ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION April 7, - - PowerPoint PPT Presentation

acrs meeting with the u s nuclear regulatory commission
SMART_READER_LITE
LIVE PREVIEW

ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION April 7, - - PowerPoint PPT Presentation

ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION April 7, 2005 OVERVIEW GRAHAM B. WALLIS Overview Major Accomplishments Since our last meeting with the Commission on June 2, 2004, we issued 24 Reports. Topics included:


slide-1
SLIDE 1

ACRS MEETING WITH THE U.S. NUCLEAR REGULATORY COMMISSION

April 7, 2005

slide-2
SLIDE 2

OVERVIEW

GRAHAM B. WALLIS

slide-3
SLIDE 3

3

Overview

Major Accomplishments Since our last meeting with the

  • Commission on June 2, 2004, we

issued 24 Reports. Topics included:

  • Draft Final 10 CFR 50.69, “Risk-

– Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Plants”

slide-4
SLIDE 4

4

Overview

Construction authorization – request for the MOX Fuel Fabrication Facility Proposed resolution of Generic – Safety Issue 185, “Control of Recriticality Following Small- Break LOCAs in PWRs” Draft proposed rule on post-fire –

  • perator manual actions
slide-5
SLIDE 5

5

Overview

Future Plant Designs Completed review of the AP1000

  • design

Reviewed pre-application

  • submittals for ACR-700 and

ESBWR designs Issued AP1000 Lessons Learned

  • Letter
slide-6
SLIDE 6

6

Overview

Future Plant Designs Reviewing proposed technology-

  • neutral framework document for

new plant licensing Reviewing early site permit

  • applications (North Anna, Clinton,

and Grand Gulf sites)

slide-7
SLIDE 7

7

Overview

Future Activities Risk-informed and performance-

  • based regulation

Thermal-hydraulic codes

  • Materials and metallurgy
  • Advanced reactor designs
  • Rules and regulatory guidance
  • Resolution of GSIs
  • Revisions to SRP
slide-8
SLIDE 8

8

Overview

Future Activities High-burnup fuel issues

  • Use of MOX fuel in commercial
  • reactors

Report on the NRC Safety

  • Research Program

Assessment of research quality

  • Core power uprates
slide-9
SLIDE 9

9

Overview

Future Activities License renewal applications

  • Digital I&C matters
  • Fire protection
  • Human factors and human
  • reliability assessment

Operating plant issues

slide-10
SLIDE 10

PWR SUMP PERFORMANCE

Graham B. Wallis

slide-11
SLIDE 11

11

PWR Sump Performance

LBLOCA Event Occurring in a PWR ECCS Sump Pit and Debris Screens

PWR LBLOCA and Sump

slide-12
SLIDE 12

12

PWR Sump Performance

Staff and Industry Activities Regulatory Guide 1.82, Revision 3

  • Bulletin 2003-01
  • Generic Letter 2004-02
  • NRC Research Reports
  • Technical Basis Report

– Pressure drop through filter beds – Chemical effects – NEI Guidance Document and Staff

  • SER
slide-13
SLIDE 13

13

PWR Sump Performance

ACRS ISSUES RG 1.82, Rev. 3 does not describe

  • methods acceptable to the staff

for meeting the requirements Generic Letter asks for

  • calculations which are dependent
  • n adequate technical guidance
slide-14
SLIDE 14

14

PWR Sump Performance

ACRS ISSUES Guidance contains errors and

  • inadequacies

Alternative solutions, possibly

  • risk-informed

Need for additional research

slide-15
SLIDE 15

RISK-INFORMING 10 CFR 50.46

George E. Apostolakis

slide-16
SLIDE 16

16

Break Size LBDEGB Current requirements are independent of the frequency of break size

Risk-Informing 10 CFR 50.46

slide-17
SLIDE 17

17

Break Size TBS 10-5 Current Requirements ACRS supports: Maintaining

  • Coolable Geometry

Developing a new

  • RG

Use of RG 1.174

  • “Risk bundling”
  • In a risk-informed 50.46, the

frequency of break size determines the requirements LBDEGB

Risk-Informing 10 CFR 50.46

slide-18
SLIDE 18

18

Break Size TBS 10-5 Uncertainties in expert opinions create uncertainty in TBS determination; ACRS supports the development of a quantitative understanding of the possible risk benefits as a function of the transition break size LBDEGB

