CAS October 2013 R.Schmidt
- Accidental and continuous beam losses
- Protection of the accelerator from beam losses
Machine Protection
Rüdiger Schmidt, CERN and ESS CAS Accelerator School October 2013 - Trondheim
Accidental and continuous beam losses Protection of the accelerator - - PowerPoint PPT Presentation
Machine Protection Rdiger Schmidt, CERN and ESS CAS Accelerator School October 2013 - Trondheim Accidental and continuous beam losses Protection of the accelerator from beam losses CAS October 2013 R.Schmidt CAS October 2013
CAS October 2013 R.Schmidt
Machine Protection
Rüdiger Schmidt, CERN and ESS CAS Accelerator School October 2013 - Trondheim
CAS October 2013 R.Schmidt
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 3
Protection from Energy and Power
when operating a system (Watt)
flow can lead to unwanted consequences
as accelerators
This lecture on Machine Protection is focused on preventing damage caused by particle beams
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 4
Content
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 5
LHC pp and ions 7 T eV/c – up to now 4 T eV/c 26.8 km circumference Energy stored in one beam 362 MJ
Switzerland Lake Geneva LHC Accelerator
(100 m down) SPS Accelerator
CMS, TOTEM ALICE LHCb ATLAS
CERN
Proton collider LHC – 362 MJ stored in one beam
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 6
LHC pp and ions 7 T eV/c – up to now 4 T eV/c 26.8 km Circumference Energy stored in one beam 362 MJ
Switzerland Lake Geneva LHC Accelerator
(100 m down) SPS Accelerator
CMS, TOTEM ALICE LHCb ATLAS
CERN
Proton collider LHC – 362 MJ stored in one beam
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 7
ESS Lund / Sweden – 5 MW beam power
Power of 5000 kW Drift tube linac with 4 tanks Low energy beam transport Medium energy beam transport Super-conducting cavities High energy beam transport
RFQ 352.2 MHz 75 keV 3 MeV 78 MeV 200 MeV 628 MeV 2500 MeV
Source LEBT RFQ MEBT DTL Spokes High β Medium β HEBT & Upgrade Target
2.4 m 4.0 m 3.6 m 32.4 m 58.5 m 113.9 m 227.9 m
352.21 MHz 704.42 MHz
As an example for a high intensity linear accelerator (similar to SNS and J-PARC)
~ 500 m
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 8 Power of 5000 kW Drift tube linac with 4 tanks Low energy beam transport Medium energy beam transport Super-conducting cavities High energy beam transport
RFQ 352.2 MHz 75 keV 3 MeV 78 MeV 200 MeV 628 MeV 2500 MeV
Source LEBT RFQ MEBT DTL Spokes High β Medium β HEBT & Upgrade Target
2.4 m 4.0 m 3.6 m 32.4 m 58.5 m 113.9 m 227.9 m
352.21 MHz 704.42 MHz
As an example for a high intensity linear accelerator (similar to SNS and J-PARC)
~ 500 m
ESS Lund / Sweden – 5 MW beam power
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 9
Energy stored in beam and magnet system
0.01 0.10 1.00 10.00 100.00 1000.00 10000.00 1 10 100 1000 10000
Energy stored in the beam [MJ] Momentum [GeV/c]
LHC 7.0 TeV LHC at injection ISR SNS LEP2 LHC ions TEVATRON SPS ppbar SPS transfer to RHIC proton LHC energy in magnets LHC 4.0 TeV SPS material test
Factor ~200
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 10
What does it mean ……… MJoule ?
360 MJ: the energy stored in
approximately to…
It matters most how easy and fast the energy is released !!
The energy of an 200 m long fast train at 155 km/hour corresponds to the energy of 360 MJ stored in one LHC beam.
0 0C to 100 0C
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 11
Consequences of a release of 600 MJ at LHC
Arcing in the interconnection 53 magnets had to be repaired The 2008 LHC accident happened during test runs without beam.
A magnet interconnect was defect and the circuit opened. An electrical arc provoked a He pressure wave damaging ~600 m of LHC, polluting the beam vacuum over more than 2 km.
