SLIDE 1 COMBINED DITCH MEETING
JD 18 SM JD 17 MS JD 32 SM Sibley CD 65
August 12, 2019 1:30 pm McLeod County North Complex
SLIDE 2 Redetermination
- Background
- JD 18 SM completed redetermination in November of 2016
- Concerns with
- Outlet fee for JD 17 MS, paying over 9% of the benefits
- Watershed boundaries do not match up to those previously
redetermined
- CD 65 boundary was extended to include portions of JD 18 SM
- Redetermination stays in effect until
another redetermination is complete
- Total cost of the project was $1,033,395.89
- Cost less seeding and damages was
$92,167.32
SLIDE 3 Redetermination
- Proposed
- Do a redetermination on JD 18 SM, JD 17 MS, JD 32 SM, Sibley CD 65
- Upon completion they are combined into 1 large system
SLIDE 4 Redetermination
Including:
SLIDE 5 Redetermination
RECAP:
- Eliminates current outlet fees
- All 4 ditch systems, big or small, pay for the maintenance of the others
- All acres are part of the system and watershed boundaries become
seamless
- CD65 and JD 18 SM boundary would no longer be an issue
- Need to pay for the redetermination again
- Drainage authority would be realigned to reflect the new benefit
percentages
- All expenses incurred up until ROB is final are spread on current benefits
- Current debt on JD 18 SM is $647,637.50
SLIDE 6
Repair Projects
Culvert Locations
SLIDE 7 Repair Projects
Repair 18-176 256th Lane Crossing
SLIDE 8 Repair Projects
Repair 18-163 Heinz
SLIDE 9 Repair Projects
Repair 18-081 Frauendienst
SLIDE 10
Repair Projects
SLIDE 11
Repair Projects
SLIDE 12
Repair Projects
SLIDE 13
Repair Projects
SLIDE 14 Repair Projects
Contractor with lowest responsible bid: Wuetherich Drainage, Brian Wuetherich Sibley County culvert pieces have been delivered to the Gaylord area and are being assembled. Cost of pieces for 3 culverts: $49,551.000
SLIDE 15 256th Lane Crossing
- Significant flooding most springs
- Impacts farm land upstream from
culvert
- Impacts farm land downstream
from culvert
- Impacts drivability of driveway east
- f 256th Lane
SLIDE 16 256th Lane Crossing
March 20, 2019- looking east down 256th Lane
SLIDE 17 256th Lane Crossing
March 20, 2019- looking NW into submerged ditch
SLIDE 18 256th Lane Crossing
March 22, 2019- looking south of 256th Lane
SLIDE 19 256th Lane Crossing
March 22, 2019- looking east down 256th Lane
SLIDE 20 256th Lane Crossing
March 22, 2019- looking NW into submerged ditch
SLIDE 21 256th Lane Crossing
May 28, 2019- looking west along 256th Lane
SLIDE 22 256th Lane Crossing
- Solutions
- Fix current 256th Lane
- Reroute the driveway
SLIDE 23 256th Lane Crossing
- Fix current 256th Lane
- 3 options from ISG Culvert Analysis, 2019
Option 1:
- Install a 10’ x 8’ dual box culvert
- Pros:
- Increase the capacity of the crossing
- Lower the peak flood elevations upstream of the crossing by up to 3’
- Will protect the culvert which currently only has .89’ of cover
- Total width of channel at culvert will be 22.5’ (currently 20’)
- Cons:
- Will not effect frequency of the road overtopping
- Will overtop the road with any 25 year rain event
- Cost: $152,840
SLIDE 24 256th Lane Crossing
- Fix current 256th Lane
- 3 options from ISG Culvert Analysis, 2019
Option 2:
- Leave existing culvert
- Pros:
- Culvert is in good condition
- Cons:
- Will continue to flood
SLIDE 25 256th Lane Crossing
- Fix current 256th Lane
- 3 options from ISG Culvert Analysis, 2019
Option 3:
- Raise the road 2 feet from elevation of 988 to 990 & install box culvert
- Pros:
- Increase the capacity of the crossing
- Lower the peak flood elevations upstream of the crossing by up to 3’
- Will protect the culvert which currently only has .89’ of cover
- Total width of channel at culvert will be 22.5’ (currently 20’)
- The lowest spot is the driveway is 300’ east of the culvert location, so
building it up would prevent further flooding
- Cons:
- Will overtop the road with any 50 year rain event
- Cost: $176,675
SLIDE 26
- Reroute the driveway
- Pros:
- Increase the capacity of
the crossing
elevations upstream of the crossing by up to 3’
driveway is 300’ east of the culvert location, so building it up would prevent further flooding
- Cons:
- Will overtop the road with
any 50 year rain event
- Cost: $60,000 minimum for
construction
256th Lane Crossing
1895
SLIDE 27
- Aaron met with Ryan from the Dept of Homeland
Security & Emergency Management in May
- Photos and hydraulic analysis have been sent to
FEMA
- FEMA hopes to be out as early as September to take
a look at the damage/repairs
- Improvements typically aren’t allowed unless it is
more cost effective
FEMA
SLIDE 28
Delta Feasibility Study
SLIDE 29
Two-Tier Ditches
SLIDE 30
Bonding
Remaining principal & interest balance of debt: JD 18 SM – Redetermination: $234,150 (5 year, final payment 2/1/2023) Cleanout: $413,487.50 (20 year, final payment 2/1/2038) JD 32 SM – Improvement: $95,637.50 Call date: February 1, 2025 Bond defeasance is only option prior to this date, but fees/penalties
SLIDE 31
Bonding
Future Bonding: Based on: $100,000 for redetermination $500,000 for culvert repairs $600,000 5 years at 1.5% up to 20 years at 2.25% Reimbursement Resolution: Look back 60 days from the date of the resolution & 18 months forward
SLIDE 32 COMBINED DITCH MEETING
JD 18 SM JD 17 MS JD 32 SM Sibley CD 65
August 12, 2019 1:30 pm McLeod County North Complex