Andy Stefanik and Ang Lee Fermilab stefanik@fnal.gov, alee@fnal.gov - - PowerPoint PPT Presentation

andy stefanik and ang lee fermilab stefanik fnal gov alee
SMART_READER_LITE
LIVE PREVIEW

Andy Stefanik and Ang Lee Fermilab stefanik@fnal.gov, alee@fnal.gov - - PowerPoint PPT Presentation

The L ong- B aseline N eutrino E xperiment Project LBNE Target Pile & Decay Pipe Cooling Andy Stefanik and Ang Lee Fermilab stefanik@fnal.gov, alee@fnal.gov September 25, 2014 Outline Air cooling schematic Decay pipe airflow


slide-1
SLIDE 1

The Long-Baseline Neutrino Experiment Project

LBNE Target Pile & Decay Pipe Cooling

Andy Stefanik and Ang Lee – Fermilab stefanik@fnal.gov, alee@fnal.gov September 25, 2014

slide-2
SLIDE 2

Outline

2 2

  • Air cooling schematic
  • Decay pipe airflow passages
  • Target pile airflow passages
  • Target pile chase cooling panels (water-cooled)
  • Heat loads and cooling parameters
  • LBNE Facility Lifetime
  • Energy and temperature distributions

– Decay pipe – Target pile chase cooling panels – Target pile bulk shielding (Not available)

  • Air pressure drops
  • Corrosion

LBNE Target Pile and Decay Pipe 2

slide-3
SLIDE 3

*

Target pile and decay pipe cooling air schematic

NOTE: The chase cooling panels are cooled with water.

3 3

Beam Target pile Decay Pipe air handler, 35,000 scfm

Steel shielding for labyrinth.

Target Pile air handler, 35,000 scfm Helium-filled Decay Pipe Concrete shielding Shielding

20 cm annular gap 20 cm annular gap

Concrete shielding

4 – 28”φ cooling air supply pipes

Upstream thin window

32 cooling pipes total Vent to atmosphere

Clean cooling air supply: 950 scfm

Downstream window

Steel

LBNE Target Pile and Decay Pipe

NOTE: The target pile air cooling system and the decay pipe air cooling system are two separate systems.

Chase cooling panels Chase cooling panels Water-proof barrier (Geomembrane) 3 * Helium purge and fill connections *

slide-4
SLIDE 4

Decay pipe airflow passages

4 4

  • LBNE Target Pile and Decay Pipe

4 – 28”φ cooling air supply pipes Cooling air returns in the annular gap of the double-wall decay pipe. Concrete shielding

Helium-filled Decay Pipe

32 clean cooling air

  • pipes. 950 scfm

airflow total. Water-proof barrier (Geomembrane)

4

slide-5
SLIDE 5

Target pile airflow passages

5 5 LBNE Target Pile and Decay Pipe

  • Cooling air inlet duct

(Radiation labyrinth) Cooling air outlet duct (Radiation labyrinth)

5

slide-6
SLIDE 6

Target pile airflow passages

6 6 LBNE Target Pile and Decay Pipe

  • Steel shielding is solid cross-

hatching.

  • Top supply airflow. Flow is

downstream to upstream. The air flows through T-blocks and

  • ther shielding blocks into the

chase.

  • “Air block” sheet metal

separates supply and return airflows.

  • Side and bottom supply
  • airflows. Flow is downstream

to upstream. Some air flows through the spaces in the bulk steel shielding.

  • Chase return airflow. Flow is

upstream to downstream. Some air flows through the spaces in the bulk steel shielding.

Chase cooling panels 6

slide-7
SLIDE 7

NuMI Target Pile

7 7

  • The air block sheet metal

in the NuMI target pile is installed in the bulk shielding.

  • Air block material is 304L

stainless steel.

  • The sheets are welded

together with continuous welds.

