9% of the benefits
  • Watershed boundaries do not match up to those previously

redetermined

  • CD 65 boundary was extended to include portions of JD 18 SM
  • Redetermination stays in effect until

another redetermination is complete

  • Total cost of the project was $1,033,395.89
  • Cost less seeding and damages was

$92,167.32

slide-3
SLIDE 3

Redetermination

  • Proposed
  • Do a redetermination on JD 18 SM, JD 17 MS, JD 32 SM, Sibley CD 65
  • Upon completion they are combined into 1 large system
slide-4
SLIDE 4

Redetermination

Including:

  • Process
  • Cost
  • Timeframe
slide-5
SLIDE 5

Redetermination

RECAP:

  • Eliminates current outlet fees
  • All 4 ditch systems, big or small, pay for the maintenance of the others
  • All acres are part of the system and watershed boundaries become

seamless

  • CD65 and JD 18 SM boundary would no longer be an issue
  • Need to pay for the redetermination again
  • Drainage authority would be realigned to reflect the new benefit

percentages

  • All expenses incurred up until ROB is final are spread on current benefits
  • Current debt on JD 18 SM is $647,637.50
slide-6
SLIDE 6

Repair Projects

Culvert Locations

slide-7
SLIDE 7

Repair Projects

Repair 18-176 256th Lane Crossing

slide-8
SLIDE 8

Repair Projects

Repair 18-163 Heinz

slide-9
SLIDE 9

Repair Projects

Repair 18-081 Frauendienst

slide-10
SLIDE 10

Repair Projects

slide-11
SLIDE 11

Repair Projects

slide-12
SLIDE 12

Repair Projects

slide-13
SLIDE 13

Repair Projects

slide-14
SLIDE 14

Repair Projects

Contractor with lowest responsible bid: Wuetherich Drainage, Brian Wuetherich Sibley County culvert pieces have been delivered to the Gaylord area and are being assembled. Cost of pieces for 3 culverts: $49,551.000

slide-15
SLIDE 15

256th Lane Crossing

  • Significant flooding most springs
  • Impacts farm land upstream from

culvert

  • Impacts farm land downstream

from culvert

  • Impacts drivability of driveway east
  • f 256th Lane
slide-16
SLIDE 16

256th Lane Crossing

March 20, 2019- looking east down 256th Lane

slide-17
SLIDE 17

256th Lane Crossing

March 20, 2019- looking NW into submerged ditch

slide-18
SLIDE 18

256th Lane Crossing

March 22, 2019- looking south of 256th Lane

slide-19
SLIDE 19

256th Lane Crossing

March 22, 2019- looking east down 256th Lane

slide-20
SLIDE 20

256th Lane Crossing

March 22, 2019- looking NW into submerged ditch

slide-21
SLIDE 21

256th Lane Crossing

May 28, 2019- looking west along 256th Lane

slide-22
SLIDE 22

256th Lane Crossing

  • Solutions
  • Fix current 256th Lane
  • Reroute the driveway
slide-23
SLIDE 23

256th Lane Crossing

  • Fix current 256th Lane
  • 3 options from ISG Culvert Analysis, 2019

Option 1:

  • Install a 10’ x 8’ dual box culvert
  • Pros:
  • Increase the capacity of the crossing
  • Lower the peak flood elevations upstream of the crossing by up to 3’
  • Will protect the culvert which currently only has .89’ of cover
  • Total width of channel at culvert will be 22.5’ (currently 20’)
  • Cons:
  • Will not effect frequency of the road overtopping
  • Will overtop the road with any 25 year rain event
  • Cost: $152,840
slide-24
SLIDE 24

256th Lane Crossing

  • Fix current 256th Lane
  • 3 options from ISG Culvert Analysis, 2019

Option 2:

  • Leave existing culvert
  • Pros:
  • Culvert is in good condition
  • Cons:
  • Will continue to flood
slide-25
SLIDE 25

256th Lane Crossing

  • Fix current 256th Lane
  • 3 options from ISG Culvert Analysis, 2019

Option 3:

  • Raise the road 2 feet from elevation of 988 to 990 & install box culvert
  • Pros:
  • Increase the capacity of the crossing
  • Lower the peak flood elevations upstream of the crossing by up to 3’
  • Will protect the culvert which currently only has .89’ of cover
  • Total width of channel at culvert will be 22.5’ (currently 20’)
  • The lowest spot is the driveway is 300’ east of the culvert location, so

building it up would prevent further flooding

  • Cons:
  • Will overtop the road with any 50 year rain event
  • Cost: $176,675
slide-26
SLIDE 26
  • Reroute the driveway
  • Pros:
  • Increase the capacity of

the crossing

  • Lower the peak flood

elevations upstream of the crossing by up to 3’

  • The lowest spot is the

driveway is 300’ east of the culvert location, so building it up would prevent further flooding

  • Cons:
  • Will overtop the road with

any 50 year rain event

  • Cost: $60,000 minimum for

construction

  • Maintain it perpetually

256th Lane Crossing

1895

slide-27
SLIDE 27
  • Aaron met with Ryan from the Dept of Homeland

Security & Emergency Management in May

  • Photos and hydraulic analysis have been sent to

FEMA

  • FEMA hopes to be out as early as September to take

a look at the damage/repairs

  • Improvements typically aren’t allowed unless it is

more cost effective

FEMA

slide-28
SLIDE 28

Delta Feasibility Study

slide-29
SLIDE 29

Two-Tier Ditches

slide-30
SLIDE 30

Bonding

Remaining principal & interest balance of debt: JD 18 SM – Redetermination: $234,150 (5 year, final payment 2/1/2023) Cleanout: $413,487.50 (20 year, final payment 2/1/2038) JD 32 SM – Improvement: $95,637.50 Call date: February 1, 2025 Bond defeasance is only option prior to this date, but fees/penalties

slide-31
SLIDE 31

Bonding

Future Bonding: Based on: $100,000 for redetermination $500,000 for culvert repairs $600,000 5 years at 1.5% up to 20 years at 2.25% Reimbursement Resolution: Look back 60 days from the date of the resolution & 18 months forward

slide-32
SLIDE 32

COMBINED DITCH MEETING

JD 18 SM JD 17 MS JD 32 SM Sibley CD 65

August 12, 2019 1:30 pm McLeod County North Complex