2017 Bond Program, Proposition D: Hughes Lane at Kalani Place Storm - - PowerPoint PPT Presentation

2017 bond program proposition d
SMART_READER_LITE
LIVE PREVIEW

2017 Bond Program, Proposition D: Hughes Lane at Kalani Place Storm - - PowerPoint PPT Presentation

2017 Bond Program, Proposition D: Hughes Lane at Kalani Place Storm Drainage Improvement Project March 25, 2019 Matt Penk, P.E. Assistant Director Capital Improvements Dallas Water Utilities Welcome/Introductions/Opening Remarks


slide-1
SLIDE 1

March 25, 2019

Matt Penk, P.E. Assistant Director Capital Improvements Dallas Water Utilities

2017 Bond Program, Proposition D:

Hughes Lane at Kalani Place Storm Drainage Improvement Project

slide-2
SLIDE 2

Welcome/Introductions/Opening Remarks

  • Welcome/Introduction:

Honorable Lee Kleinman

Council District 11

  • Team Introductions:

Matt Penk

  • Presentation:

Clifton Miller / Matt Penk

2

slide-3
SLIDE 3

Agenda

  • Project History & Purpose
  • Proposed Improvements
  • Schedule and Next Steps
  • Community Conversation

3

slide-4
SLIDE 4

Process

  • Presentation (20 Minutes)
  • Moderated Conversation (30 Minutes)
  • Questions/Input collected via index cards during presentation
  • Moderator sorts and groups index cards with similar content and

directs questions/input to City staff for response

  • Post meeting questions/inputs can be directed to City’s

Project Team

4

slide-5
SLIDE 5

Project History & Purpose

5

slide-6
SLIDE 6

Drainage Area

  • Part of White Rock

Creek Tributary #6

  • Total Drainage Area at

Hughes Lane ~ 105 acres

  • Includes 4 private ponds

in series

6

slide-7
SLIDE 7

7

Drainage Area - Ponds

slide-8
SLIDE 8

Drainage System

  • Drained at Hughes Lane

through a morning glory and auxiliary spillway

  • Drainage system built by

developer around 1960 to serve neighborhood drainage

  • Additional connectivity to the City’s

storm drainage system in the 1970’s

8

slide-9
SLIDE 9

Flood Risk Management

  • Flooding concerns expressed since the 1970’s
  • Additional inlets added on Hughes Lane in 1974
  • Flood risk management project included in City’s

Unfunded Needs Inventory in 1979

  • Flooding persisted and a study was initiated in 1988

that recommended upsizing underground pipes and modifications to the spillway

9

slide-10
SLIDE 10

Hughes Lane Flooding

10

slide-11
SLIDE 11

Flood Risk Management

  • In 2017 the City commissioned a study to reassess

current conditions and flood risk on Hughes Lane at Kalani Place

  • Study included field evaluation, survey, and flood

modeling

  • Study concluded:
  • Hughes Lane is overtopped during a 1-year storm
  • Hughes Lane considered hazardous crossing in 100-year storm
  • Improvements needed to alleviate flooding and hazardous road

condition

11

slide-12
SLIDE 12

Proposed Improvements

12

slide-13
SLIDE 13

Drainage Improvements

  • 2017 Study recommended the following:
  • Approximately 115-foot long dual 6’ x 6’ box culvert

under Hughes Lane

  • Overflow weir from pond and channel connected to

box culvert

  • Approximately 30 feet of open back inlets on Hughes

Lane draining to 36” pipe connected to box culvert

13

slide-14
SLIDE 14

Implementation

  • 2017 Bond Program includes $800,000 for drainage

improvements for this project (design and construction)

  • Design request for qualifications has been

completed and design firm selected

  • City Council consideration of the design contract

planned for May 22, 2019

14

slide-15
SLIDE 15

Schedule / Next Steps

15

slide-16
SLIDE 16

Next Steps

  • Design team will begin design in Late Spring/Early

Summer 2019

  • Proposed work will be advanced and community

updated in Fall 2019

  • Design will incorporate neighborhood feedback,

where possible, and is anticipated to be complete Summer 2020

  • Construction may begin as early as Fall 2020 and

be completed Summer 2021

16

slide-17
SLIDE 17

Community Update Milestones

17

Phase Date Comments

Preliminary Design Fall 2019 Community Update Final Design Summer 2020 Community Update Construction Start Fall 2020 Community Meeting Construction Completion Summer 2021 Community Update

slide-18
SLIDE 18

Dallas Water Utilities Project Team

18

Team Member /Contact Information Role

Matt Penk, P.E. 214-671-9560 matthew.penk@dallascityhall.com Assistant Director Capital Improvements Abidur Khan, P.E. 214-671-9526 abidur.khan@dallascityhall.com

  • Sr. Program Manager

Stormwater Project Management Shazia Ahmed, P.E. 214-948-4192 shazia.ahmed@dallascityhall.com Project Manager Stormwater Project Management Estela Ornelas 214-671-9554 Estela.ornelas@dallascityhall.com

  • Sr. Community Engagement Specialist
slide-19
SLIDE 19

Community Conversation

19

slide-20
SLIDE 20

Adjourn

20