Analyst and Investor Presentation
28 March 2012
Analyst and Investor Presentation 28 March 2012 Disclaimer This - - PowerPoint PPT Presentation
Analyst and Investor Presentation 28 March 2012 Disclaimer This presentation may contain projections or forward-looking statements regarding a variety of items. Such forward-looking statements are based upon current expectations and
28 March 2012
regarding a variety of items. Such forward-looking statements are based upon current expectations and involve risks and uncertainties
statement based on a number of important factors and risks
2
Analyst and Investor Presentation, 28 March 2012
underlying the forward-looking statements are reasonable, any of the assumptions could prove inaccurate or incorrect and, therefore, there can be no assurance that the results contemplated in the forward-looking statements will be realised
presentation, Meridian cannot guarantee it is free from errors
3
Analyst and Investor Presentation, 28 March 2012
4
Analyst and Investor Presentation, 28 March 2012
have been just above half of average
than seasonal average inflows for 16 weeks. Waitaki and Waiau catchments together have received
50 100 150 200 250 300 350 Inflows (GWh)
Pukaki + Ohau Weekly Inflows
5
Analyst and Investor Presentation, 28 March 2012 Waitaki + Waiau Inflows
0.0 200.0 400.0 600.0 800.0 1000.0 1200.0 1400.0 1600.0 Dec - Mar Inflows (cumecs)
the lowest December to late March inflow total in 79 years of historical records
Meridian has received less water in
peak at this time of year and now begin to decline
1991-92 2007-08 2011-12
Inflow Year
5th %ile 5th - 95th %ile Mean Actual
is increasing
meet contract load, instruments already in place to assist through winter
600 800 1,000 1,200 1,400 1,600 1,800 2,000 GWh
Pukaki Storage
6
Analyst and Investor Presentation, 28 March 2012
winter
improved NI / SI balance
customers
achieve greater south flow on the HVDC
200 400 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
1991-92 2000-01 2001-02 2005-06 2007-08 2008-09 Mean 2011-12 We Are here
retail and time-of-use
range of instruments on offer
2,400 2,600 2,800 3,000 3,200 3,400
GWh
Quarterly Hydro Generation
Sep qtr Dec qtr Mar qtr Jun qtr
7
Analyst and Investor Presentation, 28 March 2012
debt headroom
revenue pressure
market participants and market behaviours have matured
Actual generation by quarter. Q4 FY2012 range based on mean (high) and 5th percentile (low) hydro inflows
2,000 2,200 2,400 FY2008 FY2009 FY2010 FY2011 FY2012
8
Analyst and Investor Presentation, 28 March 2012
hedge cover is impacting earnings
significantly curtailed and Meridian is within normal risk limits
targets from the Statement of Corporate
100 150 200 250 300 350 400
$m
EBITDAF (reported)
1H 2H
9
Analyst and Investor Presentation, 28 March 2012
targets from the Statement of Corporate Intent is very unlikely
Meridian expects FY2012 EBITDAF to significantly outperform FY2008 EBITDAF of $374m
50 100 FY2008 FY2009 FY2010 FY2011 FY2012
market and individual participants, depending on nature of events
variability (standard
300 400 500 600 700 EBITDAF ($m)
Historical EBITDAF by Company 10
Analyst and Investor Presentation, 28 March 2012
variability (standard deviation/mean) since 2006 is similar to most peers (range from 18% - 22%). Contact lower at 13% (i.e. less variable)
100 200 FY2006 FY2007 FY2008 FY2009 FY2010 FY2011
Contact Trustpower Mighty River Power Genesis Meridian Energy
11
Analyst and Investor Presentation, 28 March 2012
addition to
12
Analyst and Investor Presentation, 28 March 2012
a source of competitive advantage
geothermal and are capable of displacing existing thermal generation
geothermal
LRMC or unit cost, average revenue the wind farm would need to earn to cover all its costs including cost of capital Project DCF – all capital and operating costs as above but also expected revenue, giving NPV and IRR key outcomes
13
Analyst and Investor Presentation, 28 March 2012
resource, capital costs, WACC, O&M, operating life, tax, depreciation In DCF, revenue calculation is required – using long run price, location and profile (participation) premiums or discounts, ancillary services and
DCF that must exceed internal hurdle rate Hurdle rate > WACC to provide superior returns after sunk cost recovery Terminal value (second life or sustainable cashflows) excluded from
14
Analyst and Investor Presentation, 28 March 2012
Terminal value (second life or sustainable cashflows) excluded from this calculation
Second life Risk benefits Portfolio / retail benefits Other revenue sources
capital cost, purchase contracts in EUR or USD
installed capacity has peaked and is currently on a downward to flat trend
0.40 0.60 0.80 1.00 1.20 1.40 06 06 06 07 07 07 08 08 08 09 09 09 10 10 10 11 11 11 12 12 EURm/MW
Turbine procurement costs 15
Analyst and Investor Presentation, 28 March 2012
performance between suppliers
near post float high’s against both the EUR and USD
Jan 0 May 0 Sep 0 Jan 0 May 0 Sep 0 Jan 0 May 0 Sep 0 Jan 0 May 0 Sep 0 Jan 1 May 1 Sep 1 Jan 1 May 1 Sep 1 Jan 1 May 1
New Zealand Dollar
0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 Jan 06 Jul 06 Jan 07 Jul 07 Jan 08 Jul 08 Jan 09 Jul 09 Jan 10 Jul 10 Jan 11 Jul 11 Jan 12 Jul 12 USD EUR
Capital costs range between 0.9 and 1.2 m/MW (Euro)
the largest component (~55%). Costs depend on:
batching
16
Analyst and Investor Presentation, 28 March 2012
modular, with the exception of transmission connection:
and require careful design Forward expectations are between $900 - $1200/kW civil : balance of plant ~55:45
every ±10% change in wind speed, around ±15% - 20% change in energy
17
Analyst and Investor Presentation, 28 March 2012
