Another 4 months gone Estate Works The Breheny Contract Update Lighting There has been a delay with street lighting. Temporary street lighting has been provided until permanent lights are installed. Works due to commence in


slide-1
SLIDE 1
slide-2
SLIDE 2

Another 4 months gone…

slide-3
SLIDE 3

Estate Works – The Breheny Contract Update

slide-4
SLIDE 4

Lighting…

There has been a delay with street

  • lighting. Temporary

street lighting has been provided until permanent lights are

  • installed. Works due

to commence in December.

slide-5
SLIDE 5

Manholes Gully Grates Central Reservation Raised Junctions & Crossovers

CCTV Survey for U&C Road Drainage

Progress of contract…

Survey ongoing, discovery of silt and rubble has delayed progress. Survey has highlighted additional works such as cracked pipes which have required

  • replacing. 90% of the CCTV is now

complete. Close to completion. Main roads such as London and Kestrel are finished, final few such as Park View to complete. IWNL to then inspect and adopt. These are complete apart from moving some individual grates on Holdenby. These works will see the installation of raised landscaped areas on London Road. Majority of crossovers are complete – example of these can be seen London

  • Road. Breheny are yet to complete

additional crossovers on London and Kestrel Road. These will be complete when housebuilder construction is reduced.

slide-6
SLIDE 6

Progress of contract…

Highway Repairs

Near completion – awaiting inspection from NCC to understand if any more works need to take place.

Final Footpath/Cycle Way Surfacing

Near completion – this is complete up to date and awaiting street lighting to be installed. Housebuilders to complete their own internal roads/footpaths.

Final Road Surfacing

Kestrel Road is the only area that is yet to be completed – this was due to a drainage issue which caused delays . The repair works are due to complete before Christmas, with final surfacing in the New Year.

Road Markings & Signage

We are awaiting sign off from NCC for the road markings and signage – part of the section 38 agreement.

slide-7
SLIDE 7

Progress of contract…

slide-8
SLIDE 8

Overview…

£1.24 million spent so far

  • Completion in early

2019

  • 127 variations on
  • riginal contract

Additional £500,000 spend on top of original budget

slide-9
SLIDE 9

Earth works are being completed on site by Buckingham; Area 1 – Under investigation. Area 2 – Completion in January. Area 3 - Work will be finished early December. For Area 4/5 – this will be complete by the end of November. Things we have been working on…

slide-10
SLIDE 10

The application for landscape design was granted 31st October for the County Wildlife

  • Zone. The works will

commence in early December and last 15 weeks.

Things we have been working on…

slide-11
SLIDE 11

Things we have been working on…

  • 40,000 shrubs, trees & hedges
  • 350 specimen trees 3m – 5m
  • 84 along Kestrel Road
  • 100,000 bulbs planted within the next year
  • 60,000m² grass to be planted
  • Over £500,000 spend
  • 20,000m² wildflower planted
slide-12
SLIDE 12

Things we have been working on…

Planning application submitted for Play Areas on the 4th

  • October. 5 of the LEAPS

& NEAPS were given consent on the 31st October and contracts are out for signature. Final LEAP & NEAP should receive planning before Christmas.

slide-13
SLIDE 13

Application granted for Café & Offices

Things we have been working on… Work to start in November to complete May 2019.

slide-14
SLIDE 14

Application for new changing rooms has been approved.

Things we have been working on…

slide-15
SLIDE 15
  • Agreed terms with Food store & Nursery Operator
  • Currently designing the district centre for application later this year

Things we have been working on…

slide-16
SLIDE 16

Completed the survey & management plan of the Roman Villa. This will include fencing the villa area to protect the

  • monument. There will also

be additional planting and natural footpaths created through a mowing regime.

Things we have been working on…

slide-17
SLIDE 17

localliason@materialchange.com

Material Change

slide-18
SLIDE 18

On to the next four months…

Planning

  • n

Zones 2 & 3

  • Completion of the

Breheny contract

  • Build starting on café &

Offices as well as the Changing Facilities

  • Work up application and

design for District Centre

  • Continue earth works
  • Implement Roman Villa

plans

slide-19
SLIDE 19
slide-20
SLIDE 20

www.urbanandcivic.com

Keep Talking… & thank you for listening.