Analysis and Discussion of Deepwater Horizon Accident and Barrier - - PowerPoint PPT Presentation

analysis and discussion of deepwater horizon accident and
SMART_READER_LITE
LIVE PREVIEW

Analysis and Discussion of Deepwater Horizon Accident and Barrier - - PowerPoint PPT Presentation

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion Analysis and Discussion of Deepwater Horizon Accident and Barrier Strategies Nathalie M. De Oliveira, Jeevith Hegde Faculty of Engineering Science and Technology,


slide-1
SLIDE 1

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion

Analysis and Discussion of Deepwater Horizon Accident and Barrier Strategies

Nathalie M. De Oliveira, Jeevith Hegde

Faculty of Engineering Science and Technology, Department of Marine Technology, NTNU noliveira@oceaneering.com jeevith.hegde@ntnu.no

January 23, 2015

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-2
SLIDE 2

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion

Content

1

Introduction Summary of Macando Blowout Comparison to other similar accidents

2

Failed Barrier Analysis Step Diagram MTO Analysis Bow-Tie Diagram

3

Proposed Barrier Strategy PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

4

Conclusion

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-3
SLIDE 3

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion Summary of Macando Blowout Comparison to other similar accidents

Accident Summary

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-4
SLIDE 4

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion Summary of Macando Blowout Comparison to other similar accidents

Comparison to other similar accidents

Similar Blowout Accidents

Macondo 2010 Initiating event- High pressures in the wellbore Accident Progression- Well abandonment- kick in well- hydrocarbon leak- two explosions Fatalities- 11 of 126 (9%) Usumacinta 2007 Initiating event- Bad weather Accident Progression- Storm- hydrocarbon leak Fatalities- 22 of 81 (27%) Enchova 1984 Initiating event- Unknown Accident Progression- Drilling- Gas leak Fatalities- 42 of 249 (17%) The evacuation process in Deepwater Horizon, did not result in fatalities [Vinnem, 2014]. One could infer that Transocean had better evacuation procedures than PEMEX (Usumacinta) or Petrobras (Enchova). Texas City Refinery Initiating event- Overfilling of splitter tower. Accident Progression- Maintenance faults- malfunction of level transmitters- explosion Fatalities- 15 people Injured- 170 people Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-5
SLIDE 5

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion Step Diagram MTO Analysis Bow-Tie Diagram

Step Diagram

Loss of Circulation at 18260ft and 18360ft- Stopped Drilling

BP Actors Events Halliburton Transocean Minerals Management Services

Marinas changed to Deepwater Horizon BOP: Leak in yellow Pod February 2010 March 2010 Approved Single Long string casing design April 2010 Choice of Long String Casing to complete the well. April 9 2010 April 12 2010 April 15 2010 6 Centralizers installed April 16 2010 Decision to use 7 Centralizers Analyzed 7 Centralizers design Report issued to BP with concerns on number of centralizer used sent after cementing April 18 2010 April 19 2010 Incomplete Bottoms Up

  • perations

April 20 2010 Early Presurre

  • Testing. Before

Cement Setting. Simultaneous Operations Different Iterpretation of Two Negative Pressure Test Well Kick Redirected Gas to Separator 13:28 Hours 20:00 Hours 21:45 Hours Outage of Power Explosion 1 and 2 Alarm Software Disconnected EDS Malfunction Man Technology

Barrier Legend 21:49 Hours 21:52 Hours

Uncontrolled HC Leak Bending of Drill Pipe

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-6
SLIDE 6

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion Step Diagram MTO Analysis Bow-Tie Diagram

MTO Analysis

Failed MTO Barriers

Man Organization Technology

2 3 5 3 1 2

Failures in the intersection of man and organizational barriers are higher in number than other categories. The combination of man and

  • rganization resulted in six failed

barriers

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-7
SLIDE 7

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion Step Diagram MTO Analysis Bow-Tie Diagram

Bow-Tie Diagram

Barrier Legend

Macondo Blowout

Man Organization Technology

Single String Completion Casing

Wellhead Seal Choice of Single String Casing

Blow Out Preventer

Shear Rams Annular Preventors Pipe Rams BOP Certificatio n

Pressure Testing

Testing after Cement Set Validate Test Results

Centralizers

Internal Communication Validate Results Energy Flow

HC Detection and Mitigation

Maintenance of F&G Barriers

Explosion

Fire & Gas Detection Emergency Preparedness Redirection of HC Alarm and Deluge Systems Fire Fighting System

Evacuation

Energy Flow

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-8
SLIDE 8

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

PSA Barrier Mangement Process

Figure: [PSA, 2013]

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-9
SLIDE 9

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Hazard Identification

  • SL. No.

