ACRS MEETING WITH ACRS MEETING WITH THE U.S. NUCLEAR THE U.S. - - PowerPoint PPT Presentation

acrs meeting with acrs meeting with the u s nuclear the u
SMART_READER_LITE
LIVE PREVIEW

ACRS MEETING WITH ACRS MEETING WITH THE U.S. NUCLEAR THE U.S. - - PowerPoint PPT Presentation

ACRS MEETING WITH ACRS MEETING WITH THE U.S. NUCLEAR THE U.S. NUCLEAR REGULATORY REGULATORY COMMISSION COMMISSION June 4, 2009 MARIO V. BONACA OVERVIEW Accomplishments Since our last meeting w ith the Commission on November 7,


slide-1
SLIDE 1

ACRS MEETING WITH ACRS MEETING WITH THE U.S. NUCLEAR THE U.S. NUCLEAR REGULATORY REGULATORY COMMISSION COMMISSION

June 4, 2009

slide-2
SLIDE 2

OVERVIEW

MARIO V. BONACA

slide-3
SLIDE 3

3

Accomplishments

  • Since our last meeting w ith the

Commission on November 7, 2008, w e issued 16 Reports

  • Topics included:

– Containment accident pressure credit issue – Selected Chapters of the ESBWR design certification application

slide-4
SLIDE 4

4

  • Vogtle early site permit

application and limited w ork authorization

  • Technical basis for revising

10 CFR 50.46(b) loss-of-coolant embrittlement criteria for fuel cladding materials

  • Pressurized thermal shock rule
slide-5
SLIDE 5

5

  • Regulatory Guide on managing

the safety/security interface

  • Regulatory Guide on cyber

security programs for nuclear facilities

  • Options to revise NRC regulations

based on ICRP recommendations

slide-6
SLIDE 6

6

License Renew al

Since November 2008:

  • Completed review of the Vogtle

license renew al application

  • Performed interim review of four

applications (Beaver Valley, Indian Point, Three Mile Island Unit 1, and Susquehanna)

  • Performed interim review of the

NIST research reactor

slide-7
SLIDE 7

7

  • Discussed w ith the staff the

status of license renew al activities, interim staff guidance, and implementation of the recommendations from the self assessment

slide-8
SLIDE 8

8

  • Will perform final review of six

applications, including NIST research reactor, during CY2009

  • Will review updates to the GALL

Report and license renew al guidance documents

slide-9
SLIDE 9

9

Extended Pow er Uprates

  • We have expressed concerns

w ith credit for containment accident pressure associated w ith EPUs in our February 16, 2007, and March 18, 2009, reports

  • We w ill review the Brow ns Ferry

Unit 1 EPU after receiving the complete safety evaluation report

slide-10
SLIDE 10

10

  • Brow ns Ferry Units 2 and 3 EPU

application review has been deferred by the staff at the request of TVA. ACRS w ill review this application after receiving the complete safety evaluation report.

slide-11
SLIDE 11

11

New Plant Activities

  • Completed review of the SER

Chapters for the ESBWR design certification application

  • Provided six interim letters
  • n 20 Chapters
  • Will review the resolution of
  • pen items and the ACRS

issues and the final SER

slide-12
SLIDE 12

12

  • Completed review of the early

site permit application and limited w ork authorization for the Vogtle plant

  • Review ing topical reports

associated w ith the US-APWR design

  • Review ing revisions to the

AP1000 Design Control Document

slide-13
SLIDE 13

13

  • Review of the SER on the EPR

design certification application w ill start in July 2009

  • Review of the SER on North Anna

COL application, referencing ESBWR design w ill begin in June 2009

slide-14
SLIDE 14

14

  • Will continue to interact w ith

the NRO staff to establish schedule for review of design certification and COL applications to ensure timely completion of ACRS review

slide-15
SLIDE 15

15

Ongoing/Future Activities

  • Advanced reactor research

plan

  • Combined license

applications

  • Design certification

applications

  • Digital instrumentation and

control systems

slide-16
SLIDE 16

16

  • Extended pow er uprates
  • Fire protection
  • High-burnup fuel and cladding

issues

  • Human reliability analysis
  • License renew al applications
  • New fuel designs and materials
  • Next generation nuclear plant

