an update
- Introduction
- Progress on the experiment
- Schedule
Richard Milner 1 DESY PRC Zeuthen October 14, 2010
an update Introduction Progress on the experiment Schedule DESY - - PowerPoint PPT Presentation
an update Introduction Progress on the experiment Schedule DESY PRC Zeuthen Richard Milner 1 October 14, 2010 Lepton-proton elastic scattering cross-section 2 + + 2 DESY PRC Zeuthen Richard Milner 2 October 14,
Richard Milner 1 DESY PRC Zeuthen October 14, 2010
Richard Milner DESY PRC Zeuthen October 14, 2010 2
2
Richard Milner DESY PRC Zeuthen October 14, 2010 3
P.G. Blunden et al.,
034612 (2005) Saturation at Q2 ~ 2-3 (GeV/c)2
Richard Milner DESY PRC Zeuthen October 14, 2010 4
Richard Milner DESY PRC Zeuthen October 14, 2010 5
an internal hydrogen gas target to precisely measure the e+p/e-p cross section ratio
6
Richard Milner DESY PRC Zeuthen October 14, 2010
7
Richard Milner DESY PRC Zeuthen October 14, 2010
8
Richard Milner DESY PRC Zeuthen October 14, 2010
9
Richard Milner DESY PRC Zeuthen October 14, 2010
10
– Transformer installed – Power supply installed – Power cables installed – Interconnection of coils to be made – Interlock system in preparation
– Survey and adjustment of coil positions – Commission power magnet and magnet – Perform field measurement – Re-align coil positions if necessary
Richard Milner DESY PRC Zeuthen October 14, 2010
Richard Milner DESY PRC Zeuthen October 14, 2010 11
Richard Milner DESY PRC Zeuthen October 14, 2010 12
Richard Milner DESY PRC Zeuthen October 14, 2010 13
Richard Milner DESY PRC Zeuthen October 14, 2010 14
– 8 small TOFs (1 re-glued) – 24 large TOFs (8 re-glued) – 8 Bats: (4 require back bones) – 5 full spare modules (3 rely on exchange back bone)
Richard Milner DESY PRC Zeuthen October 14, 2010 15
Richard Milner DESY PRC Zeuthen October 14, 2010 16
Richard Milner DESY PRC Zeuthen October 14, 2010 17
Richard Milner DESY PRC Zeuthen October 14, 2010 18
CAD databases and fiducialized
DESY in December
Gluing of gas pressure foils, HV foils, GEM foils partially completed
remaining elements by March 2011
and delivered July 2010
frontend designed (Sep. 2010)
designed, quote requested
prepared (October 2010)
Fitting of telescope array into available spaces in 3D CAD
last July.
but not optimized (acquisition rate improved in September work at lab).
FEC designed for bigger chambers, input capacitance to be adapted, work underway)
Richard Milner DESY PRC Zeuthen October 14, 2010 23
Richard Milner DESY PRC Zeuthen October 14, 2010 24
Richard Milner DESY PRC Zeuthen October 14, 2010 25
Richard Milner DESY PRC Zeuthen October 14, 2010 26
Richard Milner DESY PRC Zeuthen October 14, 2010 27
Richard Milner 28 DESY PRC Zeuthen October 14, 2010
DESY integration: Will be new vacuum segment. Valves controlled by DESY vacuum group. Pumps and internal valves will be controlled by OLYMPUS
Richard Milner 29 DESY PRC Zeuthen October 14, 2010
Status of slow control:
functionality) Status of hardware:
Richard Milner 30 DESY PRC Zeuthen October 14, 2010
Richard Milner DESY PRC Zeuthen October 14, 2010 31
Richard Milner DESY PRC Zeuthen October 14, 2010 32
Richard Milner DESY PRC Zeuthen October 14, 2010 33
Richard Milner DESY PRC Zeuthen October 14, 2010 34
lepton sign reversal implemented, a test experiment can be carried out in the months February through July 2011
Richard Milner 35 DESY PRC Zeuthen October 14, 2010
Richard Milner 36 DESY PRC Zeuthen October 14, 2010
Count rates: TOF: 64/s GEMs: 40/s Coincidences:19/s 1hour to get adequate statistics (at 2GeV)
Richard Milner 37 DESY PRC Zeuthen October 14, 2010
located +/- 3 m around OLYMPUS target point
readout rate)
– a = 0+/-0.1 (synch. rad.) – b = 0.3 +/- 0.001 (rest gas) – Verification with shielded scintillator planned
Time
Richard Milner DESY PRC Zeuthen October 14, 2010 41
OLYMPUS detector
Testing of OLYMPUS target at MIT-Bates
Install test experiment in December 2010-February 2011 Install complete experiment in August 2011 Commission in fall 2011 Take data in two running blocks in 2012 Detailed schedule with critical milestones available
Richard Milner DESY PRC Zeuthen October 14, 2010 42