2941 fairview park 2941 fairview park eric sobel
play

2941 Fairview Park 2941 Fairview Park Eric Sobel 2941 Fairview - PowerPoint PPT Presentation

2941 Fairview Park Eric Sobel Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option Eric Sobel 2941 Fairview Park 2941 Fairview Park Eric Sobel 2941 Fairview Park PROJECT TEAM Eric Sobel 2941


  1. 2941 Fairview Park Eric Sobel Pennsylvania State University Dept. of Architectural Engineering Spring 2003 Structural Option Eric Sobel 2941 Fairview Park

  2. 2941 Fairview Park Eric Sobel

  3. 2941 Fairview Park PROJECT TEAM Eric Sobel 2941 Fairview L.L.P. • Owner: The David Orr Company • Developer: • Contractor: Clark Construction Boggs & Partners • Architect: Cagley & Associates • Structural: Allen & Shariff • M.E.P.: PCC Consultants • Envelope:

  4. 2941 Fairview Park BUILDING Eric Sobel • $38 Million • 361,101 gross sq. ft • 15 rentable stories • Mechanical Penthouse • Basement • Offices • Atrium • Café • Restaurant

  5. 2941 Fairview Park SYSTEMS Eric Sobel • Mechanical: • VAV System • Chilled Water • 65 Ton AC Units • Electric Heating Coils • Series fan VAV Units • Electrical: • Circuit Breaker Panelboards • K-4 Rated Transformers

  6. 2941 Fairview Park CURTAIN WALL Eric Sobel • E-W: • METAL PANEL • N-S: • PRECAST CONCRETE

  7. 2941 Fairview Park PLAN Eric Sobel TYPICAL TOWER FLOOR PLAN

  8. 2941 Fairview Park EXISTING STRUCTURE Eric Sobel • Gravity System: • Composite A992 Steel • 5 ¼” LW Conc. On Metal Deck • Lateral System: • N-S: 2 Braced Frames • E-W: 5 Braced Frames & 5 Moment Frames • Foundations: • Typical Spread Foundations • Buried Mat Foundation

  9. 2941 Fairview Park PLAN Eric Sobel FOURTH FLOOR PLAN

  10. 2941 Fairview Park REDESIGN Eric Sobel • Goals: • Increase Serviceability • Decrease Initial Cost • Decrease Construction Time • Minimal Architectural Change • Advantages: • Disadvantages: • Quality Control • Increased Weight • Durability • Transportation • Material Strength • Architectural Finish • Quicker Erection

  11. 2941 Fairview Park OUTLINE Eric Sobel • Members: • Building Core • Gravity System • Building Envelope • Connections • Construction: • 4D CAD • Schedule • Estimate

  12. 2941 Fairview Park PLAN Eric Sobel TYPICAL TOWER FLOOR PLAN

  13. 2941 Fairview Park HOLLOWCORE PLANKS Eric Sobel • 8” Hollowcore Planks • Lightweight Concrete • 6 straight ½” tendons • f’c = 5,000 psi

  14. 2941 Fairview Park INVERTED TEES Eric Sobel • 20” x 30” Inverted Tees • Normal Weight Concrete • 4” x 10” Ledges • Straight Tendons • f’c = 8,000 psi

  15. 2941 Fairview Park COLUMNS Eric Sobel • Precast: • 20” x 20” • 4 floor pieces • f’ c ranging from 5,000-12,000 psi • Upper Floors: Lightweight • Corbels

  16. 2941 Fairview Park SPANDREL Eric Sobel • Construction • Reduced Members • Bearing Connection • Composition • 3” Concrete • (2) 1 ½” Insulation • Metal Facing

  17. 2941 Fairview Park WINDOWS Eric Sobel • Waussau Window System • Installation • Inside • Simple

  18. 2941 Fairview Park FOUNDATIONS Eric Sobel • Goals: • Adequate Strength • Cost Effective • Rigid Support for Shearwalls • Pinned Support for Columns

  19. 2941 Fairview Park CONNECTIONS Eric Sobel • Importance: • Define Structural Response • Influences Construction Schedule • Goals: • High Repetition • Relieve Induced Stresses • Easy Erection • Simple Formwork

  20. 2941 Fairview Park BEAM - COLUMN Eric Sobel • Goals: • Diaphragm Action • Induced Stresses • Quick Erection • Columns Stability • Description: • Mastecord Bearing Pads • Supporting Angle • Analysis: • PCI Design Guide • PCHELP

