9 km Highway E22 Between Fjlkinge & Gualv TMALL 0794 Presentation bilder sommar v 1.0 TMALL 0794 Presentation bilder sommar South of Sweden Skne Kristianstad 9 km highway - E22 Fjlkinge-Gualv 2 Agricultural


slide-1
SLIDE 1

TMALL 0794 Presentation bilder sommar v 1.0 TMALL 0794 Presentation bilder sommar

9 km Highway E22 Between Fjälkinge & Gualöv

slide-2
SLIDE 2

2

9 km highway - E22 Fjälkinge-Gualöv

South of Sweden – Skåne – Kristianstad

slide-3
SLIDE 3

3

9 km highway - E22 Fjälkinge-Gualöv

Agricultural Landscape

slide-4
SLIDE 4

4

Scope

  • 9,1 km highway - 4 lanes, total width 21,5 m.

ü 5,8 km current road, from width 13 m to 21,5 m. ü 3,3 km new road in a new stretch, width 21,5 m. § 10 km roads for local traffic, paved, width 7 m,

9 km highway - E22 Fjälkinge-Gualöv

slide-5
SLIDE 5

5

9 km highway - E22 Fjälkinge-Gualöv

Scope

§ 6 bus stops. § 2 km bike roads, width 3 m, 1 km gravelled road, width 3,5 m § 4 bridges § 5 pumping stations

slide-6
SLIDE 6

6

9 km highway - E22 Fjälkinge-Gualöv

Scope

§ Additional facilities, i e noice embankments, noice screens, crash barriers, street lightning, sign posts etc. § Drainage – pipes, ponds, dike § Groundwater protection – 2 ponds and 2,5 km of dike § Excavation = 280 000 m3 § Filling masses = 130 000 m3 § Estimated production costs; 300 - 350 MSEK ( 30 – 35 million Euro) § Estimated production time; 30 months, starting 2021