2013 Bond Referendum Board of Education Presentation July 23, 2013 - - PowerPoint PPT Presentation
2013 Bond Referendum Board of Education Presentation July 23, 2013 - - PowerPoint PPT Presentation
2013 Bond Referendum Board of Education Presentation July 23, 2013 Agenda Promises Made, Promises Kept Timeline 2013 Bond Referendum Project List Projects by Board of Education District Questions 2 Promises Made, Promised
- Promises Made, Promises Kept
- Timeline
- 2013 Bond Referendum Project List
- Projects by Board of Education District
- Questions
2
Agenda
- 24 New Elementary Schools
$293.7M Promises Made, Promised Kept 1996 - 2008 Bond Expenditures 3
School District Highland Renaissance Academy 3 Joseph W. Grier Academy 3 Walter G. Byers Elementary 2 Mountain Island Elementary 1 Providence Spring Elementary 6 Endhaven Elementary 6 Torrence Creek Elementary 1 Highland Creek Elementary 1 J.V. Washam Elementary 1 Winget Park Elementary 2 Polo Ridge Elementary 6 Ballantyne Elementary 6 Barnette Elementary 1 Croft Community School 1 Elon Park Elementary 6 Whitewater Academy 2 Berewick Elementary 2 River Oaks Academy 1 Stoney Creek Elementary 3 River Gate Elementary 2 Grand Oak Elementary 1 Winget/Lake Wylie Relief 2 *Highland Creek Relief 1 *Hickory Grove Relief 4
4
- 8 New Middle Schools
$170.1M
School District Jay M. Robinson Middle 6 Martin Luther King, Jr. Middle 3 Mint Hill Middle 6 Southwest Middle 2 Community House Middle 6 Bailey Middle 1 Ridge Road Middle 1 Whitewater Middle 2 School District Hopewell High 1 E.E. Waddell High 2 Phillip O. Berry Academy of Technology 2 Ardrey Kell High 6 Mallard Creek High 1 Hough High 1 Rocky River High 6
- 7 New High Schools
$328.4M Promises Made, Promised Kept 1996 - 2008 Bond Expenditures (continued)
5
- 17 Replacement Elementary Schools
$186.7M
School District Druid Hills Elementary 3 Barringer Academic Center 2 Highland Mill Montessori 3 Lincoln Heights Elementary 2 Sedgefield Elementary 5 J.H. Gunn Elementary 4 Sterling Elementary 2 Merry Oaks Elementary 4 Selwyn Elementary 5 First Ward Creative Arts Academy 3 Windsor Park Elementary 4 Pinewood Elementary 5 Hickory Grove Elementary 4 Long Creek Elementary 1 Bain Elementary 6 Pineville Elementary 6 *Newell Elementary 3
Promises Made, Promised Kept 1996 - 2008 Bond Expenditures (continued)
6
- 2 Replacement Middle Schools
$44.4M
School District Military & Global Leadership Academy at Marie G. Davis 2 McClintock Middle 4
- 1 Replacement High School
$22.8M
- Renovations at 91 Schools
$713.9M Total 1996-2008 Bond Expenditures $1,760B Promises Made, Promised Kept 1996 - 2008 Bond Expenditures (continued)
School District Metro 3
*Project not started and not included in the total Bond Expenditure amount
Timeline
- Capital Needs Assessment (CNA)/Capital Improvement Plan (CIP) Presentation to
Board of Education (BOE) (3-26-13)
- Scorecards Submitted to County Staff (4-16-13)
- CIP Approved by BOE (4-23-13)
- County Chief Financial Officer Presentation to BOE (4-23-13)
- Superintendent Presents CIP to Board of County Commissioners (BOCC) (5-7-13)
- County Approval of CMS Capital Program (5-21-13)
- County Approval of Revised CMS Capital Program (6-18-13)
- BOE Asked to Adopt Resolution for Bond Referendum (7-23-13)
- BOCC Adopts Bond Referendum (8-6-13)
- Bond Referendum (11-5-13)
7
2013 Bond Referendum Project List and Anticipated Delivery Dates
Project Budget Anticipated Delivery BOE District Oakhurst STEAM Magnet ES/Starmount ES Conversion $5,940,000 August 2015 4,5 Nations Ford ES Replacement $19,440,000 August 2016 2 Statesville Road ES Replacement $20,340,000 August 2016 3 Olympic HS Addition/Renovation $8,964,000 January 2017 2 J.M. Alexander MS Replacement $30,672,000 August 2017 1 New Language Immersion PK-8 Albemarle
- Rd. ES/MS Relief
$30,376,000 August 2017 4 New PK-8 Berryhill-Reid Park Relief $30,376,000 August 2017 2 Selwyn ES Renovation $2,592,000 January 2018 5 East Mecklenburg HS Addition $12,744,000 August 2018 4 8
Project Budget Anticipated Delivery BOE District Myers Park HS Addition $22,248,000 August 2018 5 Northridge MS Addition $6,448,000 August 2018 3 Northwest School of the Arts Renovation $12,420,000 August 2018 2 South Mecklenburg HS Addition $18,360,000 August 2018 5 Davidson K-8 Conversion $9,500,000 January 2019 1 Career and Technology Education Phase I: Garinger/West Meck/ North Meck/Independence $8,640,000 August 2019 1,2,3,6 PK8 Conversion Phase II (Ashley Park, Bruns Ave, Walter G. Byers, Druid Hills, Reid Park, Westerly Hills) $24,732,000 August 2019 2,3 New STEAM K-8 (Potential Ballantyne, Elon, Hawk Ridge, Polo, Community House, Jay M. Robinson Relief) $31,376,000 August 2019 6 Total $295,168,000
2013 Bond Referendum Project List and Anticipated Delivery Dates (Continued)
9
District Number of Projects Total 1 3 42,332,000 2 6 93,880,000 3 4 33,160,000 4 3 44,740,000 5 4 47,520,000 6 2 33,536,000 $295,168,000
Total Projects Per BOE District
7
10