Risk-Informing 10 CFR 50.46

slide-19
SLIDE 19

19

Risk-Informing 10 CFR 50.46

ACRS Comments and Recommendations

The NUREG Report and the

  • proposed rule should be issued for

public comment Must demonstrate that coolable

  • geometry is maintained for breaks

greater than the TBS Any changes to the licensing

  • basis should be consistent with

RG 1.174

slide-20
SLIDE 20

20

Risk-Informing 10 CFR 50.46

ACRS Comments and Recommendations

Bundling of changes in risk due to

  • unrelated changes in the licensing

basis should be allowed Expert opinion elicitations should

  • seek to produce a composite

distribution that represents the group’s (and hopefully the community’s) judgment and properly reflect the associated uncertainties

slide-21
SLIDE 21

21

Risk-Informing 10 CFR 50.46

ACRS Comments and Recommendations

Eliciting expert opinions provides

  • input to the decisionmaking

process, i.e., the selection of the TBS A quantitative understanding of

  • the possible risk benefits as a

function of the TBS is needed

slide-22
SLIDE 22

PTS REEVALUATION PROJECT — Technical Basis for Revision

  • f the PTS Screening

Criterion

William J. Shack

slide-23
SLIDE 23

23

PTS Reevaluation Project

  • Irradiation makes reactor pressure

vessels more susceptible to failure by thermal shock under some accident sequences PTS rule intended to prevent such

  • failures
slide-24
SLIDE 24

24

PTS Reevaluation Project

Reevaluation project includes:

  • Comprehensive study of scenarios

– that lead to PTS More realistic evaluation of thermal – hydraulics of PTS scenarios More realistic distributions for flaw – density and geometry Improved PFM analysis code, – FAVOR Systematic consideration of – uncertainties

slide-25
SLIDE 25

25

PTS Reevaluation Project

Materials and Metallurgy

September 2000 January 2002 May 2002 November 2004

Thermal- Hydraulic Phenomena

January 2001 May 2002 December 2002 November 2004

Reliability & Probabilistic Risk Assessment

May 2002 November 2004

October 2000 February 2001 February 2002 (Letter to EDO, Feb. 14, 2002) July 2002 (Letter to EDO, July 18, 2002) February 2003 (Letter to EDO, Feb 21, 2003) December 2004 March 2005 (Letter to EDO, March 11, 2005)

Subcommittee Meetings Full Committee Meetings

slide-26
SLIDE 26

26

PTS Reevaluation Project

ACRS Recommendation The acceptance criterion for vessel

  • failure frequency should be based
  • n considerations of large early-

release frequency and not on core damage frequency

slide-27
SLIDE 27

27

PTS Reevaluation Project

ACRS Conclusions Current PTS screening criterion is

  • very conservative
  • Improvements to the PFM code

(FAVOR) and characterization of irradiated materials and development

  • f more realistic flaw distributions

may also provide a basis for reducing unnecessary conservatism in limits

  • n heatup and cooldown
slide-28
SLIDE 28

28

PTS Reevaluation Project

ACRS Conclusions Initial draft technical basis report

  • needed revision to describe more

clearly the basic phenomena, issues, approaches, and conclusions ACRS supported plans for peer

  • review basis
slide-29
SLIDE 29

29

PTS Reevaluation Project

ACRS Conclusions External peer review was valuable,

  • and the staff response to the

criticisms and questions has strengthened the technical Documentation for the project is not

  • yet final, but significant progress has

been made Comprehensive technical basis has

  • been developed to revise the PTS

Rule

slide-30
SLIDE 30

LICENSE RENEWAL/ EXTENDED POWER UPRATES

MARIO V. BONACA

slide-31
SLIDE 31

31

Performed four interim

  • (subcommittee) reviews and two

final (full committee) reviews since June 2004 Will perform two interim reviews

  • and four final reviews during the

remainder of CY 2005 Will perform seven interim

  • reviews and six final reviews in

CY 2006

License Renewal

slide-32
SLIDE 32

32

Reviewing updates to Generic

  • License Renewal Guidance

documents (SRP, GALL Report, and Regulatory Guide) Continue to review improvements