Generic Hazard Hazard 1 Mechanical hazards High/unstable pressure in the well Stability Degradation of equipment 2 Dangerous materials Flammable 3 Thermal hazards Flame Explosion Personnel exposed to high temperature and heat radi- ation 4 Organizational hazards Safety culture Less than adequate maintenance Less than adequate competence Crowd control

[Rausand, 2011]

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-10
SLIDE 10

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Preliminary Hazard Analysis

Terminologies

Generic Hazard Mechanical, dangerous, thermal and organizational. Identifier Identify and arrange different probable causes. Hazard Specific hazard in relation to generic hazard. Accidental Event Describe what, when, where things can go wrong. Probable Causes Causes triggering the accidental event. Probability Evaluating likelihood of occurrence of an accident event. Severity Evaluating consequences if an accident event

  • ccurs.

Initial Risk Level Factor of probability, severity and lack of preventive measures. Residual Risk Level Factor of probability, severity and introduction of preventive measures. Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-11
SLIDE 11

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Risk Picture

Initial Risk Picture Residual Risk Picture

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-12
SLIDE 12

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Barriers according to PSA Memo- Part 1

Reduce Risk of Hydrocarbon Leak from the Well

Isolate areas with different pressures and fluids. Prevent collapsing and leak of well formation. Regulate flow of Hydrocarbons Kill the well Avoid Rig Drift and Drive off Avoid External Ship Collision Isolated hydrocarbons subsea. Risers BOP Casing Casing Centralizers Drilling Mud Barrier Functions Barrier Elements BOP Sub-Functions Drilling Mud Choke Valve Kill Line Valve BOP Emergency Shutdown Dynamic Positioning System Collision Avoidance Alarms Safety Zone Regulations Bottoms- up Pressure Testing (Negative and Postive)

Performance Requirements

Organization and Man barriers are included in each barrier element because the selection of the above phyiscal barriers depends on the individual/organization perceptions in form

  • f analysis and design.

 Management focus on safety through campaigns. (Top to bottom and bottom to top)  Accountability of the company towards safety incidents through industry and national regulations  Establishing single point of contacts and analysing it through Social Network Analysis tools  Continuous improvement of safety drive in the company and expansion of each project’s Risk Analysis Assessment to keep up with changes made to the original plan during the execution phase - continuous reassessment of the risk picture.  Periodically re-optimize maintenance costs  Investment in continuous training of personnel in best available safety practices  Investment in mentoring programmes  Hiring competent personnel  Sharing lessons learnt to other companies  Timely certificaiton and maintenance of safety critical systems

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-13
SLIDE 13

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Barriers according to PSA Memo- Part 2

Redirect Hydrocarbons to Safe Area

Reduce Consequence of Hydrocarbon Leak

Reduce Duration and Size of Leak Limit Exposure of Personnel at Danger Zones Plans for Emergency Preparedness Personnel Evacuation Reduce Risk of Explosion Fire & Gas Detection Alarm and Deluge Systems Emergency Procedures Fire & Gas Detection Process Shudown Systems Fire and Gas Detectors Emergency Safety Procedures Shudown Process Fire and Gas Detectors Safety Alarms Sprinklers Facility Design Based

  • n Hazards

Explosion Resistant Constrution Area Isolation (Restricted Personnel Access Areas) Lifeboats Support Vessels Personnel Protective Equipment Barrier Functions Barrier Elements Sub-Functions

Organization and Man barriers are included in each barrier element because the selection of the above phyiscal barriers depends on the individual/organization perceptions in form

  • f analysis and design.

 Management focus on safety through campaigns. (Top to bottom and bottom to top)  Accountability of the company towards safety incidents through industry and national regulations  Establishing single point of contacts and analysing it through Social Network Analysis tools  Continuous improvement of safety drive in the company and expansion of each project’s Risk Analysis Assessment to keep up with changes made to the original plan during the execution phase - continuous reassessment of the risk picture.  Periodically re-optimize maintenance costs  Investment in continuous training of personnel in best available safety practices  Investment in mentoring programmes  Hiring competent personnel  Sharing lessons learnt to other companies  Timely certificaiton and maintenance of safety critical systems

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-14
SLIDE 14

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Barrier Performance Requirement- Functional Level

Barrier Performance Stan- dard Performance Standard (Functionality, In- tegrity, Vulnerability) Isolate areas with different pres- sures and fluids Functionality Established pressure limits in various zones Prevent collapsing and leak of well formation Functionality Loss of drilling mud should not exceed the given limit Regulate flow of Hydrocarbons Integrity Minimum failure rate of BOP through quantitative

