A Case for Performance-Based Road Maintenance in Nigeria A Paper - - PowerPoint PPT Presentation

a case for performance based road maintenance in nigeria
SMART_READER_LITE
LIVE PREVIEW

A Case for Performance-Based Road Maintenance in Nigeria A Paper - - PowerPoint PPT Presentation

A Case for Performance-Based Road Maintenance in Nigeria A Paper Presented at the Technical Evening of the Nigerian Society of Engineers, Port Harcourt Branch By Engr. Alozia E. Okezie MNSE MNICE 29 August, 2013 Courtesy Indisys Nig. Limited


slide-1
SLIDE 1

A Case for Performance-Based Road Maintenance in Nigeria

A Paper Presented at the Technical Evening of the Nigerian Society of Engineers, Port Harcourt Branch By

  • Engr. Alozia E. Okezie MNSE MNICE

29 August, 2013

Courtesy Indisys Nig. Limited August 29, 2013

slide-2
SLIDE 2

About the Author

Principal Consultant/CEO,

Indisys Nigeria Limited

(Civil/Structural Engineering Consultants)

Email: contact@indisys-ng.com

(Formerly Contracts Manager, Monier Construction Co. (Nig.) Limited)

Courtesy Indisys Nig. Limited August 29, 2013

2

slide-3
SLIDE 3
  • 1. Preamble

Generally many road agencies around the world are facing difficulties controlling quality, cost and time in maintenance works using traditional methods of contracting Privatization of maintenance works is now considered a cost-effective alternative This relatively new approach involving the private sector in roads maintenance takes the form of Performance- Based Maintenance Contract (PBMC) PBMC has been deployed rapidly in the road sector in the past decade Substantial success records have been reported in many developed and developing countries during this period

Courtesy Indisys Nig. Limited August 29, 2013

3

slide-4
SLIDE 4
  • 2. Overview of Road Sector in Nigeria

Nigeria has the largest road network in West Africa and the second largest in Sub-Saharan Africa which is generally managed by government agencies as a social service Recent estimate puts the total length of the network at 200,000Km The ownership structure is Federal (17%); States (16%); LGAs (67%), as shown in Fig. 1

  • Fig. 2 shows that 65,000Km of the roads are paved with bituminous materials while the rest is unpaved

Many of the roads are either not maintained or are poorly maintained Only 27% of Federal roads are reported to be in good condition Cost to the economy is huge as road transport accounts for 95% of passenger and freight movement in the country with Federal roads accounting for 80% of national vehicular traffic Annual loss to the economy is estimated in the region of N175b (N75b due to reduction in asset value; N88b due to increased vehicle operating cost; N12b due to increased turn around and increased travel time)

Courtesy Indisys Nig. Limited August 29, 2013

4

slide-5
SLIDE 5

Courtesy Indisys Nig. Limited

To address the systemic failure the Federal Roads Maintenance Agency (FERMA) was created in 2002 with the responsibility to manage and maintain Federal roads At the State level maintenance contracts are let by the Ministries of Works (in some cases ad-hoc agencies) States have in some cases taken up maintenance of LGA roads due to weak governance at that level Both FERMA and State Agencies rely on traditional methods in contracting out road maintenance works This traditional contracting approach has generally failed to deliver road-user satisfaction and reduce maintenance cost Hence road agencies in many countries are adopting performance-based contract in roads maintenance as an alternative

August 29, 2013

5

slide-6
SLIDE 6

August 29, 2013 Courtesy Indisys Nig. Limited

6

34,000KM ([PERCENTAGE]) 32,000KM ([PERCENTAGE]) 134,000KM ([PERCENTAGE])

  • Fig. 1 Ownership Structure of the Road Network in Nigeria

Federal (Trunk A) States (Trunk B) LGAs (Trunk C)

Source: Onolememen, M. (2013)

slide-7
SLIDE 7

Courtesy Indisys Nig. Limited

[CATEGORY NAME] 65,000Km [CATEGORY NAME] 135,000Km

  • Fig. 2 Proportion of the Road Network Paved with Bituminous Materials

Paved Unpaved

Source: Onolememen, M. (2013)

August 29, 2013

7

slide-8
SLIDE 8
  • 3. What is Traditional Method of Contracting in Road Maintenance Works

Also referred to as method-based contracting Unit rate or work-order oriented Road Agency specifies methods, materials, and technologies to be used Payment is made at an agreed unit rate based on quantity of work done

Courtesy Indisys Nig. Limited August 29, 2013

8

slide-9
SLIDE 9
  • 4. Disadvantages of Traditional Method of Contracting in Road Maintenance Works

Depends

  • n

annual budgetary provisions – (long budgeting process, dwindling resources, competing needs, monetary control, whims and caprices of Parliament) Build up of maintenance backlog Prone to corruption due to the inherent decision-making processes Encourages large bureaucracy Discourages innovation by contractor Not amenable to outsourcing or privatization Road Agency bears responsibility for failure

Courtesy Indisys Nig. Limited August 29, 2013

9

slide-10
SLIDE 10
  • 5. What is Performance-Based Maintenance Contract (PBMC)?

