proto
Update on Trial Assembly at Ash River
William Miller from the couch Assembly Team doing all the work March 1st, 2017v2
at Ash River William Miller from the couch Assembly Team doing all - - PowerPoint PPT Presentation
Update on Trial Assembly at Ash River William Miller from the couch Assembly Team doing all the work March 1st, 2017v2 proto Cable Update We are starting to make some process on cable management and location of cable trays Matt has
William Miller from the couch Assembly Team doing all the work March 1st, 2017v2
We are starting to make some process on cable management and location of cable trays
CE cables-We have enough “misc.” cables to mock up the
proper cable, so we could purchase it but we have to buy a 1000’ roll ($1100) so we are just going to use free CAT6 cable but constrain it in a way that uses the same bend radius
design information
March 1st, 2017 2
March 1st, 2017 3
6m 7m
March 1st, 2017 4
PD cable feedthrough Signal flange and warm interface crate The bottom cover plate has many slots to capture the cable bundles Can the cables be pre- installed onto the bottom cover plate in the clean room?
March 1st, 2017 5
from Cold Electronics cables as much as possible
installed second and must be routed over or thru front of cable tray
cable tray and the feed-thru “umbilical” exits from the middle of the APA.
cables are pre-attached so the entire cable would also be replaced
March 1st, 2017 6
March 1st, 2017 7
Tray mounted to APA. “Differential” length is stored here. Tray mounted to I –beam. Length contingency is stored here. Also allows for APA plane to translate to the right 20cm on Bridge Beam E Only service length is stored in feed thru Cable tray can be used here to bridge to the feedthru
March 1st, 2017 8
Differential length stored in u-turns Length contingency stored in u-turn
March 1st, 2017 9
Cable supported
Cable tray on I-beam Cable Feed-Thru
DSS Support Manhong is going to start producing some drawings that showing cable lengths and distances to help in the mock-up
We have a slightly different APA head tube than the final design
March 1st, 2017 10
40mm 104mm
We need to confirm that the total of 219mm from the bottom of the SS beam to the top of the electronics Box is correct we seem to have more room
March 1st, 2017 11
62mm 115mm
March 1st, 2017 12
117mm 130mm
March 1st, 2017 13
lower field cable resistor chain to the FC termination board mounted on the top if the APA should be run when the PD cables are run. They need to be isolated from the PD cables
cables that also run from the CE boxes back to the feed
understand where they run
connectors