An Andre rew Deme metrio riou LLB B (H (Hons. s.), ), Ba - - PowerPoint PPT Presentation

an andre rew deme metrio riou llb b h hons s ba barrist
SMART_READER_LITE
LIVE PREVIEW

An Andre rew Deme metrio riou LLB B (H (Hons. s.), ), Ba - - PowerPoint PPT Presentation

THE E ST STREN ENGTHS S AN AND WEAKN EAKNESSES ESSES OF THE E AD ADR PR PROCED EDURE E IN PU PUBL BLIC CONTRAC ACTS An Andre rew Deme metrio riou LLB B (H (Hons. s.), ), Ba Barrist rrister r at Law, FCI. Arb Arb. Chart


slide-1
SLIDE 1

THE E ST STREN ENGTHS S AN AND WEAKN EAKNESSES ESSES OF THE E AD ADR PR PROCED EDURE E IN PU PUBL BLIC CONTRAC ACTS

June 2017

An Andre rew Deme metrio riou LLB B (H (Hons. s.), ), Ba Barrist rrister r at Law,

  • FCI. Arb
  • Arb. Chart

rtere red Arb Arbit itra rator, r, Accre Accredit ited Me Media iator, r, Regist istere red Tru rust sts s and Est Estates s Pra Pract ctit itio ioner Dire irect ctor r Ioannid ides s Deme metrio riou LLC

slide-2
SLIDE 2

The Gove vern rnme mental l Ap Appro roach ch to AD ADR The governmental approach to ADR and Arbitration in particular is characterised by the following traits:

slide-3
SLIDE 3

§ It is ill-informed. § It has never taken ADR seriously. § ADR is viewed with suspicion. § In Government Contracts there are two options:

  • Amicable Settlement
  • Litigation
slide-4
SLIDE 4

An Analysis lysis of Cla lause se 67.1 Se Settle leme ment of Disp isputes The 56 Day y Amica Amicable le Se Settle leme ment Pro Proce cedure re

slide-5
SLIDE 5

Any dispute between the Employer and the Contractor arising

  • ut of or as a result of the Contract or the execution of the

works either during the course of the execution of the contract

  • r after its completion and either before or after the

abandonment or termination of the Contract, including any dispute in relation to any decision, opinion, order, determination, certificate or assessment of the Engineer then either the Employer or the Contractor have the right to give notice of the dispute to the other party, with communication [of the notice] to the Engineer, and in this event the Parties are

  • bliged for the following 56 days to settle the dispute amicably

before the commencement of the judicial proceedings. The notice shall refer to the fact that it has been given in accordance with this clause. Any dispute that is not settled amicably within 56 days from the service of the above notice shall be tried by the competent district court of the Republic of Cyprus.

slide-6
SLIDE 6

Disa isadva vantages s of the Amica Amicable le Se Settle leme ment Pro Proce cedure re The process is not structured. There are no experts on hand to guide the parties in their efforts to achieve an amicable settlement.

slide-7
SLIDE 7

It is a truism that cashflow is, as Denning LJ noted in Modern Engineering (Bristol) Ltd v. Gilbert-Ash (Northern) Ltd (1973) 71 LGR 162, the ‘very lifeblood’ of the construction industry. 56 days is two months. It is too long a period, considering that the contractor is entitled to monthly payments and that payments to be made should be added to monthly certificates.

slide-8
SLIDE 8

If the Contractor disputes a decision of the Engineer to deduct LDs there will be two deductions before the dispute resolution procedure is terminated. The length of the amicable dispute process puts the contractor at a severe disadvantage and causes or increases cashflow problems. The amicable settlement procedure diverts resources from both sides.

slide-9
SLIDE 9

It provides evidence to be used in court as to the position of the Engineer – the judicial proceedings clause states “…nothing shall preclude the possibility of the Engineer being called as a witness to file exhibits before the court for any matter that is relevant to the dispute.” If it is unsuccessful, it will entrench attitudes. If it fails, two months have been lost.

slide-10
SLIDE 10

Ad Adva vantages s of the Amica Amicable le Se Settle leme ment Pro Proce cedure re

  • It may bring the sides closer together by

informing each other of their respective positions.

slide-11
SLIDE 11
  • It provides evidence to be used in court

as to the position of the Engineer – the judicial proceedings clause states “… nothing shall preclude the possibility of the Engineer being called as a witness to file exhibits before the court for any matter that is relevant to the dispute.”