Over-pressure Magnet displacement
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 12
Energy and Power density
Many accelerators operate with high beam intensity and/or energy
beam increased with time (from ISR to LHC)
power increases The emittance becomes smaller (down to a beam size of nanometer)
projects, with increased beam power / energy density (W/mm2 or J/mm2 ) and increasingly complex machines Even a small amount of energy can lead to some (limited) damage
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 13
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 14
Hazard and Risk for accelerators
Hazards are dormant or potential, with only a theoretical risk of
Consequences and possibility of an incident interact together to create RISK, can be quantified:
RISK = Consequences ∙ Probability
Related to accelerators
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 15
Example for ESS
the magnets stops deflecting the beam
pipe, possibly pollution of superconducting cavities
5 MW Beam
~ 160 m following the sc cavities
HEBT-S2
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 16
Example for LHC: SPS, transfer line and LHC
1 km
Beam is accelerated in SPS to 450 GeV (288 bunches, stored energy of 3 MJ) Beam is transferred from SPS to LHC Beam is accelerated in LHC to high energy (stored energy of 362 MJ)
Transfer line 3 km
LHC SPS
6911 m 450 GeV 3 MJ transfer to LHC
IR8
Fast extraction kicker Injection kicker
Transfer line
Injection kicker
IR2
Fast extraction kicker
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 17
Protection at injection
LHC circulating beam
Circulating beam in LHC
LHC vacuum chamber Transfer line vacuum chamber
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 18
LHC circulating beam
Beam injected from SPS and transfer line
Protection at injection
Beam from SPS Injection Kicker LHC injected beam
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 19
LHC circulating beam
Kicker failure (no kick)
Protection at injection
Beam from SPS Injection Kicker
Major damage to sc magnets, vacuum pipes, possibly LHCb / Alice experiments
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 20
LHC circulating beam
Beam absorbers take beam in case of kicker misfiring Transfer line collimators ensure that incoming beam trajectory is ok
Protection at injection
Beam from SPS Injection Kicker Set of transfer line collimators (TCDI) ~5σ Injection absorber (TDI) ~7σ
phase advance 900
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 21
LHC circulating beam
Beam absorbers take beam in case of kicker misfiring on circulating beam
Protection at injection
Injection Kicker Injection absorber (TDI) ~7σ Circulating beam – kicked out
phase advance 900
LHC circulating beam Set of transfer line collimators (TCDI) ~5σ
This type of kicker failure happened several times: protection worked
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 22
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 23
Beam losses and consequences
electrons of atoms in the material, exciting or ionizing the atoms => energy loss of traveling particle described by Bethe-Bloch formula.
particle cascades in materials, increasing the deposited energy
maximum of the hadron / electromagnetic shower
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 24
Energy loss: example for one proton in iron
(stainless steel, copper very similar)
Low energy few MeV, beam transport, RFQ for many machines SNS - ESS 1 – 3 GeV LHC 7 T eV
From Bethe- Bloch formula.
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 25
Beam losses and consequences
and no cooling
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 26
Heating of material with low energy protons
(3 MeV)
Temperature increase in the material: dTFe Np dEdxFe cFe_spec Fbeam
Fe
Temperature increase for a proton beam impacting on a Fe target: Beam size: h 1.00 mm and v 1.00 mm Iron specific heat: cFe_spec 440 J kg K Iron specific weight: Fe 7860 kg m3 Energy loss per proton/mm: dEdxFe 56.696 MeV mm Number of protons: Np 1.16 1012 Energy of the proton: Ep 0.003 GeV Temperature increase: dTFe 763K
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 27
Heating of material with high energy protons
(> GeV) Nuclear inelastic interactions (hadronic shower)
pions
large number of electromagnetic particles
its momentum and parameters of the material (atomic number, density, specific heat)
deposition
MARS
http://williamson-labs.com/ltoc/cbr-tech.htm
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 28
Maximum energy deposition in the proton cascade (one proton) : Emax_C 2.0 10 6
J kg Specific heat of graphite is cC_spec 710.6000 1 kg J K To heat 1 kg graphite by, say, by T 1500K , one needs : cC_spec T 1 kg 1.07 106 J Number of protons to deposit this energy is: cC_spec T Emax_C 5.33 1011 Maximum energy deposition in the proton cascade (one proton): Emax_Cu 1.5 10 5
J kg Specific heat of copper is cCu_spec 384.5600 1 kg J K To heat 1 kg copper by, say, by T 500K , one needs: cCu_spec T 1 kg 1.92 105 J Number of protons to deposit this energy is: cCu_spec T Emax_Cu 1.28 1010
Copper graphite
Damage of a pencil 7 TeV proton beam (LHC)
copper graphite
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 29
Beam losses and consequences
to beam impact (mechanical codes such as ANSYS, hydrodynamic codes such as BIG2 and others)
energy deposition is very high, and can lead to (limited) damage in case of beam impact
beam transport and RFQ