Courtesy Indisys Nig. Limited

Also referred to as output-based maintenance contract Client only specifies performance indicators, performance targets and response times to be met by the contractor Contractor determines the best methods, materials and technologies to be used to meet or exceed the performance indicators Payment made for management and maintenance of road assets directly linked to the contractor meeting

  • r exceeding clearly defined minimum performance indicators

Scope may be “simple” to cover individual asset such as street light maintenance (usually for several months to one year) Or “comprehensive” to cover all road assets within ROW, involving routine and periodic maintenance (usually for 3 to 10 years or more)

August 29, 2013

10

slide-11
SLIDE 11

5.1 Why Performance-Based Maintenance Contract (PBMC)?

Courtesy Indisys Nig. Limited

Saves cost Greater predictability of expenditure by road agency Stable multi-year maintenance financing Ability to manage and maintain road network with fewer road agency staff Better road-user satisfaction with road service and condition Achieving sustainable road management system

August 29, 2013

11

slide-12
SLIDE 12

5.2 How does it Save Cost?

Courtesy Indisys Nig. Limited

  • Inherent incentive for contractor to innovate and increase productivity
  • Fewer Road Agency staff required to administer and maintain road network, hence lower overheads
  • Greater flexibility to reward performance and sanction non-performers
  • Variation orders are minimized
  • Risk of cost over-runs transferred to contractor
  • Cost savings in the range 10 – 40% over traditional methods have been reported in developed countries

August 29, 2013

12

slide-13
SLIDE 13

5.3 Countries that have implemented Performance-Based Maintenance Contract (PBMC)

Courtesy Indisys Nig. Limited

Successfully applied in the following countries:

  • Canada - British Caledonia (1988), later Ontario and Alberta
  • Australia – Sydney (1995), later New South Wales, Tasmania, Southern & Western Australia
  • New Zealand (1998)
  • USA – State of Virginia (1996), later Alaska, Florida, Oklahoma and Washington D.C.
  • UK, Finland, Sweden, Netherlands, Norway, France, Estonia, Serbia & Montenegro in Europe
  • Argentina, Brazil, Colombia, Chile, Ecuador, Guatemala, Mexico, Peru in Latin America
  • South Africa, Zambia, Chad in Africa
  • Philippines, Thailand and Vietnam in Asia

August 29, 2013

13

slide-14
SLIDE 14

5.4 Example of Performance Indicators Used in Different PBMCs in Latin America

Courtesy Indisys Nig. Limited August 29, 2013

14

Asset Class Component Performance Indicator

Pavement Potholes Roughness (asphalt) Roughness (bituminous Treatment) Rutting Cracks No potholes IRI<2.0(Argentina); IRI<1.8 (Uruguay IRI<2.0(Argentina); IRI<3.4 (Uruguay) <12mm(Argentina); <10mm (Uruguay, Chile) Sealed Gravel Surfaces Potholes Roughness Thickness of gravel layer No Potholes IRI<6 (Uruguay); IRI<11 (Chile) 10cm (Chile, Uruguay) Shoulders Potholes Cracks Joints with pavement No potholes Sealed Vertical alignment < 1cm (Chile, Uruguay), sealed (Peru)

slide-15
SLIDE 15

August 29, 2013 Courtesy Indisys Nig. Limited

15

Asset Class Component Performance Indicator

Drainage system Obstructions Structures No obstructions. Should allow for free flow of water (Chile, Uruguay) Without damages and deformations (Chile, Peru) Road signs and markings Road signs Road markings Reflectivity of road markings Complete and clean (Argentina, Chile, Peru) Complete and visible (Argentina, Chile, Peru) 160 mcd/lx/sqm. (Argentina); 70 mcd/lx/sqm. (Uruguay) Right of way Vegetation Foreign elements < 15cm height (Argentina, Uruguay) No foreign elements allowed In the Performance Contracts in Latin America all Performance Indicators at to be met fully (Performance Target = 100% for every indicator)

