2018 Call for Projects Draft Recommendations Alan Clark January - - PowerPoint PPT Presentation

2018 call for projects draft recommendations
SMART_READER_LITE
LIVE PREVIEW

2018 Call for Projects Draft Recommendations Alan Clark January - - PowerPoint PPT Presentation

2018 Call for Projects Draft Recommendations Alan Clark January 16, 2019 Call for Projects Available Funding ($920M) Funding Funding STBG STBG TASA SA Cat 2. Cat 2. Total tal CMAQ CMA Program Pr Total Avail $629 M $609 M


slide-1
SLIDE 1

2018 Call for Projects Draft Recommendations

Alan Clark

January 16, 2019

slide-2
SLIDE 2

Call for Projects – Available Funding ($920M)

Funding Funding Pr Program CMA CMAQ STBG STBG TASA SA Cat 2. Cat 2. Total tal

Total Avail $629 M $609 M $20 M $0 $1259 M Set - Asides

  • $200 M
  • $139 M

$0 $0

  • $339 M

Cat 2. Swap $0

  • $127 M

$0 +$127 $0 Fed + Match $429 $343 M $20 $127 $920 M Fed @ 80% $343 M $275 M $16 M $127 $761 M

slide-3
SLIDE 3
  • 193 Proposed Projects
  • $2.9B Funding Request

Call for Projects

slide-4
SLIDE 4

Call for Projects – Project Scoring

  • Planning factors scores

Planning factors scores

  • Vary based on type of project
  • Planning Coordination, Environmental Justice,

Roadway Hierarchy, Multimodal LOS, etc.

  • Benefit/Cost R

Benefit/Cost Ratios tios

  • Total Benefits/Funding Requested
slide-5
SLIDE 5

Call for Projects – Project Scoring

  • Scaled Benefit/Cost Scores

Scaled Benefit/Cost Scores

  • B/C Ratio > 1.0 (Between 10 to 100 Points)
  • B/C Ratio < 1.0 (0 Points)
  • Similar investment categories were grouped into

1 of five “Strategies”

slide-6
SLIDE 6

B/C Grouping of Investment Categories

Strategy Strategy Investment Category Investment Category # of P # of Projects

  • jects

Major Investments (5) Project Cost More Than $100 M 5 Expand (64) Added Capacity 59 Transit Expansion 2 Transit Passenger Facilities 3 Maintain (29) Infrastructure Resiliency 10 Rehabilitation/Reconstruction 16 Transit Facility State of Good Repair 3

slide-7
SLIDE 7

B/C Grouping of Investment Categories

Strategy Strategy Investment Category Investment Category # of P # of Projects

  • jects

Manage (53) Access Management/Grade Separations 33 ITS Infrastructure 17 Transit Priority Infrastructure 3 Active Transportation Bike and Pedestrian Infrastructure 42

Total tal 193 193

slide-8
SLIDE 8

Converting B/C Ratio to a “Score”

  • B/C Ratios > 1.0 Converted into Scaled Scores
  • For each strategy, B/C scores >1/0 divided into six

groups

  • Bottom 1/6th Scored 10 – 17 Points
  • Next 1/6th Scored 17 – 33 Points
  • Top 1/6th B/C Ratios Scored 87 – 100 Points
slide-9
SLIDE 9