(NGNP) project

  • Pellet clad interaction failure

under EPU conditions

slide-17
SLIDE 17

17

  • Research quality assessment
  • Revisions to regulatory guides

and SRPs

  • Risk-Informing the regulations
  • Safeguards and security matters
  • Safety culture
  • Safety research program report
  • Seismic issues
slide-18
SLIDE 18

18

  • State-of-the-Art Reactor

Consequence Analyses (SOARCA) Project

  • Sump strainer issues
  • TRACE code applicability to

new reactors

  • Waste management, radiation

protection, decommissioning, and materials issues

  • Watts Bar Unit 2 operating

license

slide-19
SLIDE 19

19

Crediting Containment Accident Pressure in the NPSH Calculations

William J. Shack

slide-20
SLIDE 20

20

NPSH Margin NPSH Margin

Satisfactory performance of the

ECCS and containment heat removal system pumps requires adequate NPSH margin

RG 1.1: Emergency core cooling

and containment heat removal systems should be designed so that adequate NPSH is provided to system pumps assuming no increase in containment pressure from an accident

slide-21
SLIDE 21

21 “…desirable that ECCS function

“…desirable that ECCS function not depend on containment not depend on containment integrity, so that some low - integrity, so that some low - probability event involving a major probability event involving a major loss of containment integrity ... loss of containment integrity ... not lead automatically to core not lead automatically to core melt” melt” (D

(Decem ecember 18, 1972 A ber 18, 1972 ACRS R CRS Report) eport)

Defense in Depth/Additional Defense in Depth/Additional Safety Margin Safety Margin

slide-22
SLIDE 22

22

  • Sump strainer blockage is a

Sump strainer blockage is a complex issue. Difficult to complex issue. Difficult to provide a demonstrably provide a demonstrably “conservative” “conservative” answ er. Desirable answ er. Desirable to maintain margin to address to maintain margin to address uncertainties uncertainties

slide-23
SLIDE 23

23

Extended Pow er Uprates

  • For some plants, demonstrating

adequate NPSH for EPU

  • peration w ould require:

–Credit for all of the predicted containment accident pressure –Reliance on operator action to maintain NPSH

slide-24
SLIDE 24

24

– Reliance on COP credit for long duration

  • In some cases, pump cavitation

is expected even after crediting all of the predicted accident pressure

slide-25
SLIDE 25

25

ACRS Position on COP Credit

  • NRC should seek to maintain

independence of containment function and accident mitigation and additional margin for NPSH

slide-26
SLIDE 26

26

ACRS MARCH 18, 2009 LETTER

  • Intended primarily to address

voluntary requests for a change in the licensing basis

  • SRP should be revised to state

that, if COP credit is granted based on risk information, all subsequent licensing applications involving COP credit should also include risk information

slide-27
SLIDE 27

27

  • Demonstrate that it is not

practical to reduce or eliminate the need for COP credit by hardw are changes or requalification of equipment

  • If credit for COP is granted, it

should be limited in amount and duration

slide-28
SLIDE 28

28

  • If operator actions are required

to maintain overpressure, it must be demonstrated they can be performed reliably, and that any increase in risk is acceptably small

slide-29
SLIDE 29

29

  • Continue to use guidance in

RG-1.82 Rev. 3 and the licensing- basis analyses assumptions and methods to show that the available NPSH exceeds that needed for the ECCS and containment heat removal system pumps

Recommendation on Analyses and Revision of RG-1.82

slide-30
SLIDE 30

30

  • If COP credit based on the

licensing-basis analyses is not small and limited in duration, RG-1.82 should be revised to request additional analyses and information that demonstrate the COP credit needed is small and limited in duration on a more realistic basis

slide-31
SLIDE 31

31

  • Such information could include

thermal-hydraulic analyses that reduce conservatism but account for uncertainties and PRA results that show that large COP credit is needed only for very low -probability events