Source: Zietlow, G. (2004)

slide-16
SLIDE 16

5.5 Example of Performance Indicators of the Performance Contract let in Sydney, Australia

Courtesy Indisys Nig. Limited August 29, 2013

16

Asset Outcome Performance Target (% of Asset) Performance Indicator

Cross Pipes < 36 ft sq) Structurally sound Open drains Joints intact Adequate capacity No erosion 95 < 10% deteriorated barrel > 90% diameter open Joints intact End protection intact No dip in road over pipe indicating structural problems Paved Ditches Aligned Structurally sound Clean 95 < 1” settlement < 25% spalled no obstruction to flow of water Sidewalks and Ramps Smooth Safe Sound 90 No settlement > ½” No unsealed cracks > ¼” < 25% spalled In Australia, New Zealand and US, Performance Targets are allowed to be less than 100%

Source: Zietlow, G. (2004)

slide-17
SLIDE 17

5.6 Example of Contract Standards and Response Times used in New Zealand

Courtesy Indisys Nig. Limited August 29, 2013

17

Feature Contract Standard Response Time

Potholes on highways with > 10000 veh./day Not more than 3 potholes with a diameter greater than 70mm on any 10km section 48 hours Potholes on all highways No potholes greater than 150mm in diameter 48 hours Depressions and Rutting No ponding greater than 30mm in depth at any location 6 months Edge Break No more than 2m of edge break within any continuous kilometer greater than 0.5m 1month Lined Channels No lined channels with more than 10%

  • f the cross-sectional area obstructed,

and free of vegetation 1 week

Source: Zietlow, G. (2004)

slide-18
SLIDE 18

5.7 Lessons from Other Countries

Courtesy Indisys Nig. Limited

Lessons from mostly Latin American countries include

  • Funding security throughout contract duration (sometimes up to 10 years) critical to success
  • Each PBMC should be customized to suit specific situations
  • Where there is inadequate experience, gradual approach is recommended starting with short term contracts and

simple performance indicators such as pot holes control, patching and drainage cleaning

  • Well qualified contractors and inspectors are key to success. Traditional contractors would require training in

modern management and maintenance techniques to adapt to the relatively new PBMC

  • Duration should be long enough as an incentive to allow contractor innovate and optimize potential benefits
  • Proper performance monitoring and strict application of penalties for non-performance is also critical to success
  • f PBMC
  • Performance indicators need to be further developed from the present rudimentary level
  • Cost-savings may not be immediate

August 29, 2013

18

slide-19
SLIDE 19

5.8 Key Issues to Consider in Introducing Performance-Based Maintenance Contract (PBMC)

Courtesy Indisys Nig. Limited

  • Road Agency to decide the type of road and duration of contract (Simple or Comprehensive)
  • Define Performance criteria – to reflect road user expectations
  • Consider starting on a pilot scale to enable road authority and contractor gain requisite experience
  • Clearly identify risk exposures to the parties at the tendering stage
  • Performance monitoring:
  • Level of Service Effectiveness – extent of compliance with performance criteria and performance targets in

the contract

  • Timeliness of Response – evaluates response time of contractor to service requests
  • Safety Procedures – evaluates adherence to safety program to minimize exposure of road users and workers

to risk of accidents

  • Quality of Service – assesses road user perceptions with respect to condition of assets and contractor

performance

  • Cost Efficiency – assesses cost savings, if any, accruing to government as a result of engaging contractor on

PBMC

August 29, 2013

19

slide-20
SLIDE 20

August 29, 2013 Courtesy Indisys Nig. Limited

20

  • Employee Issues –
  • road authority to plan for staff who will lose jobs
  • consider retaining enough staff to preserve experience base
  • Private operator or contractor to consider absorbing existing employees of road

agency for the benefit of retaining experienced workforce

  • Payment and Termination of Contract-
  • Fixed fee to cover basic facility operating cost, any maintenance and major upgrades
  • variable fee tied to performance against a basket of outcome measures
  • Escalating

scale

  • f

specific sanctions culminating in termination for non- compliance, non-performance or general breach of contract

slide-21
SLIDE 21

5.9 Special Issues in Developing Countries

Courtesy Indisys Nig. Limited

  • Government commitment – governments are more interested in constructing new roads than in maintaining

existing ones for political gains

  • Political interference in selection of contractors
  • Poor supervision by road agency due to corruption
  • Secure funding independent of foreign aid or loans
  • Challenges in estimation of the cost of PBMC due to lack of existing data base on roads

