A RISK ANALYSIS OF THE MOLYBDENUM-99 SUPPLY CHAIN USING BAYESIAN - - PowerPoint PPT Presentation

a risk analysis of the molybdenum 99 supply chain using
SMART_READER_LITE
LIVE PREVIEW

A RISK ANALYSIS OF THE MOLYBDENUM-99 SUPPLY CHAIN USING BAYESIAN - - PowerPoint PPT Presentation

A RISK ANALYSIS OF THE MOLYBDENUM-99 SUPPLY CHAIN USING BAYESIAN NETWORKS 2017 Mo-99 Topical Meeting Jeffrey Liang, D.Eng. OVERVIEW Motivation Background and Problem Description Research Questions and Limitations Methodology


slide-1
SLIDE 1

A RISK ANALYSIS OF THE MOLYBDENUM-99 SUPPLY CHAIN USING BAYESIAN NETWORKS

2017 Mo-99 Topical Meeting Jeffrey Liang, D.Eng.

slide-2
SLIDE 2

OVERVIEW

  • Motivation
  • Background and Problem Description
  • Research Questions and Limitations
  • Methodology
  • Findings
  • Conclusions and Future Recommendations
slide-3
SLIDE 3

MOTIVATION

  • Subject for Dissertation, focusing on Engineering Management
  • National Research Universal (NRU) reactor ceased production of Molybdenum-99 (99Mo) in Oct 2016
  • Represents 19% of global 99Mo production
  • Only producer in North America
  • Effects of the NRU shutdown on the 99Mo supply chain is the subject of debate
  • National Academy of Sciences: “>50% likelihood of severe shortages”
  • Nuclear Energy Agency: “supply chain capacity should be sufficient”
  • Majority of the remaining reactors are over 45 years old
slide-4
SLIDE 4

METHODOLOGY

  • Bayesian Network
  • Each risk or performance measure is represented as an event
  • Captures the likelihood of a given chain of events occurring
  • Allows for back-propagation to see what parent events caused an outcome
  • Modeled Reactor to Processor section of the supply chain
  • Once processed into Generators, 99Mo can be shipped anywhere by air
  • Each reactor and processing facility was a node in the network
  • Quantity of 99Mo produced or processed was the outcome of each node
slide-5
SLIDE 5

WHAT IS A BAYESIAN NETWORK?

  • Extension of Bayes’ Theorem, which represents the probability of a hypothesis occurring after considering the effect
  • f evidence on past experience
  • Provides a way to combine both evidence and subjective beliefs
  • Particularly useful in situations where there is a high degree of uncertainty
  • The network consists of nodes and arcs
  • Each node represents variables; each arc denotes parent-child relationships
  • Each node has a conditional probability table that lists each of the different combinations of values from parent nodes and

the probabilities of that outcome occurring

slide-6
SLIDE 6

BAYESIAN EXAMPLE

  • 20% Chance of Rain
  • If it is not raining, the sprinklers

are set to turn on 40% of the time

  • If it rains, there is a 1% chance the

rain sensor will fail and the sprinkler will still activate

  • What is the probability the grass

will be wet at any given time?

slide-7
SLIDE 7

NETWORK DIAGRAM

Reprinted from “Molybdenum-99 for Medical Imaging” (p. 53), by the National Academies of Sciences, Engineering, and Medicine, 2016, Washington, DC: The National Academies Press.

Mo-99 Supply Chain Bayesian Network Model

slide-8
SLIDE 8

LIMITATIONS

  • Could not access business-specific operating information
  • Proprietary Information
  • Reactor scheduling or production decisions
  • Processor sourcing decisions
  • Does not include actual vs planned operating data
  • Impact on Model
  • Used typical number of operating days to calculate probability of operating
  • Model is focused on determining probability of final production levels
  • Not a system dynamics or stock-and-flow model
  • Does not illustrate how companies would choose where to ship
slide-9
SLIDE 9

PROBABILITY TABLES

Reactor Normal Production Maximum Production Value Probability Value Probability NRU

23.29% 23.29% 4680 76.71% 4680 76.71%

Maria

45.21% 45.21% 1500 54.79% 1500 0.00% 2700 0.00% 2700 54.79%

HFR

27.12% 27.12% 4680 72.88% 4680 0.00% 5400 0.00% 5400 72.88%

BR-2

47.95% 47.95% 5200 52.05% 5200 0.00% 7800 0.00% 7800 52.05%

LVR-15

42.67% 42.67% 600 57.33% 0.00% 2400 0.00% 2400 57.33%

SAFARI-1

16.44% 16.44% 2500 83.56% 2500 0.00% 3000 0.00% 3000 83.56%

  • Each reactor node’s probability table was based on:
  • Normal operating level
  • Maximum operating level
  • Number of operating days per year
  • Not meant to be an accurate model of actual production levels
  • Illustrates the validity of using Bayesian Networks
  • Quantify risk in the supply chain
  • The data in the tables can be updated with more accurate data
slide-10
SLIDE 10

Complete Bayesian Network

  • Determines the probability of different levels
  • f Mo-99 production in the supply chain
  • Allows for “what-if” scenarios
  • What if reactor X has unscheduled

downtime?

  • Enter an outcome and find the root cause
  • If a major shortage took place, what

node(s) were the likely root cause(s)?

slide-11
SLIDE 11

SCENARIOS

  • Prior to NRU Production Cessation
  • Probability of shortages with normal and maximum production rates
  • After NRU Production Cessation
  • Probability of shortages with normal and maximum production rates
  • Probability of shortages if another reactor goes offline
  • Root Causes of a major or minor shortage
slide-12
SLIDE 12

FINDINGS

  • Supply chain can meet demand after

NRU shutdown, but reactor coordination will be critical

  • Very difficult to handle additional

unscheduled outages

Normal Production Maximum Production Pre-NRU Cessation Post-NRU Cessation

slide-13
SLIDE 13

ROOT CAUSE ANALYSIS

  • HFR is largest source of risk
  • Not largest producer
  • Longest operating period
  • SAFARI-1 has significant impact despite being

mid-level producer

  • Single supplier to NTP
  • Loss of entire NTP supply

Normal Production Maximum Production Major Shortage Minor Shortage

slide-14
SLIDE 14

CONCLUSIONS

  • Theoretically there is enough production capacity in other reactors to compensate for the loss of NRU, but there are

significant sources of risk:

  • Processing facilities do not have the capacity to processing more targets
  • Multiple processing facilities can only be supplied by one reactor
  • Results are a middle ground between NASM and NEA assessments
  • 24% chance of major shortage (NASM: >50%, NEA: no impact)
  • Operating schedule is just as important as production capacity
  • SAFARI-1 and NTP will guarantee a shortage if offline
slide-15
SLIDE 15

CONTRIBUTIONS/FUTURE WORK

  • Contributions
  • Existing assessments focused on only maximum production scenarios
  • Prior studies do not quantify the risk each node introduces
  • Prior work did not quantify probability of shortages based on different reactor outages
  • Future Work
  • Extending the model
  • Different production levels for reactors
  • Incorporate actual scheduling/coordination
  • Real-time decision making tool
  • Geographic analysis of facility locations
  • Where to build new facilities mitigate the most risk
  • Which facilities are best suited for adding capacity
slide-16
SLIDE 16

QUESTIONS?