Public Works Delivery Methods and Use at Sound Transit
December 2019
and Use at Sound Transit December 2019 Presenters Ted Lucas, - - PowerPoint PPT Presentation
Public Works Delivery Methods and Use at Sound Transit December 2019 Presenters Ted Lucas, Procurement and Contracts Nick Datz, Procurement and Contracts Joe Gildner, DECM Mike Bell, DECM Presentation Overview Quick Profile
December 2019
Governing Legislation: RCW Chapter 39.04
improvement other than ordinary maintenance, executed at the cost
Standard Public Works Delivery Methods
OWNER
DESIGNER
DESIGN SUBCONSULTANTS SPECIALTY TRADES
GENERAL CONTRACTOR
Designer and Contractor
One Step Procurement
Lump Sum Contract Agency Examples:
Planning & Programing
Final Design Construction
Designer Selected
Minimal Contractor Input No Contractor Input
Contractor Selected Cost Established Phase Gate 2
Owner
Contractor Designer
OWNER
DESIGNER
DESIGN SUBCONSULTANTS SPECIALTY TRADES GENERAL CONTRACTOR / CONSTRUCTION MANAGER
Designer and Contractor
Two Step Procurement
Contract
negotiated subcontract work
Planning & Programing
Final Design Construction
No Contractor Input
Cost Established Contractor Selected Designer Selected
Contractor Input Minimal Contractor Input
Owner
Contractor Designer
Phase Gate 2
University Link
North Gate Link
East Link
(L200)
Lynnwood Link
OWNER
DESIGN BUILDER
DESIGN SUBCONSULTANTS SPECIALTY TRADES
Design and Construction
Two Step Procurement
Contract
Planning & Programing
Final Design & Construction
Maximum Contractor Input No Contractor Input
Cost Established Design Builder Selected Phase Gate 2
Owner Design Builder
Central Link
South Link
East Link
Sounder
for Alignment
Federal Way Link Extension
for Alignment
Redmond Link Extension
RCW 39.10.250 Public Bodies must obtain approval through the State’s Project Review Committee (PRC) Two Ways to Gain PRC Approval:
Public Body Certification Requires:
Sound Transit Alternative Delivery Approval History
projects for GCCM & Design Build
Sound Transit Currently holds Public Body Certification for both Design Build and GCCM
GCCM
Design Build
Project Delivery Workshop(s) Phase Gate 2 – Select Delivery Method Informs Next Phase of Work
Evaluate Project Establish Evaluation Criteria
Establish Project Goals
22
Project Delivery Selection; Continuous Learning
10+ Years Experience Selecting and Delivering Alternative Public Works Projects Process Continues to be Reviewed and Refined as ST Gains Experience Updated Guidelines in 2019
Expanded Use of Alternative Delivery Beyond Light Rail
Commitments
25
Quality, Commissioning and Certification.
Development (DB)
(DB)
Transit Cooperative Research Program
TCRP 131
FTA OP 32D
Contents
RCW 39.10
Contracting Procedures
Project Definition
Early Project Design Establish Project Goals Establish High Level Project Risks
Corridor Plus Consultation
Broad Project Assessment Identify Range Of Delivery Method Options Decision Making Advice Workshop / Assessment Template
Advisory Panel
Composed of Subject Matter Experts Provide Input into Selection Decision
Recommend Delivery Method
Consider Criteria And Evaluations Consider Contract Packaging Rate Feasible Delivery Methods Iterative Process: Packaging, Size and Scope
Report
Written Report Of Decision and Process
Corridor Plus Check-In
Review Report Phase Gate Run-through
30
Contract Size Market Conditions Schedule Innovation Jurisdictions Administrative Efficiencies Competing Projects Staff Experience Scope