Another 4 months gone Estate Works The Breheny Contract Update Lighting There has been a delay with street lighting. Temporary street lighting has been provided until permanent lights are installed. Works due to commence in
Another 4 months gone…
Estate Works – The Breheny Contract Update
Lighting…
There has been a delay with street
- lighting. Temporary
street lighting has been provided until permanent lights are
- installed. Works due
to commence in December.
Manholes Gully Grates Central Reservation Raised Junctions & Crossovers
CCTV Survey for U&C Road Drainage
Progress of contract…
Survey ongoing, discovery of silt and rubble has delayed progress. Survey has highlighted additional works such as cracked pipes which have required
- replacing. 90% of the CCTV is now
complete. Close to completion. Main roads such as London and Kestrel are finished, final few such as Park View to complete. IWNL to then inspect and adopt. These are complete apart from moving some individual grates on Holdenby. These works will see the installation of raised landscaped areas on London Road. Majority of crossovers are complete – example of these can be seen London
- Road. Breheny are yet to complete
additional crossovers on London and Kestrel Road. These will be complete when housebuilder construction is reduced.
Progress of contract…
Highway Repairs
Near completion – awaiting inspection from NCC to understand if any more works need to take place.
Final Footpath/Cycle Way Surfacing
Near completion – this is complete up to date and awaiting street lighting to be installed. Housebuilders to complete their own internal roads/footpaths.
Final Road Surfacing
Kestrel Road is the only area that is yet to be completed – this was due to a drainage issue which caused delays . The repair works are due to complete before Christmas, with final surfacing in the New Year.
Road Markings & Signage
We are awaiting sign off from NCC for the road markings and signage – part of the section 38 agreement.
Progress of contract…
Overview…
£1.24 million spent so far
- Completion in early
2019
- 127 variations on
- riginal contract
Additional £500,000 spend on top of original budget
Earth works are being completed on site by Buckingham; Area 1 – Under investigation. Area 2 – Completion in January. Area 3 - Work will be finished early December. For Area 4/5 – this will be complete by the end of November. Things we have been working on…
The application for landscape design was granted 31st October for the County Wildlife
- Zone. The works will
commence in early December and last 15 weeks.
Things we have been working on…
Things we have been working on…
- 40,000 shrubs, trees & hedges
- 350 specimen trees 3m – 5m
- 84 along Kestrel Road
- 100,000 bulbs planted within the next year
- 60,000m² grass to be planted
- Over £500,000 spend
- 20,000m² wildflower planted
Things we have been working on…
Planning application submitted for Play Areas on the 4th
- October. 5 of the LEAPS
& NEAPS were given consent on the 31st October and contracts are out for signature. Final LEAP & NEAP should receive planning before Christmas.
Application granted for Café & Offices
Things we have been working on… Work to start in November to complete May 2019.
Application for new changing rooms has been approved.
Things we have been working on…
- Agreed terms with Food store & Nursery Operator
- Currently designing the district centre for application later this year
Things we have been working on…
Completed the survey & management plan of the Roman Villa. This will include fencing the villa area to protect the
- monument. There will also
be additional planting and natural footpaths created through a mowing regime.
Things we have been working on…
localliason@materialchange.com
Material Change
On to the next four months…
Planning
- n
Zones 2 & 3
- Completion of the
Breheny contract
- Build starting on café &
Offices as well as the Changing Facilities
- Work up application and
design for District Centre
- Continue earth works
- Implement Roman Villa
plans
www.urbanandcivic.com
Keep Talking… & thank you for listening.
Becky O’Brien