AESO 2018 ISO Tariff Transmission Wire Cost Allocation Issues - - PowerPoint PPT Presentation

aeso 2018 iso tariff
SMART_READER_LITE
LIVE PREVIEW

AESO 2018 ISO Tariff Transmission Wire Cost Allocation Issues - - PowerPoint PPT Presentation

AESO 2018 ISO Tariff Transmission Wire Cost Allocation Issues Current Approach Bulk system defined as lines operating at 240kV and above. Allocated using a 12 monthly Coincident Peak Allocator (with each of 12 months based on a single


slide-1
SLIDE 1

AESO 2018 ISO Tariff

Transmission Wire Cost Allocation Issues

slide-2
SLIDE 2
  • Bulk system defined as lines operating at 240kV

and above.

  • Allocated using a 12 monthly Coincident Peak

Allocator (with each of 12 months based on a single hour)

  • Regional system defined as lines operating

below 240kV

  • Allocated using Non-Coincident Peak (NCP)

Allocator

2

Current Approach

slide-3
SLIDE 3

3

Concerns with Current Approach

  • Does resulting allocation fairly reflect cost

causation?

  • Based on old vertically integrated centrally

planned concepts

  • Alberta now de-segregated with distributed

independent generation

  • HVDC is part of significant changes to system

topology and trade

  • Does allocation method provide stable results?
  • The use of CP based on single hour allows

gaming and instabilities.

slide-4
SLIDE 4

4

Requested Sensitivity Analysis

  • 1. For cost allocation purposes redefine

“bulk” and “regional” system so that:

  • The bulk system comprises HVDC and AC

lines operating above 240kV only

  • Regional systems AC lines operating up to and

including 240kV

  • Provide the resulting cost allocation and tariff

change distributions by customer class

slide-5
SLIDE 5

5

Requested Sensitivity Analysis

  • 2. Modify the existing 12 CP allocators:
  • So that the allocations for each of the 12

months are based on the mean of the 12 highest hourly peak demands within that month.

  • Provide the resulting cost allocation and tariff

change distributions by customer class

slide-6
SLIDE 6

Requested Sensitivity Analysis

6

  • 3. Combine both modifications suggested in 1

and 2, and provide:

  • the resulting costs allocation
  • Tariff change distributions by customer class
slide-7
SLIDE 7

Conclusion

7

It is the UCA’s view that completion of the requested analyses will assist in the review of a functionalization and cost allocation process that better reflects the nature of Alberta’s evolving transmission.

slide-8
SLIDE 8

Questions

8