  • It is shorter than court proceedings.
slide-12
SLIDE 12

Quest stio ion Why not provide for Mediation?

slide-13
SLIDE 13

It is structured. It is confidential. An expert mediator is present to assist the parties. A shorter time limit can be achieved than 56 days. It is not binding unless a settlement agreement is concluded.

slide-14
SLIDE 14

So what has the government got to lose?

slide-15
SLIDE 15

I sa say y enter r in into me media iatio ion agre reeme ments s for r all ll co contra ract cts s tomo morro rrow.

slide-16
SLIDE 16

The The Housing Housing Grants, Grants, Construction Construction and and Regenera ratio ion Act Act 1996 (H (HGRA A -

  • also

lso kn known as s the Const stru ruct ctio ion Act Act) is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.

slide-17
SLIDE 17

Provisions of the Act include: § The right to be paid in interim, periodic or stage payments. § The right to be informed of the amount due,

  • r any amounts to be withheld.

§ The right to suspend performance for non- payment. § The right to adjudication. § Disallowing pay when paid clauses.

slide-18
SLIDE 18

The Act applies to all contracts for 'construction operations' (including construction contracts and consultants‘ appointments). If contracts fail to comply with the act, then the Scheme for Construction Contracts applies.

slide-19
SLIDE 19

Const stru ruct ctio ion Contra ract cts s Act Act 2002 This Act provides those carrying out construction work with the ability to issue payment claims and, where not responded to fully or on time, elevates the amount sought in payment claims to being amounts that are due and owing.

slide-20
SLIDE 20

§ The aim behind the Act is to promote cashflow or, said in a different way, the philosophy is “p “pay y now arg rgue la later” r”. It is in this context that adjudications pursuant to this Act operate. It is possible for a party to a construction contract to refer a matter to an adjudication under the Act. § This is a fast-track dispute resolution mechanism that potentially places a duly appointed adjudicator under an obligation to make a determination within 35 working days of the adjudication claim being served by the claimant.

slide-21
SLIDE 21

What What is is the the Reason Reason for for Such Such Legisla islative ive Pro Provisio visions? s? What has s been the Resu sult lt of Su Such ch Pro Provisio visions s and Pro Proce cedure res? s?

slide-22
SLIDE 22

Po Poin ints s to Consid sider r What studies have been carried out in Cyprus? Has anyone considered the effects of the current regime of ADR? The government may not be losing cases in arbitration, but what are the effects on the economy? Has the regime of dispute resolution contributed to the corruption in Cyprus public sector contracts?

slide-23
SLIDE 23

Ju Judicia icial l Pro Proce ceedin ings s in in Cyp ypru rus s The Se Seco cond Pa Part rt of Cla lause se 67.1

  • Its no secret that Cyprus has one of the

slowest court processes in the EU.

  • On average cases may take anything

from 3 to 7 years for a first instance judgment; we are now in our office trying cases from 2007 and even one

  • n a retrial from 1986.
slide-24
SLIDE 24
  • Additionally, appeals take between 3 and 5

years to he heard.

  • The courts are not equipped to hear complex

construction disputes.

  • There is no technology in court.
  • After waiting sometimes up to 5 years for a

case to go to trial the judge tries to persuade the parties to go to arbitration.

slide-25
SLIDE 25
  • Therefore, there is a tremendous delay in

the administration of justice.

  • This has a price. For the contractor and for

the Employer.

  • Memories fade, witnesses retire,

documents are lost.

  • The government may benefit from a longer

period to pay, but it will always be at a disadvantage against an organised and well-resourced contractor.

slide-26
SLIDE 26

Lig ight at the En End of the Tunnel AD ADR and the Priva Private Se Sect ctor

slide-27
SLIDE 27

Arbitration, Adjudication, Mediation and Conciliation have all developed b e c a u s e s o c i e t y a n d t h e commercial and economic realities saw that there was a need and a place for them.

slide-28
SLIDE 28

Cyp ypru rus s ca cannot and sh should ld not co contin inue to be the exce xceptio ion.

slide-29
SLIDE 29

ioannides demetriou LLC The City House, 17-19 Them. Dervi Str. 1066 Nicosia, Cyprus. P.O. Box 20106, 1601 Nicosia, Cyprus. Tel: +357 22022999 Fax: +357 22022900 www.idlaw.com.cy

Thank you