  21. 2941 Fairview Park PRECAST - SITECAST Eric Sobel • Goals: • Transfer Gravity & Lateral Forces • Simple Formwork • Description: • JVI-Inc. BSF 200/40 • “The Invisible Corbel” • Box cast in beam • “Knife” cast in column • Weld Plate • Analysis: • JVI Design Aids

  22. 2941 Fairview Park CONSTRUCTION Eric Sobel DAY 1

  23. 2941 Fairview Park CONSTRUCTION Eric Sobel DAY 1 DAY 2

  24. 2941 Fairview Park CONSTRUCTION Eric Sobel DAY 1 DAY 2 DAY 3

  25. 2941 Fairview Park CONSTRUCTION Eric Sobel DAY 1 DAY 2 DAY 3 DAY 4

  26. 2941 Fairview Park CONSTRUCTION Eric Sobel DAY 1 DAY 2 DAY 3 DAY 4 DAY 5

  27. 2941 Fairview Park CONSTRUCTION Eric Sobel

  28. 2941 Fairview Park SCHEDULE Eric Sobel COMPOSITE STEEL PRECAST

  29. 2941 Fairview Park ESTIMATE Eric Sobel • Composite Steel: $5.95 million • Precast: $6.07 million Site Cast $ Million Flooring Columns Foundations Steel Precast

  30. 2941 Fairview Park CONCLUSIONS Eric Sobel • Drift: 30% Stiffer • Initial Cost: Similar • Construction Schedule: 4 Weeks Quicker • Rentable Area: 650 Additional sq. ft. • Plenum Depth: Varies • Acoustics: 10 dB STL & INR

  31. 2941 Fairview Park THANKS Eric Sobel Thanks to: Joe Ajello, PE Jimmy Lakey, PE All others at Cagley & Associates Mark Tayor Mike Patton Clement Enyeji Prof’s: Parffit, Geschwindner, Boothby, & Burnette All other AE Faculty AE Class of 2003 Karen My Family

  32. 2941 Fairview Park Eric Sobel Questions? • Members • Connections • Construction • Trades Affected

  33. 2941 Fairview Park SHEARWALLS Eric Sobel • East-West: • (4) 22’-8” Shearwall • 24” Thick • North-South: • (2) Shearwall / Moment Frame Lines • 20” Thick • Deep Beams • General: • Locations matched existing braced frame locations • Loadbearing => R=4.0

  34. 2941 Fairview Park MOMENT FRAME Eric Sobel • Location: • Along grid Line H • Lower Portion • Goals: • Increase stiffness to region • Free up Space • Description: • Site cast • Spans parallel to plank

  35. 2941 Fairview Park EXPANSION JOINT Eric Sobel • Goals: • Transfer gravity loads • Transfer E-W lateral loads • Separate N-S lateral loads • Description: • Slotted Connector • Teflon bearing pad

  36. 2941 Fairview Park GROUTED KEYS Eric Sobel • Goals: • Member Connectivity • Diaphragm Action • Description: •Grouted Keys

  37. 2941 Fairview Park PLANK – INVERTED TEE Eric Sobel • Goals: • Diaphragm Action • Induced Stresses • Quick Erection • Description: • Mastecord Bearing Pads • Supporting Angle • Analysis: • PCI Design Guide

  38. 2941 Fairview Park DAPPED BEAM Eric Sobel • Goals: • Transfer Gravity & Lateral Forces • Simple Connection • Description: • Mastecord Bearing Pad • Analysis: • PCI Design Method • PCHELP

  39. 2941 Fairview Park DAPPED BEAM Eric Sobel

  40. 2941 Fairview Park COLUMN SPLICE Eric Sobel Goals: • Aesthetically pleasing • Transfer only axial and shear loads • Simple erection Description: • Bolted connection • Grouted • Splice occurs just above floor level Analysis: • PCI design aids

  41. 2941 Fairview Park FEATURES Eric Sobel • Architectural Atrium • Entrance Plaza • ME/TC rooms per floor • Tenant Build-Out • Superb Landscaping

  42. 2941 Fairview Park SCHEDULE Eric Sobel • General: •20 columns / day •20 beams / day •40 planks / day •Core: 1 level / week •Windows: 1 level / week • Core: •2 weeks ahead • Windows: •2 weeks behind

  43. 2941 Fairview Park DETAIL Eric Sobel BUILDING END DETAIL

  44. 2941 Fairview Park CRANES Eric Sobel

  45. 2941 Fairview Park TRANSPORTATION Eric Sobel

  46. 2941 Fairview Park TRADES AFFECTED Eric Sobel

  47. 2941 Fairview Park TRADES AFFECTED Eric Sobel

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend