aeso 2018 iso tariff consultation
play

AESO 2018 ISO Tariff Consultation January 30, 2017 AESO Office, - PowerPoint PPT Presentation

AESO 2018 ISO Tariff Consultation January 30, 2017 AESO Office, Calgary Public Agenda Introduction and objectives (slide 1-4) Transmission cost causation study preliminary results (slide 5-36) Point-of-delivery cost function


  1. AESO 2018 ISO Tariff Consultation January 30, 2017 AESO Office, Calgary Public

  2. Agenda • Introduction and objectives (slide 1-4) • Transmission cost causation study preliminary results (slide 5-36) • Point-of-delivery cost function database preliminary results and discussion (slides 37-61) • Rider C / Deferral Account Reconciliation (DAR) / Rates Update (slide 62-80) • Summary of comments from previous session (slides 81-82) • Application process and next steps (slides 83-85) • Discussion and wrap-up (slide 86) Please feel free to ask questions during presentation Public 1

  3. Stakeholder session objectives • Enhance understanding of ISO tariff application • Review technical results of a number of analytical exercises by the AESO • Share information prior to filing of 2018 ISO tariff application • Gather feedback to ensure tariff application provides all information stakeholders require • Review application timeline and next steps Public 2

  4. Applications currently in progress • Directions 5-8 on advancement costs and related provisions – Decision 3473-D02-2015 issued on August 26, 2015 – Process letter issued on October 22, 2015 with additional information on process in the new year [2016] – Awaiting Commission follow-up • 2015 Deferral Account Reconciliation application – Currently before the Commission in Proceeding 21735 – Interim settlement was approved and occurred in October 2016 – Hearing held on December 13 and 14, 2016 – Decision expected mid-March Public 3

  5. Applications currently in progress • 2017 ISO tariff update – Currently before the Commission in Proceeding 22093 – Interim, refundable approval for January 1, 2017 issued by Commission on December 2, 2016 – Still some matters before the Commission – Final approval expected in 2017 Public 4

  6. Transmission Cost Causation Study Preliminary Results Raj Sharma Public 5

  7. Plan for 2018–2020 Transmission Cost Causation Study • The AESO included a 2014-2016 transmission cost causation study prepared by London Economics International (“LEI”) in its 2014 ISO tariff application – The study established the inputs and methodology for a comprehensive cost causation study that used both capital cost and operating and maintenance cost data – A negotiated settlement process was used with participants and approved by the Commission • The AESO proposed to update the LEI study itself using identical methodology with functionalization by voltage and classification by minimum system approach (in August 2015) 6

  8. 2014-2016 Transmission Cost Causation Study • The 2014-2016 Cost Causation Negotiated Settlement Agreement was approved as filed November 27, 2013 • In accordance with agreement, an updated study was filed January 21, 2014 • Results of this study set functionalization and classification values for ISO tariff for 2014, 2015, 2016 (and 2017). 7

  9. Scope of 2014-2016 Transmission Cost Causation Study Scope included: • Functionalization of capital costs by voltage methodology (including use of low-side voltage to functionalize substation costs) • Functionalization of operating and maintenance (O&M) costs by specific allocators for most cost components, and functionalization of non-capitalized general and administration (G&A) costs in proportion to O&M costs • Weighting of capital and O&M costs over 2014-2016 • Classification of bulk system and regional system costs by minimum system methodology 8

  10. Capital Functionalization Method in 2014- 2016 Transmission Cost Causation Study • Functionalizing individual line and individual substation facilities: – Point of Delivery: radial line and delivery substation – Bulk: remaining facilities 240kV and over – Regional: remaining facilities below 240kV 9

  11. Capital Functionalization in 2014-2016 Transmission Cost Causation Study Function Year Total Bulk Regional POD 2014 $6.4 billion $2.2 billion $1.9 billion $10.5 billion 2015 $9.3 billion $2.6 billion $2.1 billion $14.0 billion 2016 $9.9 billion $2.7 billion $2.2 billion $14.7 billion 10

  12. O&M Functionalization Method in 2014- 2016 Transmission Cost Causation Study • Capital related costs: depreciation, return, income tax, structure payments, linear and property taxes and capital related offsets • Non-capital costs: labour, G&A, fuel and variable O&M for isolated generation and revenue offsets to labour costs – Isolated generation cost as regional and POD using capital cost functionalization ratio – Control center operations cost based on number of lines and transformers – Vegetation management cost based on line brushing allocator – Substation cost based on transformers – Overhead line and miscellaneous cost based on km of line – Net salaries and wages allocated to groups using proportion of full time equivalents (FTEs) and then further to functions 11