B/C Scoring – Expand Strategy

10 20 30 40 50 60 70 80 90 100 1 2 3 4 5 6 7 8

Scaled B/C Ratio Scores B/C Ratios B/C Ratio Scores

5-10 10-20 >20

slide-10
SLIDE 10

B/C Scoring – Manage Strategy

10 20 30 40 50 60 70 80 90 100

10 20 30 40 50 60 70 80 90 100

Scaled B/C Ratio Scores B/C Ratios B/C Ratio Scores

>

slide-11
SLIDE 11

B/C Scoring – Maintain Strategy

10 20 30 40 50 60 70 80 90 100 1 2 3 4 5 6

SCALED B/C RATIO SCORES B/C RATIOS SCORES B/C B/C RATIOS

slide-12
SLIDE 12

B/C Scoring – Active Transportation

10 20 30 40 50 60 70 80 90 100 2 4 6 8 10

SCALED B/C RATIO SCORE B/C RTIOS B/C RATIO SCORES

slide-13
SLIDE 13

B/C Scoring – Major Investments

  • Three of Five P

Three of Five Projects Candidates for Funding

  • jects Candidates for Funding
  • Inner Katy Busway – B/C score 1.81 = 100 pts
  • Hempstead Highway – B/C score 1.76 = 75 pts
  • Shepard/Durham Drive – B/C score 1.09 = 50 pts
slide-14
SLIDE 14

Call for Projects – Draft Recommendation

  • Projects scoring 150 points or more appear to be

fundable IF:

  • Projects meet “Readiness Requirements”. Delays

beyond sponsor identified “Readiness Year” could increase project cost and reduce funding available.

  • Only 1 of the three “Major Projects” is found “Ready”

(For purposes of this analysis Inner Katy Busway is assumed to be funded)

slide-15
SLIDE 15

Call for Projects – Draft Recommendation

  • Projects scoring 150 points or more appear to be

fundable IF:

  • METRO Bus Accessibility Project funded at $30M
  • Pelican Island Bridge Replacement is funded at $18M
  • Project sponsors with projects scoring more than

100 points should be invited to add their project to RTP

slide-16
SLIDE 16

Investment Investment Strategy Strategy >150 P >150 Points ints >145 P >145 Points ints >140 P >140 Points ints

Major Inv. $190 M $175 M $80 M Expand $307 M $395 M $465 M Manage $52 M $52 M $110 Maintain (+ADA) $103 M $143 M $188 Active Transport $16 M $16 M $16 M

Total tal $668 M $668 M $781 M $781 M $859 M $859 M

Call for Projects – Funding vs Scoring

  • Funding Requests in YOE Dollars
  • Metro ADA and Pelican Island Projects to Maintain
  • Not Recommending US 90 A Widening from FM 359 to 99 Project in “150” Scenario
slide-17
SLIDE 17
  • Public Comment Period
  • http://www.h-gac.com/2018-call-for-

projects/submitted-applications.aspx

  • Complete Review of Project Readiness
  • Consult with project sponsors on candidates for

RTP

  • Prepare final recommendations

Call for Projects – Next Steps

slide-18
SLIDE 18
  • January 24, 2019 – Friendswood City Hall
  • January 29, 2019 – Liberty City Hall
  • February 5, 2019 – Kingdom City Houston
  • February 7, 2019 – Tomball City Hall
  • February 12, 2019 – HGAC Office

Call for Projects – Public Meetings

slide-19
SLIDE 19

Call for Projects Schedule

July Aug Sept Oct Nov Dec Jan Feb March Evaluation Criteria Evaluation Criteria Workshop Approve Project Call Application Submission Application Workshop Project Selection/Prioritization Draft Project List 30 Day Public Comment Project Recommendation

TIP TIP/RTP Subc P Subcommitte ttee Meet e Meeting Transpor ansportation tation Advi visor sory C Comm mmittee M ittee Meeting ing Transportati tion P Poli licy Co Coun uncil Meeti Meeting Appl Applic ication W ation Workshop Appl Applic ication Su ation Submis ission

  • n

Projects S

  • jects Select

ction/P ion/Priorit ioritizat zation

  • n

Pu Public C Comment Period

2019

slide-20
SLIDE 20

More Information

  • Vishu Lingala: Vishu.Lingala@h-gac.com
  • Phone: 713-993-4561
slide-21
SLIDE 21

Set – Aside Programs

Set - Aside Program Funding in $Millions

Regional ITS (TranStar) $16 Regional Incident Management (Towing) $84 Regional Incident Management (MAP/IMU) $42 Clean Cities/Clean Vehicles $52 TDM Marketing/Outreach (Commute Solutions) $30 Regional Vanpool $43 Pilot/Commuter Transit Operations $39 Transit Regional Fare Collection System $20 1 % for Planning $13 TOTAL $339