LBNE Target Pile and Decay Pipe 7

slide-8
SLIDE 8

Target pile chase cooling panels (water-cooled)

8 8

  • LBNE Target Pile and Decay Pipe

CROSS SECTION AT HORN 1 5 m high

The chase cooling panels are 100 mm (4”) thick steel plates.

8

slide-9
SLIDE 9

Target pile chase cooling panels (water-cooled)

9 9

  • 2D: Iso-view (1/2 model): Internal water passages:

LBNE Target Pile and Decay Pipe

5 side panels 5 bottom panels ½ width

9

Radiation Labyrinth with module

slide-10
SLIDE 10

Target pile chase cooling panels (water-cooled)

10 10

  • Side panel dimensions: 1,219 mm length along the

beamline x 5,050 mm height (48” length x 199” height); 100 mm (4”) thick.

  • Bottom panel dimensions: 1,219 mm length along the

beamline x 1,371 mm width (48” length x 54” width); 100 mm (4”) thick.

  • The chase cooling panels are low carbon steel plates.

LBNE Target Pile and Decay Pipe 10

slide-11
SLIDE 11

Heat loads and cooling parameters for 2.3 MW

11 11

  • Annular decay pipe: MARS energy deposition is 700 kW.

– Inner pipe: 360 kW MARS energy deposition – Outer pipe: 100 kW MARS energy deposition – Shielding concrete: 240 kW MARS energy deposition – Air flow rate: 35,000 scfm (71,440 kg/hour) in decay pipe – Heat load: 834 kW (1.2 multiplier on MARS energy deposition) – Air supply temperature: 15 °C (59 °F) – Air return temperature: 57 °C (135 °F) – Air flow rate: 950 scfm (1,940 kg /hour) by geomembranes – Heat load: 6 kW (1.2 multiplier on MARS energy deposition) – Air supply temperature: 15 °C (59 °F) – Air return temperature: 26 °C (79 °F)

LBNE Target Pile and Decay Pipe 11

slide-12
SLIDE 12

Heat loads and cooling parameters for 2.3 MW

12 12

  • Target pile: MARS energy deposition is 525 kW.

– Chase cooling panels: 317 kW MARS energy deposition – Bulk steel shielding: 208 kW MARS energy deposition – Air flow rate: 35,000 scfm (71,440 kg/hour) – Heat load: 250 kW (1.2 multiplier on MARS energy deposition) – Air supply temperature: 15 °C (59 °F) – Air return temperature: 27.5 °C (81.5 °F) – Water flow rate: 290 gpm (66 m^3/hour) – Heat load: 380 kW (1.2 multiplier on MARS energy deposition) – Water supply temperature: 38 °C (100 °F) – Water return temperature: 43 °C (109 °F)

LBNE Target Pile and Decay Pipe 12

slide-13
SLIDE 13

LBNE Facility Lifetime

13 13

  • Lifetime required for the facility and the waterproof barrier is 50

years:

– 5 years operating at 1.2 MW – 15 years operating at 2.4 MW – 10 years for construction, upgrades and maintenance

  • Sub-total = 30 years for the Operating Lifetime

– 10 years for activation cool-down

  • The facility is ready for demolition after the cool-down period.

– Allow 10 years to plan and complete demolition. – Facility Lifetime requirement is 30 + 10 + 10 = 50 years. – NOTE: The waterproof barrier must have a lifetime of at least 50 years so it is intact when concrete demolition starts. The concrete will have a sizable tritium inventory 20 years after the 30-year operating lifetime is over and the waterproof barriers will still be needed to prevent water from wetting undisturbed concrete during demolition.