  • If operator actions are required,

it should be show n they can be implemented in procedures and performed reliably and that any resulting increases in risk are small

slide-32
SLIDE 32

32

ACRS Position on Decisionmaking

  • Granting COP credit should

depend on integrated decisionmaking that considers less conservative estimates of the COP credit; the likelihood of scenarios that require COP credit; and the operator actions required to maintain NPSH

slide-33
SLIDE 33

33

Conclusion

  • Our March 18, 2009 letter is

consistent w ith long-standing ACRS position

  • Expect to provide technical input

to the development of Revision 4 to RG-1.82

slide-34
SLIDE 34

34

  • Had a briefing on a draft of the

staff’s White Paper. While comprehensive, it did not resolve the ACRS concerns

  • In the review of any particular

application for credit, the fidelity

  • f containment and core

calculations need to be taken into account

slide-35
SLIDE 35

35

  • BWROG submitted and staff

review ed a more realistic methodology for evaluating COP credit

  • ACRS aw aits the staff’s safety

evaluation of the BWROG methodology

slide-36
SLIDE 36

Pressurized Thermal Shock Rule

  • J. Sam Armijo
slide-37
SLIDE 37

37

Rule Requirements

  • This rule requires plant-

specific evaluations of vessel embrittlement and flaw

  • distributions. It also requires

evaluation of new surveillance data to ensure detection of unexpected embrittlement trends

slide-38
SLIDE 38

38

Three Plant Study

  • The screening limits are based

upon a detailed study of the PTS challenges at three plants

  • Medium and large LOCAs w ere

the major contributors to the through-w all cracking frequency (TWCF), w hich is the risk metric

slide-39
SLIDE 39

39

Generalization

  • A generalization study

evaluated the variability of PTS challenges from internal events in plants not included in the detailed study

  • The likelihood and severity of

the important PTS challenges w ere determined to be representative of those for the entire fleet of PWRs

slide-40
SLIDE 40

40

  • A bounding analysis on the

effects of external events show ed that their contribution to TWCF w as less than that of internal events

  • Together w ith the

generalization study on internal events, this finding provides assurance that plant-specific analyses of PTS challenges are not needed

slide-41
SLIDE 41

41

  • The Committee concurs w ith

the staff’s conclusion that plant-specific evaluations of PTS challenges are not needed and that the screening criteria in 10 CFR 50.61a may be applied to the entire fleet of PWRs

slide-42
SLIDE 42

42

Recommendations

  • To aid in the implementation of

the rule, the staff should undertake an effort to verify and document the capability of NDE procedures that w ill be used to characterize the flaw distributions in reactor vessels

slide-43
SLIDE 43

43

  • An effort is needed to plan for

the most effective use of surveillance samples to ensure that any deviations from the current understanding of embrittlement trends in reactor vessels w ill be identified in a timely manner

slide-44
SLIDE 44

44

Digital I& C Matters

George E. Apostolakis

slide-45
SLIDE 45

45

  • Review ed Regulatory Guide

5.71, “Cyber Security Programs For Nuclear Facilities”

  • Review ed Digital I& C Interim

Staff Guidance 5, “Highly- Integrated Control Room- Human Factors Issues,” and 6, “Licensing Process”

slide-46
SLIDE 46

46

ACRS March 19, 2009 Report

  • RG-5.71 on cyber security should

not be published until it is revised to:

  • Provide a reference DI& C

computer, communication, and netw ork security framew ork that identifies assets, associated plant functions, vulnerabilities, interaction, and access pathw ays

slide-47
SLIDE 47

47

  • Include examples and more

specific guidance on how the requirements of 10 CFR 73.54 can be met

  • Ensure that the guidance

distinguishes betw een DI& C system and non-real-time information technology system architectures

slide-48
SLIDE 48

48

  • Address the issues of threat

assessment, dependency analysis, and the use of Probabilistic risk assessment

slide-49
SLIDE 49

49

ACRS April 21, 2009 Report

  • n Digital I& C Interim Staff

Guidance 5 and 6

  • Section 3, “Crediting Manual

Operator Actions in Diversity and Defense- in-Depth (D3) Analyses,”

