2021 & 2025 Final LCR Study Results Stockton Area Ebrahim - - PowerPoint PPT Presentation

2021 2025 final lcr study results
SMART_READER_LITE
LIVE PREVIEW

2021 & 2025 Final LCR Study Results Stockton Area Ebrahim - - PowerPoint PPT Presentation

2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13, 2020 ISO Public ISO Public Stockton Area Transmission System & LCR Sub-areas Vierra Legend: Bellota


slide-1
SLIDE 1

ISO Public ISO Public

2021 & 2025 Final LCR Study Results Stockton Area

Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13, 2020

slide-2
SLIDE 2

ISO Public

Stockton Area Transmission System & LCR Sub-areas

Slide 2

Legend:

Rio Oso 230 kV Lockeford 60 kV

Lockeford LCR Sub-Area

Lodi 60 kV Industrial 60 kV 60 kV Colony 60 kV Victor 60 kV Lockeford 230 kV Bellota 230 kV 230 kV Wodberg 60 kV

Manteca 115 kV

Legend:

115 kV Kasson 115 kV Vierra 115 kV Schulte Tesla 115 kV Tracy Salado 115 kV Ingram Creek 115 kV

G

GWF Tracy Units Lammers Melones 115 kV Bellota 115 kV Riverbank 115 kV Tulloch 115 kV Stanislaus 115 kV Ripon 115 kV Riverbank JCT 115 kV Bellota 230 kV

Stanislaus Tesla - Bellota Lockeford

Weber was a sub-area within the Stockton area in the past, requiring generation to address P6 contingencies on 60 kV non-bulk

  • system. However due to change in

LCR criteria, Weber doesn’t have any LCR requirement.

slide-3
SLIDE 3

ISO Public

New major transmission projects

Slide 3

Project Name Expected ISD Year 2021 Ripon 115 kV Line Operational since May 2019 Stockton A – Weber #1 & #2 60 kV lines Reconductor Operational since Aug. 2019 Year 2025 Vierra 115 kV Looping Project Jan-23 Tesla 230 kV Bus Series reactor Dec-23 Lockeford-Lodi Area 230 kV Development Jun-25

slide-4
SLIDE 4

ISO Public

Power plant changes

Additions:

  • No new resource addition

Retirements:

  • No new retirements

Slide 4

slide-5
SLIDE 5

ISO Public

Stockton Area Overall: Load and Resources

Slide 5

Load (MW) 2021 2025 Generation (MW) 2021 2025 Gross Load 1,095 938 Market/ Net Seller/ Battery 445 491 AAEE

  • 4
  • 7

Solar 12 12 Behind the meter DG Wind Net Load 1,091 931 Muni 139 116 Transmission Losses 22 19 QF Pumps Future preferred resource and energy storage Load + Losses + Pumps 1,113 950 Total Qualifying Capacity 596 619

slide-6
SLIDE 6

ISO Public

Lockeford Sub-Area : Requirements

Slide 6

Year Category Limiting Facility Contingency LCR (MW) (Deficiency) 2021 P3 Lockeford – Lodi #2 60 kV Lockeford-Industrial 60 kV line and Lodi CT 36 (12) 2025 All No requirements due to Lockeford-Lodi Area 230 kV Development project

Lockeford Lodi Industrial

New Hope Colony Victor Lodi Jct Lockeford-Lodi #1 Lockeford-Industrial Lockeford-Lodi #2 Lockeford-Lodi #3

Legend:

60 kV

X X

Contingency Overload

slide-7
SLIDE 7

ISO Public

Lockeford Sub-area: Load Profiles

Slide 7

Lockeford Sub-area LCR requirement will be eliminated due to the Lockeford--Lodi Area 230 kV development transmission project expected to be in service in 2025

slide-8
SLIDE 8

ISO Public

Stanislaus Sub-Area : Requirements

Slide 8

Year Category Limiting Facility Contingency LCR (MW) (Deficiency) 2021 P3 Manteca - Ripon 115 kV Line Bellota-Riverbank-Melones 115 kV line and Stanislaus PH unit 205 2025 P3 Manteca - Ripon 115 kV Line Bellota-Riverbank-Melones 115 kV line and Stanislaus PH unit 213 (1) Manteca 115 kV Melones 115 kV Bellota 115 kV Riverbank 115 kV Tulloch 115 kV Stanislaus 115 kV Ripon 115 kV Bellota – Riverbank – Melones SW STA Bellota – Riverbank Riverbank JCT SW STA - Menteca Stanislaus – Melones SW STA - Manteca Stanislaus – Melones SW STA – Riverbank JCT SW STA Stanislaus – Manteca #2 Riverbank JCT 115 kV