depending on spare situation
potential
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 30
Controlled SPS experiment
above damage limit for copper stainless steel no damage
below damage limit for copper
6 cm 25 cm
bunch train injected into LHC
V.Kain et al
A B D C
SPS experiment: Damage with 450 GeV protons
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 31
Vacuum chamber in SPS extraction line, 2004
be replaced
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 32
Collimator in Tevatron after, 2003
moved into the beam
pot quenched superconducting magnets
mm/turn, and touched a collimator jaw surface after about 300 turns
Observation of HERA tungsten collimators: grooves on the surface when opening the vacuum chamber were observed. No impact on
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 33
Beam Current Monitors (BCM) measure current pulse at different locations along the linac. About 16 µsec of beam lost in the superconducting part of linac
680 µs of beam before sc linac 664 µs of beam after sc linac 16 µs of beam lost in the sc linac Beam energy in 16 µs End of DTL = 30 J End of CCL = 66 J End of SCL = 350 J
Beam losses in SNS linac
M.Plum / C.Peters
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 34
Beam loss with low energy deposition
cavities)
might appear (not possible to operate at the same voltage, increased probability of arcing, …)
beam transfer and normal conducting linac
most cases
hitting the cavity desorbs gas or particulates (=small particles) creating an environment for arcing
M.Plum / C.Peters
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 35
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 36
Beam losses mechanisms
In accelerators, particles are lost due to a variety of reasons: beam gas interaction, losses from collisions, losses of the beam halo, …
accelerators
mechanisms
is (nearly) infinite
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 37
Continuous beam losses: Collimation prevents too high beam losses around the accelerator (beam cleaning) A collimation system is a (very complex) system with (massive) material blocks close to the beam installed in an accelerator to capture halo particles Such system is also called (beam) Cleaning System Accidental beam losses: “Machine Protection” protects equipment from damage, activation and downtime Machine protection includes a large variety of systems, including collimators (or beam absorbers) to capture mis-steered beam
Machine Protection Beam Cleaning
Beam losses, machine protection and collimation
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 38
Regular and irregular operation
Failures during
Beam losses due to failures, timescale
from nanoseconds to seconds
Machine protection systems Collimators Beam absorbers
Regular operation
Many accelerator systems Continuous beam losses Collimators for beam cleaning Collimators for halo scraping Collimators to prevent ion-induced desorption
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 39
Continuous beam losses: Collimation
Continuous beam with a power of 1 MW and more (SNS, JPARC, PSI)
avoid activation of material, heating, quenching, …
Limitation of beam losses is in order of 1 W/m to avoid activation and still allow hands-on maintenance
LHC stored beam with an energy of 360 MJ
to be lost in superconducting magnets
….but also: capture fast accidental beam losses
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 40
RF contacts for guiding image currents Beam spot 2 mm
View of a two sided collimator for LHC about 100 collimators are installed in LHC
Ralph Assmann, CERN
length about 120 cm
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 41
Accidental beam losses: Machine Protection
Single-passage beam loss in the accelerator complex (ns - s)
station (target for secondary particle production, beam dump block)
for example for diagnostics)
Very fast beam loss (ms)
powering system, with a typical time constant of ~1 ms to many seconds
Fast beam loss (some 10 ms to seconds) Slow beam loss (many seconds)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 42
Classification of failures
failure such as thunderstorm, object in vacuum chamber, vacuum leak, RF trip, kicker magnet misfires, .…)
problem, timing system, feedback failure, ..)
defined as risk
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 43
Probability of a failure leading to beam loss
detect the failure and dump the beams
sources)
(…. more accurate numbers are appreciated)
not mitigated = > the machine protection system is an essential part of the accelerator
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 44
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 45
Example for Active Protection - Traffic
dangerous situation
the system is safely dissipated
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 46
Example for Passive Protection
detect a dangerous situation
too short
possible – passive protection by bumper, air bag, safety belts
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 47
Strategy for protection and related systems
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 48
Strategy for protection and related systems
….before it is too late…
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 49
Beam instrumentation for machine protection
high (=beam lost somewhere): stop beam operation
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 50
detect abnormal beam losses and if necessary trigger a beam abort !