  13. O&M Functionalization in 2014-2016 Transmission Cost Causation Study Function Year Total Bulk Regional POD 2014 $35.3 million $66.6 million $68 million $169.9 million 12

  14. Combined (Capital and O&M) Functionalization in 2014-2016 Transmission Cost Causation Study Ratio of Non-Capital to Capital Costs Type 2014 2015 2016 Non-Capital 19.5% 18.0% 16.3% Capital 80.5% 82.0% 83.7% Combined Functionalization Function Year Bulk Regional POD 2014 53.2% 24.2% 22.6% 2015 58.4% 22.2% 19.4% 59.4% 21.5% 19.1% 2016 13

  15. Functionalization in 2014-2016 Transmission Cost Causation Study – Other Items • Deduct Regulated Generating Unit Connection Charge (RGUCC) revenue from bulk function revenue requirement for the year 14

  16. Functionalization in 2014-2016 Transmission Cost Causation Study Function Year Bulk Regional POD 2014 52.8% 24.4% 22.8% 2015 58.2% 22.3% 19.5% 2016 59.2% 21.6% 19.2% 15

  17. Classification Methodology in 2014-2016 Transmission Cost Causation Study • Bulk classification: – Ratio of per kM cost of 2x795 ACSR and 2x1033 ACSR 240kV conductor – Ratio of per kM cost of 3x1590 ACSR and 2x2156 ACSR 500kV conductor – Ratio of cost of basic and high efficiency transformer • Regional classification: – Ratio of per kM cost of 1x266 ACSR and 1x477 ACSR 138kV conductor – Ratio of cost of basic and high efficiency transformer 16

  18. Classification in 2014-2016 Transmission Cost Causation Study Function Classification Bulk Regional Demand 93.1% 87.4% Energy 6.9% 12.6% 17

  19. Scope of 2018-2020 Transmission Cost Causation Study • Update of 2014-2016 transmission cost causation study • Using identical methodology • Using same data sources, plus a few additional sources • For years 2018-2020 18

  20. Process for 2018-2020 Transmission Cost Causation Study • Update inputs and conduct 2018-2020 transmission cost causation study in 2016 • Present draft results to stakeholders in January 2017 • Include the study in the 2018 ISO tariff application 19

  21. Preliminary 2018 Functionalization - Capital Capital Cost Functionalization Function TOTAL Bulk Regional POD $10.6 billion $4.4 billion $3.1 billion $18.1 billion 20

  22. Preliminary 2018 Functionalization – O&M 2014 O&M Cost Functionalization Function Total Bulk Regional POD $37.3 million $64.3 million $67.1 million $168.8 million 21

  23. Preliminary 2018 Functionalization – Combined (Capital and O&M) Ratio of Non-Capital to Capital Costs Non-Capital 13.2% Capital 86.8% Combined Functionalization Function Bulk Regional POD 53.5% 26.2% 20.3% 22

  24. Preliminary 2018 Functionalization – Other Items • Deduct Regulated Generating Unit Connection Cost (RGUCC) revenue from bulk function revenue requirement for the year 23

  25. Preliminary 2018 Functionalization Function Bulk Regional POD 53.4% 26.3% 20.3% 24

  26. Preliminary 2019 Functionalization - Capital Capital Cost Functionalization Function TOTAL Bulk* Regional POD $10.5 billion $4.5 billion $3.3 billion $18.3 billion 25

  27. Preliminary 2019 Functionalization – O&M 2014 O&M Cost Functionalization Function Total Bulk Regional POD $37.3 million $64.3 million $67.1 million $168.8 million 26

  28. Preliminary 2019 Functionalization – Combined (Capital and O&M) Ratio of Non-Capital to Capital Costs Non-Capital 12.2% Capital 87.8% Combined Functionalization Function Bulk Regional POD 53.2% 26.1% 20.7% 27

  29. Preliminary 2019 Functionalization – Other Items • Deduct Regulated Generating Unit Connection Cost (RGUCC) revenue from bulk function revenue requirement for the year • Add Fort McMurray West 500kV transmission project (“CP” project) revenue requirement to bulk function revenue requirement for the year 28

  30. Preliminary 2019 Functionalization Function Bulk Regional POD 55.0% 25.1% 19.9% 29

  31. Preliminary 2020 Functionalization - Capital Capital Cost Functionalization Function TOTAL Bulk* Regional POD $10.4 billion $4.8 billion $3.5 billion $18.7 billion 30

  32. Preliminary 2020 Functionalization – O&M O&M Cost Functionalization Function Total Bulk Regional POD $37.3 million $64.3 million $67.1 million $168.8 million 31

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend