Agenda 1. Process and Timeline 2. Original Submission 3. - - PowerPoint PPT Presentation

agenda
SMART_READER_LITE
LIVE PREVIEW

Agenda 1. Process and Timeline 2. Original Submission 3. - - PowerPoint PPT Presentation

March 21, 2018 ALCA Meeting March 21, 2018 Agenda 1. Process and Timeline 2. Original Submission 3. Revised Submission 4. Next Steps The City of Calgary Role: The City is responsible for capturing and using public feedback, along


slide-1
SLIDE 1

March 21, 2018 ALCA Meeting

March 21, 2018

slide-2
SLIDE 2

Agenda

1. Process and Timeline 2. Original Submission 3. Revised Submission 4. Next Steps

slide-3
SLIDE 3

The City of Calgary

Role:

  • The City is responsible for capturing and using public feedback, along with a comprehensive

technical review, to assess the application and make a recommendation to Calgary Planning Commission (CPC) and City Council. Process:

  • Aug. 2017: Open house and online engagement.
  • Sept. 2017: City provides technical review comments to applicant.
  • Jan. 2018: Applicant submits amended application. Revised application shared with the public.
  • Feb. 2018: City provides additional technical comments on revised application.
  • (Current) Mar. 2018: Applicant working on final application.
  • Spring 2018: Tentative date for final land use application submission.
  • Summer 2018: Tentative date for presentation to CPC.
  • Summer 2018: Tentative date for City Council Public Hearing.

March 21, 2018 ALCA Town Hall Meeting 3

slide-4
SLIDE 4

ORIGINAL SUBMISSION

MAY 2018

slide-5
SLIDE 5

Plan Considerations

  • Generally slopes from the north and

east to the south and west

  • Predominantly undeveloped – except

for one existing homestead

  • Existing views from the existing

community to the north and east

  • High pressure gas line (to be

converted to a low pressure gas line in 2020) along the northern boundary

  • Crowfoot LRT located approximately

600 metre from southern boundary

  • Regional pathway on east boundary
  • Close proximity to the Crowfoot

Commercial Centre

  • Existing loam pile requiring removal

March 21, 2018 ALCA Town Hall Meeting 5

slide-6
SLIDE 6

Environmental Studies

  • Preliminary Biophysical Impact

Assessment (BIA) conducted by Stantec Consulting

  • Field assessments completed in the

Spring and Summer of 2015 & 2017

  • Stantec Determined:
  • Six wetland areas ranging in class
  • Most of the habitat provide limited

wildlife potential

  • Treed areas may provide some
  • pportunities for songbirds, raptors

and bats

  • Wetlands provide low to moderate

habitats for wildlife

  • Disconnected and fragmented habitat
  • Overall, due to existing level of

disturbance and previous impacts to vegetation, leading to a low quality wildlife habitat, the development is considered to have an “overall low environmental consequence.”

March 21, 2018 ALCA Town Hall Meeting 6

slide-7
SLIDE 7

Wetlands

  • Still under consideration is the

retention of Wetland 4

  • City policy interpretation is the driving

force behind keeping Wetland 4

  • Due to elevation of wetland, building

heights would be higher and park space would likely not be as central and large

  • Impact to the plan is still under review,

to be considered by the City, Hopewell and affected stakeholders.

March 21, 2018 ALCA Town Hall Meeting 7

slide-8
SLIDE 8

Staged Master Drainage Plan

Conclusions:

  • The stormwater management facility

proposed in this report will control the discharge from the proposed development, at the discharge rate stipulated by the City of Calgary, Water Resources.

  • The Best Management Practices

suggested in this report will reduce the runoff volume discharge to the Bow River to an average annual of 50 mm/year.

  • Water quality enhancement will be

achieved by the proposed oil/grit separator.

  • This stormwater will be cleaner than

the stormwater coming from the existing community

March 21, 2018 ALCA Town Hall Meeting 8

slide-9
SLIDE 9

Developing the Block Pattern

  • Access, combined with grading

constraints, determined the block layout and access points.

  • Access points are relatively fixed

based on:

1. the existing access point to Watergrove Mobile Home park 2. City requirements of a 150 m technical

  • ffset from the northern plan boundary

3. City requiring minimum intersection distances of 60 metres.

  • The project team proposed the

northern access slightly south of the fixed point to provide additional distance from Arbour Meadows Close NW, while allowing a 90 degree connection to Arbour Lake Road, and to allow space to work with challenging grades to the north.