LHC Beam Loss Monitors
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 51
Layout of beam dump system in IR6
51
LHC Layout eight arcs (sectors) eight long straight section (about 700 m long) IR6: Beam dumping system IR4: RF + Beam instrumentation IR5:CMS IR1: ATLAS IR8: LHC-B IR2: ALICE
Injection Injection
IR3: Moment Beam Clearing (warm) IR7: Betatron Beam Cleaning (warm)
Beam dump blocks
Detection of beam losses with >3600 monitors around LHC
Signal to kicker magnet Beams from SPS
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 52
LHC: Continuous beam losses during collisions
CMS Experiment ATLAS Experiment LHC Experiment ALICE Experiment Momentum Cleaning RF and BI Beam dump Betatron Cleaning
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 53
LHC: Accidental beam losses during collisions
CMS Experiment ATLAS Experiment LHC Experiment ALICE Experiment Momentum Cleaning RF and BI Beam dump Betatron Cleaning
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 54
LHC: Accidental beam losses during collisions
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 55
Beam 2
Beam dump block Kicker magnets to paint (dilute) the beam about 700 m about 500 m 15 fast ‘kicker’ magnets deflect the beam to the
When it is time to get rid of the beams (also in case of emergency!), the beams are ‘kicked’ out of the ring by a system of kicker magnetsd send into a dump block ! Septum magnets deflect the extracted beam vertically quadrupoles The 3 s gap in the beam gives the kicker time to reach full field.
Ultra-high reliable system !!
R.Schmidt HASCO 2013 55
CERN
Layout of LHC beam dumping system in IR6
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 56
Beam dumping system line for LHC
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 57
LHC Beam dump
beam dump block
the passage of one proton bunch traversing the screen
has a different trajectory, to better distribute the energy across a large volume
50 cm
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 58
High power accelerators …
FRIB (ions) – planned for 0.4 MW
1 ms, the deposited energy is up to 130 kJ, for 1 s it is up to 5 MJ
beam loss – how fast?
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 59
Example for ESS
source
dT = dT_detect failure + dT_transmit signal + dT_inhibit source + dT_beam off inhibit beam interlock signal Example: After the DTL normal conducting linac, the proton energy is 78 MeV. In case of a beam size of 2 mm radius, melting would start after about 200 µs. Inhibiting beam should be in about 10% of this time.
L.Tchelidze
Time to melting point
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 60
Some design principles for protection systems
than damage equipment
rate
beams
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 61
Accelerators that require protection systems I
power of some 10 kW to above 1 MW
power (SNS, ISIS, PSI cyclotron, JPARC, and in the future ESS, FRIB, MYRRHA and IFMIF)
secondary photon beams
equipment, but in case of beam loss next train must not leave the (injector) station
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 62
Accelerators that require protection systems II
densities due to small beam size
600 kW, JLab FEL 1.5 MW, ILC 11 MW
beam trajectory of component alignment (~fraction of a second), pilot beam must be used to prove the integrity” from NLC paper 1999
that can damage the environment (bellows, beam instruments, cavities, …)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 63
For future high intensity machines
Machine protection should always start during the design phase of an accelerators
tunnel) required
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 64
Summary
Machine protection
could lead to beam loss
accelerator (accelerator physics, operation, equipment, instrumentation, functional safety)
increased beam power / energy density (W/mm2 or J/mm2 ) and increasingly complex machines
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 65
Acknowledgements to many colleagues from CERN and to the authors of the listed papers
2005
Laboratory Energy Recovery Linac Prototype, EPAC 2006
LINAC 2006
done about it, HB2006
HB2006
ICALEPCS 2007
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 66
CERN and LHC
experiments, Phys. Rev. ST Accel. Beams 13, 061002 (2010)
IPAC 2010, Kyoto, Japan, 23 - 28 May 2010 Theses
2005-047
CERN-THESIS-2006-012 PCCF-T-0509
CERN-THESIS-2009-023
Availability /, CERN-THESIS-2010-215
Acknowledgements to many colleagues from CERN and to the authors of the listed papers
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 67
components? ESS AD Technical Note, ESS/AD/0031, 2012
Acknowledgements to many colleagues from CERN and to the authors of the listed papers
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 68
68
Assume that two 100 MJoule beams (=25 kg TNT) are circulating with the speed of light through the 56 mm diameter vacuum chamber and 2 mm wide collimators
1.