LBNE Target Pile and Decay Pipe 13

slide-14
SLIDE 14

LBNE Facility Lifetime

14 14

  • Waterproof barrier (geomembrane) strength half-life is a

function of operating temperature:

– Detailed information only available for HDPE (Courtesy of Ed Kavazanjian - Consultant):

  • Geomembrane “strength half-life” from Rowe (2005)

130 yrs @ 35oC continuous 80 yrs @ 40oC continuous 35 yrs @ 50oC continuous

  • Based on the facility lifetime requirement of 50 years, we

select a geomembrane strength half-life of 80 years and specify 40 to 45 °C as the maximum operating temperature range for the waterproof barrier. Waterproof barrier temperature will slightly exceed 40 °C during the 15 years of 2.4 MW operation but will be much less than 40 °C when the particle beam is off so we believe we will be very close to achieving the 80-year strength half-life.

LBNE Target Pile and Decay Pipe 14

slide-15
SLIDE 15

Energy distribution – Decay pipe

15 15

  • Energy distribution at 2.3 MW

LBNE Target Pile and Decay Pipe

2.3 MW

15

0.00E+00 2.00E-08 4.00E-08 6.00E-08 8.00E-08 1.00E-07 1.20E-07 1.40E-07 1.60E-07 50 100 150 200 250 EDEP(Gev/g) distance (m)

EDEP VS THE Z_ beam direction

  • uter steel liner

inner_steel decay pipe

Decay pipe Steel liner

The peak occurs

between Z=~50(m)

slide-16
SLIDE 16

Energy distribution – Decay pipe

16 16

  • Energy distribution at 2.3 MW

LBNE Target Pile and Decay Pipe

2.3 MW

16

0.00E+00 2.00E-09 4.00E-09 6.00E-09 8.00E-09 1.00E-08 1.20E-08 50 100 150 200 250 EDEP (Gev/g) distance (m)

EDEP VS Z for the Concrete section

C_1 C_2 C_3

For R=2.2254 m -2.4754 m section_ closer to the center

For R=2.4754 – 2.7254 m section

Further away from center, EDEP decays quickly Note: Similar as decay pipe and steel liner, the maximum

  • ccurs at Z=~50 m
slide-17
SLIDE 17

Temperature distributions – Decay pipe

17 17 LBNE Target Pile and Decay Pipe

Case 74 pipes (base line) Case_1

32 pipes Case_1a

Maximum steel decay pipe temperature (C) 89.118 89.118

Maximum annulus steel liner temperature (C)

76.623 76.803

Maximum Concrete Temperature C

94.164 94.778

Maximum temperature (Geomembrane _ inboard)

41.795 41.93

2.3 MW

17

slide-18
SLIDE 18

Temperature distributions – Decay pipe

18 18

  • Water-proof barrier (geomembrane) temperatures:

LBNE Target Pile and Decay Pipe

2.3 MW

18

slide-19
SLIDE 19

Energy distribution – Target pile chase cooling panels

19 19

  • Energy distribution at 2.3 MW

LBNE Target Pile and Decay Pipe

5 panels at horn 1 3 panels at horn 2

19

slide-20
SLIDE 20

Temperature distributions – Target pile chase cooling panels

20 20

  • Eight cooling passages in each side panel, 8 tube

passes on each bottom panel, 38 °C (100 °F) cooling water supply temperature, 2.3 MW:

LBNE Target Pile and Decay Pipe 20

slide-21
SLIDE 21

Air pressure loss – Decay pipe

21 21

  • Air flow rate for the decay pipe: 35,000 scfm (71,440

kg/hour)

– ΔP = 2,500 Pa (10 “WC) for the 4 supply lines and the decay pipe annulus.

  • Air flow rate out by the geomembranes: 950 scfm

(16,330 kg /hour)

– ΔP = 625 Pa (2.5 “WC) for the 32, 76.2 mm (3”) inside diameter pipes.

LBNE Target Pile and Decay Pipe 21

slide-22
SLIDE 22

Air pressure loss example – NuMI target pile

22 22

  • NuMI: ΔP = 746 Pa (3” WC) for only the target pile, not

including the air ducts and filters. I expect the same pressure loss for LBNE.

LBNE Target Pile and Decay Pipe 22

ΔP

slide-23
SLIDE 23

Corrosion

  • Design life for beam related corrosion is 20 years. (5

years at 1.2 MW plus 15 years at 2.4 MW.)