  • analysis. Example- SIL analysis

Isolated hydrocarbons subsea Integrity Minimum failure rate of BOP through quantitative

  • analysis. Example- SIL analysis

Avoid Rig Drift and Drive off Functionality Limits and accuracy dynamic positioning system en- velopes Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-15
SLIDE 15

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Barrier Performance Requirement- Element Level

Barrier Performance Stan- dard Performance Standard (Functionality, In- tegrity, Vulnerability) Fire and Gas Detectors Integrity Determine acceptable failure rate of detectors through quantitative analysis. Example- SIL analysis Emergency Safety Procedures Functionality Be aligned with the risk picture Safety Alarms Integrity Determine acceptable failure rate of detectors through quantitative analysis. Example- SIL analysis Sprinklers Integrity Determine acceptable failure rate of FF equipment through quantitative analysis. Example- SIL analysis Process Shutdown Systems Integrity Determine acceptable failure rate of Process Shutdown System through quantitative analysis. Example- SIL analysis Lifeboats Functionality Have sufficient capacity to include all personnel on- board the rig Support Vessels Functionality Response to an emergency call within a given time limit Restricted Personnel Access Ar- eas Functionality Normally manned working stations should be sheltered

  • r out of reach from potential explosions caused by HC

release Personnel Protective Equipment Vulnerability Guarantees impact and thermal protection to a stipu- lated level Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-16
SLIDE 16

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Barrier Performance Requirement- Organizational Level

Barrier Performance Stan- dard (Functionality, Integrity, Vulnerabil- ity) Performance Standard Management focus on safety through cam- paigns Functionality Commit management time to safety activi-

  • ties. Safety walk. Walk-Observe-Feedback.

Accountability of the company towards safety incidents through industry and na- tional regulations Functionality Social corporate responsibility drive Establishing single point of contacts and analyzing it through Social Network Analy- sis tools Functionality Make contact information of single points

  • f contact public and know

Continuous improvement of safety drive in the company and expansion of each projects Risk Analysis Assessment to keep up with changes made to the original plan during the execution phase - continuous re- assessment of the risk picture. Functionality Risk Analysis Assessments should be re- viewed at fixed intervals during planning phase and whenever a major modification to plan occurs during project execution Periodically re-optimize maintenance costs Functionality At predetermined given time intervals, aim- ing to cut a given percentage of labor Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-17
SLIDE 17

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion PSA Process Hazard Identification Specific Barrier Strategy Barrier Requirements

Barrier Performance Requirement- Organizational Level

Barrier Performance Stan- dard (Functionality, Integrity, Vulnerabil- ity) Performance Standard Investment in continuous training of per- sonnel in best available safety practices Functionality Annual evaluation of relevant technical knowledge Investment in mentoring programmes Functionality Ensure mentoring program for new employ- ees Hiring competent personnel Functionality Assessment of technical knowledge and per- sonality Sharing lessons learnt to other companies Functionality Target number of published industry white papers Timely certification and maintenance of safety critical systems Integrity Traceability of equipment and process cer- tificates Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-18
SLIDE 18

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion

Conclusion

1 Complex systems = complex accident propagation 2 Risk analysis must be performed and updated 3 Barrier management is paramount 4 Organizational and human barriers are constantly in demand

during accident progression

5 Systems safety should not be neglected in favor of traditional

HSE indicators

Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-19
SLIDE 19

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion

References

CSB, (2007) CSB Safety Video: Explosion at BP Refinery. YouTube: http://youtu.be/c9JY3eT4cdM CSB, (2014) Deepwater Horizon Blowout Animation. YouTube: https://www.youtube.com/watch?v=FCVCOWejlag Petroleum Safety Authority Norway- PSA (2014) PSA regulations. Webpage: PSA regulations PSA, (2013) Principles for barrier management in the petroleum industry Technical Report Rausand, M, (2005) Lecture Notes- Risk Assessment- Preliminary Hazard Analysis (PHA). Rausand, M, (2011) Risk Assessment : Theory, Methods, and Applications. Book- John Wiley & Sons, Inc. Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project

slide-20
SLIDE 20

Introduction Failed Barrier Analysis Proposed Barrier Strategy Conclusion

References

Sklet, (2006) Safety barriers on oil and gas platforms. Means to prevent hydrocarbon releases. PhD Thesis (DHSG)(2011) The Deepwater Horizon Study Group (DHSG)(2011). Final report on the investigation of the Macondo well blowout Technical report, Center for Catastrophic Risk Management (CCRM). Vinnem (2014) Offshore Risk Assessment Vol 1 and 2 Springer, London, 3rd edition Nathalie M. De Oliveira, Jeevith Hegde TMR4555 Project