Suddenly the AC distribution for CERN fails – no power!
2.
An object falls into the beam
3.
The betatron tune is driven right onto a 1/3 order resonance
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 69
LHC from injection to collisions
3.5 TeV / 100 MJoule 0.45 TeV / 13 MJoule Energy ramp Luminosity: start collisions Injection of 1380 bunches per beam About 2 hours
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 70
Orbit for last 1000 turns before power cut
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 71
Example for power radiated during particle collisions for LHC Rate of collision: 𝑔 𝐼𝑨 = 𝑀 𝑑𝑛−2 ∙ 𝑡−1 ∙ 𝜏 𝑑𝑛2 Power in collision products: 𝑄[𝑋] = 𝑔[𝐼𝑨] ∙ 𝐹[𝑓𝑊] Assume LHC operating at 7 TeV with a luminosity of: 𝑀 = 1034 ∙ 𝑑𝑛−2 ∙ 𝑡−1 Total cross section for pp collision of 110 mBarn: 𝑄 𝑋 = 1034 ∙ 𝑑𝑛−2 ∙ 𝑡−1 ∙ 10−25 𝑑𝑛2 ∙ 7[𝑈𝑓𝑊] Power in collision products per experiment: 𝑄 𝑋 = 1100 𝑋
remain in the vacuum chamber
Continuous beam losses
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 72
Total power cut atLHC - 18 August 2011, 11:45
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 73
CERN fails – no power for LHC!
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 74
\\cern.ch\dfs\Users\r\rudi\Documents\ConferencesWorkshops\SCHOOL S\CAS\CAS2011\UFO-slideshow.pptx
UFO at LHC
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 75
LHC from injection to collisions: beam loss
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 76
…zoom - going into collisions
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 77
Beam cleaning system captures beam losses
are captured by collimators in the Momentum Cleaning Insertion Questions
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 78
Collimator material
boron nitride for the injection absorber
further to the next collimators in the cleaning insertions
P.Sievers / A.Ferrari /
7 T eV, 21012 protons
the beam, metal absorbers would be destroyed
collimators close to the beam are preferred (carbon – carbon)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 79
Collimation
in general Gaussian, or close to Gaussian (beams can have non- Gaussian tails)
might touch the aperture
before getting lost (except those that do a inelastic collision with gas molecules)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 80
Phase space and collimation
x’ x x’
Starting with a Gaussian beam profile
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 81
Phase space and collimation
x’ x x’
Collimator outside the beam
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 82 82
Phase space and collimation: multi turn
x’ x’ x
Collimator driven into the beam tail: loss of particles
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 83 83
Phase space and collimation: multi turn
x’ x’ x
Collimator again outside the beam – beam size reduction (for proton synchrotrons)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 84 84
Phase space and collimation: single turn
x’ x’ x
Collimator in a transfer line or linac: cuts only part
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 85 85
Phase space and collimation: single turn
x’ x x’
Collimator in a transfer line or linac: cuts only part
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 86 86
Phase space and collimation: single turn
x’ x’ x
Collimator in a transfer line or linac: several collimators are required
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 87 87
Phase space and collimation: single turn
x’ x’ x
Collimator in a transfer line or linac: several collimators are required …. at different betatron phases
90 degrees further down
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 88
Gaussian beam not collimated
4
3
2
1
1 2 3 4 3 10
4
6 10
4
9 10
4
1.2 10
3
1.5 10
3
1.8 10
3
2.1 10
3
2.4 10
3
2.7 10
3
3 10
3
0.003
g.h t ( )
4 4
t
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 89
Gaussian beam collimated at 4 sigma
4
3
2
1
1 2 3 4 3 10
4
6 10
4
9 10
4
1.2 10
3
1.5 10
3
1.8 10
3
2.1 10
3
2.4 10
3
2.7 10
3
3 10
3
0.003
g.h t ( )
4 4
t
N = 0.999 (number of protons) L = 0.999 (luminosity)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 90
Gaussian beam collimated at 3 sigma
4
3
2
1
1 2 3 4 3 10
4
6 10
4
9 10
4
1.2 10
3
1.5 10
3
1.8 10
3
2.1 10
3
2.4 10
3
2.7 10
3
3 10
3
0.003
g.h t ( )
4 4
t
N= 0.987 L = 0.992
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 91
Gaussian beam collimated at 2 sigma
4
3
2
1
1 2 3 4 3 10
4
6 10
4
9 10
4
1.2 10
3
1.5 10
3
1.8 10
3
2.1 10
3
2.4 10
3
2.7 10
3
3 10
3
0.003
g.h t ( )
4 4
t
N= 0.863 L = 0.866
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 92
Collimation: why so many?
