Tab 19 2018/19 Performance Benchmark Report Directors Office of Asset Management 1 What is the Performance Benchmark Report? CTC Guidelines: CTC Guidelines require an annual report to the Commission showing progress toward asset


  1. Tab 19 2018/19 Performance Benchmark Report Director’s Office of Asset Management 1

  2. What is the Performance Benchmark Report? • CTC Guidelines: CTC Guidelines require an annual report to the Commission showing progress toward asset management and SB1 performance targets • What’s in the Report: Reports the current condition and future projections relative to the 19 established baseline conditions 2017- 2027. • Timing: The 2018/19 Performance Benchmark Report is presented in October of each year. This is the second reporting with actual conditions through 20% of the time period (2017- 2027) Slide 2

  3. Benchmark Development Slide 3

  4. Report Features Slide 4

  5. Summary of Progress on SB1 Targets Slide 5

  6. Culvert Condition Detail Slide 6

  7. TMS Projection Slide 7

  8. TMS Challenges • Data quality and business process for post project updates • Reporting of project level accomplishments Slide 8

  9. Summary of Progress on Asset Management Targets Slide 9

  10. Bridge Condition Slide 10

  11. SHOPP Bridge Project Timeline Average Time Period = 9.5 Years On - 2 1 2.2 1.6 0.5 Year 1.2 1 going Years Year Years Years Years Year TAMP Planning Program Capital Outlay Support (COS) COS Closeout Allocation Construction PS&E (Design) Need & Programming & Allocation Priority Re - inspection PA&ED PID Allocation Identified Right of Way Programming PA&ED End Project Design Complete, RTL and Right of Way Certification Begin Construction End Construction Complete DEFINITIONS TAMP Transportation Asset Management Plan PID Project Initiation Document PA&ED Project Approval and Environmental Document PS&E Plans, Specifications and Estimate RTL Ready to List for Advertising Slide 11

  12. Bridge Corrective Strategies • Permit streamlining – AB 1282 • Increase the Bridge Project Portfolio • Utilize quicker delivery programs • SHOPP • Potential Programming Changes • Liberal use of Long Lead for Bridges • Innovative Delivery (Design Build, CMGC) • Inspection Data Update • Post project update coordination Slide 12

  13. Conclusion • Overall, we are making good progress • Watching LOS and TMS • Need to make changes to achieve bridge condition targets Slide 13

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.