  • to the license renewal process

Will review Interim Staff

  • Guidance on license renewal

issues

License Renewal

slide-33
SLIDE 33

33

ACRS comments and

  • recommendations resulted in:

Proposed GL concerning failures –

  • f inaccessible/underground

cables that disable accident mitigation systems Inclusion of adequate – information on TLAAs in applications and independent staff evaluation of TLAAs associated with reactor vessel embrittlement

License Renewal

slide-34
SLIDE 34

34

Inclusion of steam dryers in scope – for Dresden and Quad Cities Proposed revisions to GALL – Report to ensure that Inspection frequency for buried

  • piping is adequate

Aging management of steam

  • dryer cracking due to flow

induced vibration is addressed

License Renewal

slide-35
SLIDE 35

35

Evaluation of operating – experience at EPU levels RES study on the need for – phosphate limits at sites of plants applying for license renewal

License Renewal

slide-36
SLIDE 36

36

Extended Power Uprates

Waterford 3 8% EPU

  • First use of EPU Review Standard
  • RS-001

Similar to EPU for ANO-2

  • Large-transient testing should be
  • waived because other approaches

are more appropriate in this case

slide-37
SLIDE 37

37

Extended Power Uprates

Waterford 3 Generic concern identified

  • regarding boron concentration

and precipitation EPU should be authorized

slide-38
SLIDE 38

38

Extended Power Uprates

Upcoming EPU Requests Vermont Yankee

  • Browns Ferry
  • Beaver Valley
  • Hope Creek
  • Ginna
slide-39
SLIDE 39

DIFFERENCES IN REGULATORY APPROACHES BETWEEN U.S. AND OTHER COUNTRIES

Dana A. Powers

slide-40
SLIDE 40

40

Differences In Regulatory Approaches

  • Focus on BWRs and PWRs

Baseline Report by H. Nourbakhsh

  • Strong influence of the U.S.
  • regulatory system in many

countries Great similarities in accepting the

  • principles of traditional

deterministic approach

slide-41
SLIDE 41

41

Differences In Regulatory Approaches

  • Differences in use of quantitative

risk estimates

  • Greater attention by Europeans to

severe accident management measures No major differences in response

  • to:

Sump blockage – Vessel head penetration issue –

slide-42
SLIDE 42

42

Differences In Regulatory Approaches

  • The ACRS will endeavor to keep

the Commission informed of significant differences in regulatory requirements between United States and other countries that come to its attention

slide-43
SLIDE 43

43

Abbreviations

ACR Advanced CANDU Reactor ACRS Advisory Committee on Reactor Safeguards ANO Arkansas Nuclear One BWR Boiling Water Reactor CFR Code of Federal Regulations CY Calendar Year ECCS Emergency Core Cooling System EPU Extended Power Uprate ESBWR Economic Simplified Boiling Water Reactor GALL Generic Aging Lessons Learned Report GL Generic Letter GSI Generic Safety Issue I&C Instrumentation and Control LBDEGB Large Break Double Ended Guillotine Break LBLOCA Large Break Loss-of- Coolant Accident

slide-44
SLIDE 44

44

Abbreviations

LOCA Loss-of-Coolant-Accident MOX Mixed Oxide NEI Nuclear Energy Institute NPSH Net Positive Suction Head NRC Nuclear Regulatory Commission PFM Probabilistic Fracture Mechanics PTS Pressurized Thermal Shock PWR Pressurized Water Reactor RES Office of Nuclear Regulatory Research RG Regulatory Guide RS Review Standard SER Safety Evaluation Report

slide-45
SLIDE 45

45

Abbreviations

SRM Staff Requirements Memorandum SRP Standard Review Plan TBS Transition Break Size TLAAs Time Limited Aging Analyses U.S. United States