X Legend:

115 kV

X

Contingency Overload

slide-9
SLIDE 9

ISO Public

Slide 9

Year

Category

Limiting Facility Contingency LCR (MW) (Deficiency) 2021 P2-4 Stanislaus – Melones – Riverbank Jct line Tesla 115 kV bus 690 (117 NQC/129 Peak) 2021 P6 Schulte-Kasson- Manteca 115 kV line Schulte – Lammers and Tesla – Tracy 115 kV lines 909 (646 NQC/658 Peak) Total LCR Need in 2021 1,219 (646 NQC/658 Peak)

Tesla - Bellota Sub-Area : Requirements (2021)

Manteca 115 kV

Legend:

115 kV Kasson 115 kV Vierra 115 kV Schulte Tesla 115 kV Tracy Salado 115 kV Ingram Creek 115 kV

G

GWF Tracy Units Lammers

X X

Melones 115 kV Bellota 115 kV Riverbank 115 kV Tulloch 115 kV Stanislaus 115 kV Ripon 115 kV Riverbank JCT 115 kV Bellota 230 kV

slide-10
SLIDE 10

ISO Public

Slide 10

Year

Category

Limiting Facility Contingency LCR (MW) (Deficiency) 2025 P2-4 Stanislaus – Melones – Riverbank Jct line Tesla 115 kV bus 674 (55 NQC/67 Peak) 2025 P6 Tesla – Vierra 115 kV line Schulte – Lammers and Schulte-Kasson- Manteca 115 kV lines 431 (122 NQC/134 Peak) Total LCR Need in 2025 741 (122 NQC/134 Peak)

Tesla - Bellota Sub-Area : Requirements (2025)

Manteca 115 kV

Legend:

115 kV Kasson 115 kV Vierra 115 kV Schulte Tesla 115 kV Tracy Salado 115 kV Ingram Creek 115 kV

G

GWF Tracy Units Lammers

X X

Melones 115 kV Bellota 115 kV Riverbank 115 kV Tulloch 115 kV Stanislaus 115 kV Ripon 115 kV Riverbank JCT 115 kV Bellota 230 kV

slide-11
SLIDE 11

ISO Public

Tesla - Bellota Sub-area: Load Profiles

Slide 11

slide-12
SLIDE 12

ISO Public

Slide 12

Sub-area 2020 2021 Load LCR Load LCR Lockeford 190 97 (73) 194 36 (12) Weber 238 26 243 N/A Stanislaus N/A 179 N/A 205 Tesla - Bellota 848 1,117 (543) 898 1,219 (658) Total 1,275 1,241 (616) 1,349 1,255 (670) LCR increases in sub-areas are mostly due to load increase. The LCR decreases in sub-areas are due to the change in criteria.

N/A=Flow-through area. No defined load pocket or not an LCR sub-area anymore

Changes from 2020 to 2021

slide-13
SLIDE 13

ISO Public

Changes from 2024 to 2025

Slide 13

Reduction in total LCR is due to transmission development or some sub-areas not being an LCR sub-area anymore due to change in LCR criteria.

N/A=Flow-through area. No defined load pocket.

Sub-area 2024 2025 Load LCR Load LCR Lockeford 193 102 (78) 198 N/A Weber 238 26 247 N/A Stanislaus N/A 185 N/A 213 (1) Tesla - Bellota 899 881 (260) 950 741 (134) Total 1,330 1,009 (338) 1,395 741 (134)

slide-14
SLIDE 14

ISO Public

Stockton Area Total LCR Need

Slide 14

Study Year Existing Generation Capacity Needed (MW) Deficiency (MW) Total MW Need 2021 585 670 1,255 2025 607 134 741