March 21, 2018 ALCA Town Hall Meeting 9

slide-10
SLIDE 10

Concept Plan Original Submission

  • A variety of housing options including

single-detached and multi-residential

  • Townhomes: 2-3 storeys
  • Apartments: 4-6 storeys
  • Higher densities located along Arbour

Lake Road and in close proximity to similar uses to the north and southeast; and in closer proximity to the LRT

  • Large central open space
  • Maintain connections to the existing

community

  • Approximately 890 units
  • No commercial uses

March 21, 2018 ALCA Town Hall Meeting 10

slide-11
SLIDE 11

Transportation

  • Transportation Impact Assessment

(TIA) conducted by Bunt and Associates

  • Weekday peak hour intersection

capacity analysis was completed at four (4) study area intersections for the Existing and Opening Day Post Development horizons.

  • The Existing analysis indicates that all

study area intersections are currently

  • perating within acceptable capacity

parameters therefore no intersection improvements are required to accommodate the existing traffic.

March 21, 2018 11

slide-12
SLIDE 12

Transportation

The Post Development intersection capacity analysis indicated:

  • All study area intersections will

continue operating within acceptable capacity parameters therefore no intersection improvements are required to accommodate the proposed development.

  • A sensitivity analysis was completed to

determine the effect of a higher percentage of vehicles utilizing the main site access, specifically 70% to the main access and 30% to the secondary access. The intersection

  • f the Main Site Access/Arbour Lake

Road NW will continue operating within acceptable capacity parameters as a stop controlled intersection

  • Signalization is not required at the site

access intersections with Arbour Lake Road NW.

March 21, 2018 12

slide-13
SLIDE 13

Sanitary Servicing

  • Sanitary Servicing Study completed by

Pasquini and Associates

  • Sanitary sewer pipe capacity is

reviewed under existing and post development scenarios.

  • Any infrastructure replacements will be

addressed in due course as required by the City of Calgary

  • Therefore, service won’t be

interrupted.

March 21, 2018 ALCA Town Hall Meeting 13

slide-14
SLIDE 14

Fulfillment of Municipal Development Plan Goals (including the Developed Areas Guidebook)

1. The plan proposes to sensitively intensify the existing community of Arbour Lake in order to leverage the City’s existing capital investments and location of major employment centres. 2. Shaping a more compact urban form is an overarching city-wide strategic goal of the City. 3. Aligns with the MDP’s intent to integrate land use planning and transit investments by providing residential densities in areas served by existing transit service. 4. The plan proposes a diverse housing mix and varying built forms. This aligns with the MDP’s intent to encourage a broad range of housing options through intensification and redevelopment of the Developed Area. 5. The plan will maintain existing connections to the community of Arbour Lake by providing direct road and pathway connections to existing amenities, exceeding the connectivity expectations

  • utlined in the MDP.

March 21, 2018 ALCA Town Hall Meeting 14

slide-15
SLIDE 15

REVISED SUBMISSION

DECEMBER 2018

slide-16
SLIDE 16

Community Engagement What we heard?

  • Citizens expressed concern about the

proposed locations of apartment buildings and the potential for them to block existing views from their homes.

  • Citizens mentioned that they would like

to see additional access points throughout the area, to improve walkability.

  • Concerns relating to the density of the

Plan Area

March 21, 2018 ALCA Town Hall Meeting 16

slide-17
SLIDE 17

Major Changes – Location/Configuration of Apartment Buildings

March 21, 2018 ALCA Town Hall Meeting 17

slide-18
SLIDE 18

Major Changes – New Pedestrian Connections

March 21, 2018 ALCA Town Hall Meeting 18

slide-19
SLIDE 19

Concept Plan Revised Submission

  • Similar to the original submission in

terms of uses and units

  • Density is appropriate given close

proximity to Crowfoot LRT station and Crowfoot Commercial Centre

  • Southeast multi-residential now

provides an opportunity for commercial uses (i.e. a small day care facility or a coffee shop near the park)

  • Improved connections through the

multi-residential sites to Arbour Lake Road NW

  • Relocated apartment buildings to

maintain existing views from nearby residents

March 21, 2018 ALCA Town Hall Meeting 19

slide-20
SLIDE 20

NEXT STEPS

Spring/Summer 2018