Answer A:
required to take out particles at all phases Answer B:
possible to make them mad”
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 93
Betatron beam cleaning
Cold aperture Cleaning insertion Arc(s) IP
Circulating beam Illustration drawing
Arc(s)
Primary collimator Secondary collimators
Tertiary beam halo + hadronic showers
Shower absorbers Tertiary collimators SC Triplet
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 94
Measurement: 500kJ losses at primary collimators (loss rate: 9.1e11 p/s) – IR7
Daniel Wollmann
94
TCP: ~505 kJ Q8L7: ~335 J Q11L7: ~35 J Q19L7: ~4.7 J Q8L7: ~ 6.7e-4 Lower limit: RqLdil ~ 1.22e9 p/s (with cresp= 2 ) Lost energy over 1 s
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 95
Film from Alessandro
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 96
173 bunches grazing incident on injection absorber
Upstream of IP2
Beam 1
Downstream of IP2
Beam 1
Insertion losses: 3 magnets quenched (D1.L2, MQX.L2, D2.R2)
TDI
Losses starting at TDI, no injection loss signature only circulating beam kicked by MKI
In comparison to flashover event of April 18th in P8 (LMC 20/04/11), cleaner in arc less magnet quenches (3), ALICE SDD permanent effect, open MCSOX.3L2 circuit
C.Bracco
CAS October 2013 R.Schmidt 97
CAS October 2013 R.Schmidt 98
Protection for beam transfer from SPS to LHC
A signal “extraction permit” is required to extract beam from SPS and another signal “injection permit“ to inject beam into LHC
beam transfer and injection relies on correct settings
–
tolerances verified with BPMs – correct magnet currents (slow pulsing magnets, fast pulsing magnets) – position of vacuum valves, beam screens,… must all be OUT – energy of SPS, transfer line and LHC must match – LHC must be ready to accept beam
LHC injection region to protect from misfiring
CAS October 2013 R.Schmidt 99
Case studies
The principles of machine protection are illustrated with examples from different accelerators
CAS October 2013 R.Schmidt 100
Example: SNS
– the deposited energy is proportional to the time of exposure – the risk (possible damage) increases with time
CAS October 2013 R.Schmidt 101
SNS damage limits
copper assuming a beam size of 2 mm, a current of 36 mA and an energy density of 62 J/gm as maximum permitted energy deposition (from C.Sibley, PAC 2003)
power supplies, vacuum system, kickers, etc.
