The onshore wind farm at Overgaard 46 new wind turbines in the northern part of Randers Municipality Randers Kommune Program By planner Thomas Djerns from the Planning Section of Randers Municipality Welcome Introduction to the


slide-1
SLIDE 1

Randers Kommune

The onshore wind farm at Overgaard

46 new wind turbines in the northern part of Randers Municipality

slide-2
SLIDE 2

2

Program

By planner Thomas Djernæs from the Planning Section of Randers Municipality

  • Welcome
  • Introduction to the onshore wind farm at Overgaard
  • Questions.

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

slide-3
SLIDE 3

3

Background

  • Randers Municipality is the local planning authority, responsible for the

actual areas, to be proposed for the location of coming wind farms.

  • The City Council of Randers has the final word about which particular

areas in the municipality, that is most appropriate for wind turbines.

  • But before a final decision can be

made by the City Council, plans for the project has to undergo several stages of public hearings.

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

slide-4
SLIDE 4

At Overgaard there´s a large wind power potential, compare to the rest of Randers Municipality

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

Wind power

W / m²

slide-5
SLIDE 5

Randers Kommune – Borgermøde i Udbyneder Forsamlingshus, 04.12.2017.

This area is also one

  • f the most scarcely

populated areas of Mid- Eastern Jutland

Legend

Inhabitants 100 m grid inhabitants inhabitants inhabitants inhabitants inhabitants

slide-6
SLIDE 6

6

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019. Existing wind farm at Overgaard: Light gray dots: 20 wind turbines from 2002. Dark gray dots: 10 wind turbines from 2008. Red dots: Neighbors.

slide-7
SLIDE 7

7

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019. New project: Blue circles: New 46 wind turbines. Red dots: Residential houses. Green dots: Owners of wind turbines. Yellow dots: Agreements on compensation.

1.5 km

1.0 km 600 m

slide-8
SLIDE 8

8

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

27 houses. Residents participate in the project. Future owners of new wind turbines. 4 houses, where residents are critical of the project. No agreement on the amount of conpensation. 7 houses where residents have made an agreement about compensation. 4 houses, where residents have no wish for compensation.

IN TOTAL 42 RESIDENTIAL HOUSES WITHIN 1.5 KM FROM THE WIND FARM AT OVERGAARD

Of the 4 houses with critical residents, one house is situated more than 950 m from the closest existing wind turbine. The other 3 houses are situated more than 1 km from existing wind turbines. Ale 4 houses are situated with unchanged distance to new wind turbines, compared to the existing ones in the area. Residents in 4 out of 42 houses are critical of the project, and can't agree on the amount of compensation offered, by the future owners of wind turbines at Overgaard

slide-9
SLIDE 9

9

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

  • The 46 new wind turbines will be able to

produce  3.6 times more energy than the 30 existing wind turbines at Overgaard.  1.5 times as much as all existing wind turbines in Randers Municipality.  510 mio. kWh annually, in at least 20 years to come.

  • Annual production corresponds to the annual

consumption of electricity in 127,500 private households.

Production on Overgaard wind farm

slide-10
SLIDE 10

10

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

  • If the consumption of

 factories,  private businesses and  public buildings are included in the calculation of total electricity consumption, then the 46 new wind turbines at Overgaard will be able to cover 88 % of the needs of electricity in Randers Municipality.

Production on Overgaard wind farm

slide-11
SLIDE 11

11

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

Public hearing, 8 weeks Public hearing, 10 weeks

  • The detailed written proposals goes to public hearing.
slide-12
SLIDE 12

12

  • http://plan.randers.dk/overgaard
  • E-mail: plan@randers.dk

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

Public hearing, 10 weeks

Main concerns from neighbors are:

  • Noise from wind turbines.
  • Shadows and reflections from wings.
  • Visual disturbance of the coastal landscape.
  • Reduced value of real estate in the area.
slide-13
SLIDE 13

13

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.

Public hearing, 8 weeks

Main concerns from neighbors are:

  • Noise from wind turbines.
  • Shadows and reflections from wings.
  • Visual disturbance of the coastal landscape.
  • Reduced value of real estate in the area.

National investigations into the subject, has not found any clear relation between noise from wind turbines, and the cause

  • f either heart decease, diabetes or

cancer.

slide-14
SLIDE 14

14

Further information

  • http://plan.randers.dk/overgaard
  • E-mail: plan@randers.dk

Introduction to the onshore wind farm at Overgaard, Randers Municipality, 29.01.2019.