  • f ISG-5 should be revised to

incorporate additional guidance

  • n the estimation methods of the

time required for operator action

slide-50
SLIDE 50

50

  • Increased rigor in the supporting

analyses should be required as the difference betw een the time available and the time required for operator action decreases

slide-51
SLIDE 51

51

  • Draft ISG-6 should not be issued

until Sections C and D are revised to specify that sufficient design detail be provided to ensure deterministic behavior and independence of each DI& C safety train

slide-52
SLIDE 52

Options to Revise NRC Regulations Regulations Based on ICRP Recommendations

Michael T. Ryan

slide-53
SLIDE 53

53

Staff Options

  • No changes to existing

framew ork

  • Update parts of regulations, not

previously revised, to conform to existing 10 CFR Part 20 concepts and quantities based on ICRP Publications 26 and 30

  • Begin to further align NRC’s

regulatory framew ork w ith ICRP Publication 103

slide-54
SLIDE 54

54

  • ACRS endorses the staff’s

preferred option 3, w hich w ould begin to move tow ard greater alignment betw een 10 CFR Parts 20 and 50 and Appendix I of Part 50 w ith recommendations in ICRP Publication 103

February 18, 2009 ACRS Report

slide-55
SLIDE 55

55

  • ACRS concurs w ith the staff

position that NRC’s current regulatory framew ork continues to provide adequate protection for the health and safety of w orkers, the public, and the environment

slide-56
SLIDE 56

56

  • The staff should continue its

participation in ICRP and other national and international committees and standards

  • rganizations
  • The NRC should not develop

separate radiation protection regulations for plant and animal species

slide-57
SLIDE 57

Progress on Progress on Recommendations of the Recommendations of the Independent External Independent External Review Panel on the Review Panel on the Materials Licensing Program Materials Licensing Program

Michael T. Ryan

slide-58
SLIDE 58

58 58

  • The staff has addressed each of

the recommendations of the Independent External Review Panel

  • The staff has developed Interim

Staff Guidance for review ing new license applications

  • Includes more detailed

information gathering and on-site applicant visits

slide-59
SLIDE 59

59 59

  • Staff is developing a process to

integrate the National Source Tracking and the Web-Based Licensing Systems as part of the License Verification System

  • Efforts are under w ay to

integrate all 37 Agreement States into this system

  • This integration w ill take time

and resources to complete and implement

slide-60
SLIDE 60

60 60

  • Staff is pursuing w ays to add

more detail to the physical security requirements as recommended by the Panel and w ill be addressed in currently planned rulemakings for larger sealed sources

slide-61
SLIDE 61

61 61

  • Adding Security w ith equal

emphasis as Health, Safety, and Environment for materials licensees w ill require a change in the culture of the Agency

  • The Agency and the Agreement

States share this responsibility

slide-62
SLIDE 62

62 62

  • The staff has plans to

accomplish the objectives developed from all of the Panel’s recommendations

  • Some short term goals have

already been accomplished

  • Additional progress w ill take

time and resources

slide-63
SLIDE 63

63

Abbreviations

ACRS Advisory Committee on Reactor Safeguards BWR Boiling w ater reactor BWROG Boiling Water Reactor Ow ners Group CFR Code of Federal Regulations COL Combined license COP Containment overpressure CY Calendar year D3 Diversity and defense in depth DI& C Digital Instrumentation and Control ECCS Emergency core cooling system EPR Evolutionary Pow er Reactor EPU Extended pow er uprate ESBWR Economic Simplified Boiling Water Reactor GALL Generic Aging Lessons Learned Report ICRP International Commission on Radiological Protection ESF Engineered safety features I& C Instrumentation and control ISG Interim staff guidance LOCA Loss-of-coolant accident NDE Non-destructive examination NGNP Next Generation Nuclear Plant NIST National Institute of Standards and Technology NPSH Net positive suction head NRC Nuclear Regulatory Commission NRO Office of New Reactors PRA Probabilistic risk assessment PTS Pressurized thermal shock PWR Pressurized w ater reactor RG Regulatory Guide SER Safety evaluation report SRP Standard Review Plan SOARCA State-of-the-Art Reactor Consequence Analyses TVA Tennessee Valley Authority TWCF Through-w all cracking frequency US-APWR United States – Advanced Pressurized Water Reactor