August 29, 2013

21

slide-22
SLIDE 22
  • 6. Requisite Reforms in Nigerian Road Sector To Implement PBMC

Courtesy Indisys Nig. Limited

To successfully implement and take advantage of PBMC in the Nigerian road sector, the following key reforms are necessary:

  • Creation of Road Authority
  • Independent of the Ministry of Works (FERMA does not meet this requirement)
  • Private sector representation on the board
  • Responsible for contracting out public works and road network management
  • Creation of a Roads Fund
  • Ring-fenced from general government budget
  • administered by an autonomous board
  • funded from road-user charges and realistic fuel levy

August 29, 2013

22

slide-23
SLIDE 23

6.1 Sub-Saharan African Transport Policy Program (SSATP) Criteria for Roads Fund

Courtesy Indisys Nig. Limited

Well designed Roads Fund is expected to meet the following criteria:

  • Clear legal foundation
  • Separation of functions
  • Application of road user charges
  • Direct transfer of funds
  • Representation of road users on the board
  • Clear revenue allocation rules
  • Independent auditing of accounts

August 29, 2013

23

slide-24
SLIDE 24
  • 7. Conclusion

Courtesy Indisys Nig. Limited

Implementation of PBMC in the roads sector in Nigeria has the potential to:

  • Positively affect economic activity due to improved road conditions
  • Save cost which can be channeled to the expansion of the road network
  • Enthrone transparency in the management and maintenance of the road network
  • Increase road-user satisfaction with road service and condition

It is however necessary to:

  • Implement requisite road sector reforms (creation of a Roads Fund and a Roads Authority)
  • States and LGAs also need to carry out similar reforms as part owners of the national road network
  • Learn from the experience of other countries that have implemented PBMC

August 29, 2013

24

slide-25
SLIDE 25

Bibliography

Courtesy Indisys Nig. Limited

1. Sultana, M., Rahman, A. and Chowdhury, S. (2012), Performance Based Maintenance of Road Infrastructure by Contracting—A Challenge for Developing Countries, Journal of Service Science and Management, 118-123, Scientific Research. 2. Stankevich, N., Qureshi, N. and Queiroz, C. (2005), Performance-Based Contracting for the Preservation and Improvement of Road Assets, Transport Note No. TN-27, Transport Notes, Roads and Rural Transport Thematic Group, World Bank, Washington D.C. 3. Sultana, M., Rahman, A. and Chowdhury, S. (2012), An Overview of Issues to Consider Before Introducing Performance-Based Road Maintenance Contracting, World Academy of Science, Engineering and Technology 62. 4. Federal Ministry of Works (2013), Compendium Report on Road Infrastructure & Related Development in Nigeria – An Investors Manual, Pison Housing Company, Nigeria. 5. Onolememen, M. (2013), Federal Ministry of Works: Transforming Nigerian Roads, Achievements and Challenges in 2012, Presented to the Federal Executive Council (FEC). 6. Zietlow, G. (2004), Implementing Performance-based Road Management and Maintenance Contracts in Developing Countries, An Instrument of German Technical Cooperation, German Development Cooperation (GTZ), Eschborn, Germany, November, 2004.

August 29, 2013

25

slide-26
SLIDE 26

August 29, 2013 Courtesy Indisys Nig. Limited

26

7. Tirluka, S. (2011), Performance Based Contracts – Case Study of Road Sector 8. Piñero, J. and de la Garza, J. (2003), Issues Related to the Assessment of Performance-Based Road Maintenance Contracts, Proceedings, Towards a Vision for Information Technology in Civil Engineering,

  • pp. 1-8, America Society of Civil Engineers.

9. Zietlow, G.(2011), Cutting Costs and Improving Quality through Performance-Based Road Management and Maintenance Contracts - The Latin American and OECD Experiences, University of Birmingham Senior Road Executives Course 2011. 10. Gwilliam, K., Foster, V., Archondo-Callao, R., Briceño-Garmendia, C., Nogales, A. and Sethi, K. (2008), Roads in Sub-Saharan Africa, Summary of Background Paper 14, Africa Infrastructure Country Diagnostic (ACID), World Bank and SSATP.

slide-27
SLIDE 27

August 29, 2013 Courtesy Indisys Nig. Limited

27

THANK YOU

Download presentation at www.nseph.org