and as an owner/operator is able to calibrate using actual operational data
engineering system
potential for wind generation in complex terrain
Good sites have a yield between 35% and 49%
Failure Rate for Gearbox
(by failure type by year) 0.8% 1.7% 2.5% 3.3% 4.2% 5.0% All Infant Mortality Random Wear Out Premature Serial
characteristics because of its associated wind profile
are optimised for each individual turbine, with learnings applied across the site and portfolio
18
Analyst and Investor Presentation, 28 March 2012
vendor technical engagement and in-house expertise at a component-by- component level
maintenance strategy O&M costs range between $9 and $20/MWh Availability between 90% and 99%
0.0% 2 4 6 8 10 12 14 16 18 20 22 24
across the site and portfolio
year
Detailed modelling considers premature and late failure of turbines Confidence in performance of assets over time
Consent is typically indefinite
19
Analyst and Investor Presentation, 28 March 2012
Consent is typically indefinite Wind resource does not degrade Civil works (50 years) – roads and foundations Electrical and mechanical infrastructure (50 years)
Assume 60-70% original “above ground” costs at refurbishment Assume ‘like for like’ yield and operational metrics Contributes typically ~$5/MWh additional value
Typical lifetime of 25 years used in first life valuation
“Participation rate” or “GWAP” – wind capture of market price (includes daily and seasonal correlation effects) Constraints and outages, both planned and unplanned Operational strategies of turbines (deratings in certain conditions) Electrical losses within the wind farm
20
Analyst and Investor Presentation, 28 March 2012
Electrical losses within the wind farm
up to 20% of installed capacity can be met with wind at minimal additional cost
generation option and “setting” long run prices
GWAP or “participation rate” is site specific with wider range of 85% - 104% depending on project characteristics and location
Capital Cost Turbines Balance of Plant and Civil Yield
0.9 1.2 900 1,200 35% 49% Percent m/MW (Euro) $/kW (NZD)
21
Analyst and Investor Presentation, 28 March 2012
Resultant unit costs can vary significantly depending on where a particular site sits within these ranges
Operations and Maintenance Availability Life GWAP:TWAP (participation rate)
9 20 20 25 Years $/MWh 85% 104% Percent Percent 90% 99%
Capital Cost Turbines Balance of Plant and Civil Yield
0.9 1.2 900 1,200 35% 49% Percent $m/MW (Euro) $/kW (NZD)
22
Analyst and Investor Presentation, 28 March 2012
Can expect good projects to have unit cost <$85/MWh
Operations and Maintenance Availability Life GWAP:TWAP (participation rate)
9 20 20 25 Years $/MWh 85% 104% Percent Percent 90% 99%
planning and design, and the performance of the selected technology
thermals
between $85 and $95/MWh
23
Analyst and Investor Presentation, 28 March 2012
between $85 and $95/MWh
True greenfield geothermal Thermal (gas / coal)
Need to carefully assess economics of individual site and turbines best matched to that site Lets not forget hydro – attractive options remain at competitive costs
24
Analyst and Investor Presentation, 28 March 2012
"#$%& # ' !"#$%& "
Underlying growth in demand has significantly reduced…… …but is forecast to recover during 2012- 2020.
1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000
Cumulative GWh, 2012-2020
100 200 300 400 500 600 700 800 900 1000
GWh p.a.
25
Analyst and Investor Presentation, 28 March 2012
reduced GDP
next nine years, or 710 GWh pa, consistent with other industry estimates
will maintain its generation market share
( (
Electricity Consumption by Sector (Strategy and Finance: Jan 2012) Projected Demand Growth 2012 - 2020 (Strategy and Finance, RD Jan 2012)
1,000 MED (2011) EC SOO (2010) Transpow er (Sep 11) Meridian (Low ) Meridian (Medium) Meridian (High) 100
Thermal output is variable, but trending down since 2008
2,000 4,000 6,000 8,000 10,000 12,000 14,000 2003 2004 2005 2006 2007 2008 2009 2010 2011
GWh
) *( +!',
( (
+%.1# 2 3. ,4/56 $
Analyst and Investor Presentation, 28 March 2012
to hydrology and asset reliability uncertainties
Electricity Output (GWh) by Major Thermal Plant (Source: Electricity Authority, RocMo)
Huntly 1-4 Otahuhu B TCC + peaking turbines Southdown New Plymouth Huntly e3p Huntly p40
(Source: Meridian Analysis)
( ( *
Capacity needed Capacity needed
Long term view versus shorter term market conditions
Analyst and Investor Presentation, 28 March 2012
Consentability, yield, grid access, cost, land owner arrangements
28
Analyst and Investor Presentation, 28 March 2012
Turbine prices similar to 2005 levels Exchange rate at highly favourable levels Site yield is one of the best in New Zealand Unit cost < average running costs of thermals
29
Analyst and Investor Presentation, 28 March 2012
Unit cost < average running costs of thermals
prices, matched to current, low growth environment
No significant investment in transmission Enhances HVDC southward flow, reducing South Island dry year risk
30
Analyst and Investor Presentation, 28 March 2012
31
Analyst and Investor Presentation, 28 March 2012
term demand upside (home heating / electric vehicles)
carbon pricing compared to other countries
Affordable, value accretive wind and hydro pipeline Retail – improving performance and differentiation
32
Analyst and Investor Presentation, 28 March 2012
Earnings upside in core business through wholesale price uplift Highly flexible assets Overseas opportunities to provide superior return from competitive advantages
100% Renewable Largest energy business in NZ
no show stoppers
33
Analyst and Investor Presentation, 28 March 2012
Retail Offshore investment