  • LBNE will receive 27.3 MW-years in its operating

lifetime.

  • NuMI has received 1 MW-year so far.
  • If moist air is used to cool the LBNE target pile and

decay pipe, the primary corrosive issues are:

– Moisture (non-beam related corrosion) – Nitric acid, HNO3 (beam related corrosion) – Ozone, O3 (beam related corrosion) – Stress corrosion cracking/hydrogen embrittlement of high strength low alloy steel (beam related corrosion)

  • We will eliminate the last issue by not using high

strength low alloy steels.

LBNE Target Pile and Decay Pipe 23

slide-24
SLIDE 24

Corrosion

  • We will control some corrosion by drying the air. Relative

humidity for the cooling air supply is currently required to be less than or equal to 10%.

  • For comparison, the relative humidity in the NuMI target

pile for the cooling air supply is 20%. The cooling air return is in the 30% to 50% range.

  • With dry cooling air the primary corrosive agents in the

LBNE target pile and decay pipe are:

– Ozone, O3 (beam related corrosion). – NxOx (beam related corrosion)

  • Of these two, ozone is the dominate corrosive agent.

LBNE Target Pile and Decay Pipe 24

slide-25
SLIDE 25

Corrosion

  • Our plan to study ozone and NxOx corrosion:

– Consult with HEP facilities. – Conduct literature search. – Work with corrosion consultants. We are working with a consultant now and might do so again in the future. – Develop a mathematical model to predict the formation of corrosive agents when the beam interacts with the cooling airflow. – Test the mathematical model by measuring concentrations of corrosive agents in the NuMI target pile. We have started installing sample tubing in the target pile and will be purchasing instruments in the near future. – Expose metal samples to the high radiation and the corrosive environment in the NuMI target pile. The material samples include: aluminum, carbon steel, stainless steel, anodized aluminum, the heat affected zone (HAZ) of welded joints, and weld material.

LBNE Target Pile and Decay Pipe 25

slide-26
SLIDE 26

Corrosion

  • Our plan to study ozone and NxOx corrosion (continued):

– If necessary, run tests to determine quantitative ozone corrosion rates (uniform and pitting) at concentrations and temperatures expected in the LBNE target pile for base metals, the heat affected zone (HAZ) of welded joints, and the weld material.

  • Corrosion is most critical for components made with thin

materials because function can be lost or impaired when the material corrodes through. An important example is the decay pipe.

  • We can eliminate oxygen related corrosion in most of the

decay pipe by cooling it with dry nitrogen gas instead air.

LBNE Target Pile and Decay Pipe 26

slide-27
SLIDE 27

*

Target pile and decay pipe cooling air schematic

NOTE: The chase cooling panels are cooled with water.

27 27

Beam Target pile Decay Pipe air handler, 35,000 scfm

Steel shielding for labyrinth.

Target Pile air handler, 35,000 scfm Helium-filled Decay Pipe Concrete shielding Shielding

20 cm annular gap 20 cm annular gap

Concrete shielding

4 – 28”φ cooling air supply pipes

Upstream thin window

32 cooling pipes total Vent to atmosphere

Clean cooling air supply: 950 scfm

Downstream window

Steel

LBNE Target Pile and Decay Pipe

NOTE: The target pile air cooling system and the decay pipe air cooling system are two separate systems.

Chase cooling panels Chase cooling panels Water-proof barrier (Geomembrane) 27 * Helium purge and fill connections *

slide-28
SLIDE 28

Corrosion

  • Sample basket in the NuMI target pile. It gets installed in

the chase by the horns.

LBNE Target Pile and Decay Pipe 28

slide-29
SLIDE 29

Conclusion

  • We have reviewed the preliminary decay pipe design.
  • We have more work to do to finalize the design.
  • Thank you for attending my presentation.
  • Comments?
  • Questions?

LBNE Target Pile and Decay Pipe 29