102
Radiation Damage to Undulator Magnets
when irradiated
10−8/Gy (gammas) — 10−4/Gy (fast neutrons)
hybrid magnet structure Nd2Fe14B permanent magnets soft magnetic pole pieces
Lars Froehlich, DESY and Uni Hamburg, Machine Protection Machine Protection for FLASH and the European XFEL
103
Conclusion
dangerously powerful beams
among the most vulnerable components
tightly (FLASH design: 3∙10−8)
required
fully functional & reliable
be more complex, but concepts & first prototypes are ready
Lars Froehlich, DESY and Uni Hamburg, Machine Protection Machine Protection for FLASH and the European XFEL
CAS October 2013 R.Schmidt 104
Machine Protection during all phases of operation
already far above threshold for damage, protection during the injection process is mandatory
“nominal bunch” could damage equipment (e.g. superconducting coils)
dump block - all other components would be damaged
– at the end of a fill – in case of failure
quench protection and powering interlocks must be operational long before starting beam operation
CAS October 2013 R.Schmidt 105
Multiturn beam losses
Consequence of a magnet powering failure
– Closed orbit grows and moves everywhere the ring or downstream the linac (follows free betatron oscillation with one kick) – Beam size explodes – Can happen very fast (for example, if a normal conducting magnet trips or after a magnet quench) – Can be detected around the entire accelerator
Local orbit bump
– Can be generated due to BPM offset – Needs several magnets to fail and cannot happen very fast – Might be detected only locally
CAS October 2013 R.Schmidt 106
Failure of normal conducting magnets
After about 13 turns 3·109 protons touch collimator, about 6 turns later 1011 protons touch collimator
V.Kain / O.Bruning
“Dump beam” level
1011 protons at collimator
CAS October 2013 R.Schmidt 107
Fast Magnet Current change Monitors
(initial development for HERA, upgrade for LHC in collaboration with DESY)
ested using steep reference changes to trigger FMCM. The trigger threshold and the magnet current (resolution one ms)
Reference PC current time (ms) I (A) FMCM trigger 0.1% drop ! time (ms) I (A) 10 ms
FMCM triggers @ 3984.4 <103
CAS October 2013 R.Schmidt
CAS October 2013 R.Schmidt 109
Principle of LHC / SPS Beam Interlock Systems
BIS
LHC Dump kicker
Beam ‘Permit’
User permit signals
send a hardwired signal to the beam interlock system (user permit)
dump triggered !
no extraction !
Hardware links /systems, fully redundant
SPS Extraction kicker LHC Injection kicker SPS Dump kicker
CAS October 2013 R.Schmidt 110
Machine Protection and Controls
protection for complex but also less critical conditions
– Surveillance of magnet currents to avoid certain failures (local bumps) that would reduce the aperture – The reaction time of those systems will be at the level of a few seconds – The systems rely entirely on the computer network, databases, etc – clearly not as safe as HW systems!
– To execute defined well-tested procedures for beam operation
logging and for transients (beam dump, quench, …)
– Very important to understand what happened
CAS October 2013 R.Schmidt 111
P.Sievers / A.Ferrari /
Beryllium
Accidental kick by the beam dump kicker at 7 TeV part of beam touches collimators (about 21012 from 31014 )
CAS October 2013 R.Schmidt 112
T arget length [cm] vaporisation melting
N.Tahir (GSI) et al.
Copper target 2 m Energy density [GeV/cm3]
2808 bunches 7 T eV 350 MJoule
Full LHC beam deflected into copper target
CAS October 2013 R.Schmidt 113
LHC circulating beam Injection absorbers (TCLI) ~7σ
n·180 +/- 20 degrees
Beam absorbers take beam in case of kicker wrong strength
Protection at injection
Beam from SPS Injection Kicker Set of transfer line collimators (TCDI) ~5σ Injection absorber (TDI) ~7σ Circulating beam – kicked out Injection kicker – wrong strength
phase advance 900
LHC circulating beam
CAS October 2013 R.Schmidt 114
LHC circulating beam Injection Kicker Injection absorber TDI ~7σ Injection absorbers TCLI ~7σ
Only when beam is circulating in the LHC, injection of high intensity beam is permitted – verification of LHC magnet settings
Probe Beam: Replacing low intensity beam by a full batch from SPS
Set of transfer line collimators TCDI ~5σ Beam from SPS
CAS October 2013 R.Schmidt 115
Active and passive protection
Start operation with low intensity beam (“pilot beam”) Active protection
accelerator complex in case of positive confirmation that all parameters are within predefined limits
Passive protection
protection is not possible
CAS October 2013 R.Schmidt 116
Active protection
Monitoring of the beam detects a failure and allows to switch off the beam before damage
– multi turn beam losses – monitor beam losses, and dump the beam if losses exceed threshold
– continuous: if the time constant for a failure is such that the source can be switched off in time
magnet powering system, with a typical time constant of ms to many seconds
CAS October 2013 R.Schmidt
Cold aperture
Primary beam halo
Primary collimator Secondary collimators
Tertiary beam halo + hadronic showers Secondary beam halo + hadronic showers
Shower absorbers
Cleaning insertion
Tertiary collimators SC Triplet
Arc(s) IP
Protection devices
Circulating beam
Illustrative scheme
CAS October 2013 R.Schmidt 118
CAS October 2013 R.Schmidt 119
Failure of a kicker magnet
1 km
Extraction kicker magnet:
Injection kicker magnet:
Transfer line
LHC SPS
6911 m 450 GeV / 400 GeV 3 MJ Acceleration cycle of 10 s
CNGS Target
IR8
Switching magnet Fast extraction kicker Injection kicker
Transfer line
Injection kicker
IR2
Fast extraction kicker
CAS October 2013 R.Schmidt 120
Failure in the transfer line (magnet, other element)
1 km
Wrong setting of magnets Object in the transfer line blocks beam passage
Transfer line
LHC SPS
6911 m 450 GeV / 400 GeV 3 MJ Acceleration cycle of 10 s
CNGS Target
IR8
Switching magnet Fast extraction kicker Injection kicker
Transfer line
Injection kicker
IR2
Fast extraction kicker
CAS October 2013 R.Schmidt
M.Jonker
Beam damage capabilities
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 122
Accidental beam losses: Risks and protection
consequences (in Euro, downtime, radiation dose to people)
is an practical infinite number of mechanisms to lose the beam)?
equipment is delayed
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 123
Damage of LHC during the 2008 accident
Accidental release of an energy of 600 MJoule stored in the magnet system - no beam in LHC
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 124
Energy loss: example for protons in Aluminium
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 125
Temperature increase in the material: dTFe Np dEdxFe cFe_spec Fbeam
Fe
Temperature increase for a proton beam impacting on a Fe target: Beam size: h mm and v mm Iron specific heat: cFe_spec J kg K Iron specific weight: Fe kg m3 Energy loss per proton/mm: dEdxFe MeV mm Number of protons: Np Energy of the proton: Ep GeV Temperature increase: dTFe
Heating of material with low energy protons
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 126
Strategy for Machine Protection
Beam Interlock System Collimator and Beam Absorbers
(inhibit injection, dump beam).
abnormal beam conditions and generates beam abort request.
beam stop system. Active signal required for
beam abort request and injection inhibit.
collimators for specific failure cases.
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 127
LHC: Strategy for machine protection
Beam Cleaning System Beam Loss Monitors Other Beam Monitors Beam Interlock System Powering Interlocks Fast Magnet Current change Monitor Beam Dumping System Collimator and Beam Absorbers
before the beam is affected.
abnormal beam conditions and generates beam dump requests down to a single machine turn.
to beam dumping system. Active signal required for operation, absence of signal is considered as beam dump request and injection inhibit.
dump requests or internal faults, safely extract the beams onto the external dump blocks.
collimators for specific failure cases.
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 128
Beam losses and consequences
~1 W/m, but must be “As Low As Reasonably Achievable – ALARA”)
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 129
Energy deposition and temperature increase
2.2 MeV/mm
expected to be about 1020 C
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 130
Energy deposition and temperature increase
1.1 × 1015
proton energy of 3 MeV
59.7 MeV/mm
deflected to the wall would be far above damage limit
increase to about 600 C
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 131
Energy deposition and temperature increase
momentum, and the parameters of the material (atomic number, density, specific heat)
used for the calculation of energy deposition and activation
material (deformation, melting, …) to beam impact (mechanical codes such as ANSYS, hydrodynamic codes such as BIG2 and
Question: what is dangerous (stored beam energy, beam power)?
CERN
Rüdiger Schmidt CAS Trondheim 2013 page 132
What parameters are relevant?
hadron accelerators
1.5 kg of copper
energy stored in 0.25 kg of TNT
corresponds to a MJoule
(MJoule/mm2, MWatt/mm2)
Consequences for an accident with 360 MJ beam can be catastrophic (LHC damage beyond repair) Delicate components can be damaged already with some Joule (e.g. RFQ) Machine protection becomes very important if beam energy > 0.1 – 1 MJ