2012 half yearly results
play

2012 Half Yearly Results 23 August 2012 Forward looking statements - PowerPoint PPT Presentation

2012 Half Yearly Results 23 August 2012 Forward looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are


  1. 2012 Half Yearly Results 23 August 2012

  2. Forward looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject to known and unknown risks and uncertainties. A number of factors could cause actual results, performance or events to differ materially from those expressed or implied by these forward-looking statements. 23 August 2012 | Page 1

  3. Agenda Introduction Simon Lockett Operations update Neil Hawkings Exploration update Andrew Lodge Financial results Tony Durrant Outlook Simon Lockett 23 August 2012 | Page 2

  4. Premier today ... is in an even stronger position than ... which is reflected in our first half six months ago ... results • Stronger production and resource base • Production up 58% year-on-year; pro-forma resources of 725 mmboe • Portfolio of operated developments will • Solan, Pelikan, Naga and Dua approved; deliver 100,000 boepd Catcher moving forward • Acquisition activity positions us for future • Falkland Islands transaction growth beyond 100,000 boepd • Transforming the exploration portfolio • Prospective resource portfolio increased to 2.7 billion boe • Existing projects, dividend and future • $1.3 billion of cash and undrawn facilities; exploration programme fully funded strongly rising cashflows and profitability Historic NAV/share CAGR of 14.2% at constant oil prices 23 August 2012 | Page 3

  5. Operations update 23 August 2012 | Page 4

  6. Production update • Production averaged 58,400 boepd, up Huntington/Rochelle 2012 Production Other UK (bbls/day) 58 per cent Pakistan & Mauritania Vietnam – Q2 production in excess of 60,000 boepd 80,000 Indonesia • Chim Sáo and Gajah Baru performing well 70,000 • Strong Pakistan production due to compression 60,000 upgrades and successful infill drilling • Improved uptime at Balmoral and good 50,000 production from a new well at Scott • Increased share of Wytch Farm production 40,000 following completion of acquisition 30,000 • 75,000 boepd, once Huntington and Rochelle on-stream 20,000 10,000 0 Q1 Q2 Q3 Q4 Year end run rate 23 August 2012 | Page 5

  7. Chim Sáo and Dua Chim Sáo • 1H Production averaged 26,000 boepd; higher level of uptime achieved in Q2 • Currently producing at 35,000 boepd • Water injection has commenced and rates are ramping up to support reservoir pressure • Two well supplementary drilling programme into additional reservoirs completed in June – first well tied-in; initial production rate of 4,000 boepd – second well due on-stream in Q3 • Total well capacity in excess of 40,000 bopd Dua • Dua will develop ~10 mmbbls • Prime Minister approval of FDP received in August • Long lead items being procured and contracted • Development drilling to commence in April 2013 • Subsea installation and tie-in in Summer 2013 • First oil 2014 23 August 2012 | Page 6

  8. Natuna Sea Block A GSA 1 (Anoa) • 1H production at maximum capacity • Block A’s share of deliveries under GSA1 was 47% against a contractual market share of 37% • Block A’s share of remaining reserves dedicated to GSA1 was 64% at start of year (before the Anoa Deep discovery) GSA 2 (Gajah Baru) • Production facility has performed very well • All Singapore demand was met during the period but build-up of rates has been slower than anticipated due to end user project delays Gas Swap Agreement (Gajah Baru) • Discussions to sell an additional 40 BBtud into the Indonesian domestic market continue 23 August 2012 | Page 7

  9. Anoa Phase 4, Pelikan and Naga Anoa Phase 4 Pelikan and Naga • Project will increase Anoa reserves by ~200 bcf • Pelikan and Naga will develop ~150 bcf of gas by lowering surface flowing pressures • EPCI contract awarded in May • Also increases Anoa capacity above 200 BBtud – Construction of jacket / topsides commenced • Construction barge has arrived on location; • Construction of pipeline material underway compression modules currently being installed • Tendering process to secure a rig for 2013 and • Second construction campaign prior to first gas 2014 development drilling commenced in Q3 2013 • First gas 2014 23 August 2012 | Page 8

  10. Huntington and Rochelle Huntington Rochelle • Development drilling completed in August • Drilling of East Rochelle, the first of the two development wells, is in progress – To schedule and on budget – Better than expected well results • Upgrade of Scott Platform remains on track – Debottlenecking study underway • Subsea installation underway following the • FPSO onshore modifications nearing completion arrival of the pipe lay vessel • Operator expecting first gas in December • Operator targeting sail away in September for installation in October and first oil in December 23 August 2012 | Page 9

  11. Solan • Premier is Operator with 60% equity • All significant contracts have been awarded – Procurement and fabrication of platform (Burntisland Fabrications) – Heavy lift installation (Heerema) – Subsea tank fabrication (Dry Docks World Dubai) – Drilling rig (Awilco) • Construction of topsides has commenced • Phase 1 development drilling expected to commence in March 2013 • First oil targeted for Q4 2014 with an initial production rate of 24,000 bopd 23 August 2012 | Page 10

  12. Solan development schedule 2012 2013 2014 Government Approval First Oil Platform Tank Drilling Installation, Hook-up and Commissioning FEED Design and Procurement Construct 23 August 2012 | Page 11

  13. Catcher update Significant licence changes • Premier increased stake to 50% and appointed operator • Strengthened partnership to progress development • Time is needed to achieve consensus within new JV Concept Selection work • JV agreed subsurface work programme is in progress to generate resource volume ranges • Schedule and cost data for development concepts has been validated through market enquiries FPSO and Subsea Wells • Contracting strategies have been developed • Concept Selection Recommendation has recently been made to JV • Continue to work with JV to expedite approval process and first oil now modelled for early 2016, subject to FPSO contractor discussions 23 August 2012 | Page 12

  14. Non-operated projects Bream • Completed SPA with Skeie in July; increased equity in Bream to 40% • FPSO and SURF FEED near completion • Operator planning project sanction in October – Cost pressures – Scope for area development exists • Operator targeting 2015 for first oil Frøy Block A Aceh • Joint Area Studies are underway with other • EPCI re-tender resulted in higher than operators to identify and evaluate the anticipated bids preferred options for an area development – Revisiting gas price with buyer 23 August 2012 | Page 13

  15. Sea Lion – transaction rationale • Progresses Premier’s strategy of growth through Pro-forma 2P Reserves and 2C Contingent Resources (mmboe) investment in high quality development projects 800 • Provides a further operated core area for Premier 600 in a new oil prone basin • Leverages Premier’s strong operatorship and 400 FPSO development capabilities 200 • Ongoing exploration opportunities in the North 0 Falklands basin, leveraging Rockhopper’s proven 2P Reserves 2C 2P Reserves Falkland Pro-forma 2P Contingent & 2C Islands Reserves & 2C exploration expertise Resources Contingent Farm-in Contingent Resources Resources • Adds approximately 200 mmbbls of net discovered Pro-forma 2P Reserves and 2C Contingent Resources 2C resources at a low upfront cost, together with Split by Region net risked prospective resources of 175 mmboe Falkland Islands North Sea • Significantly extends Premier’s production growth 28% 31% beyond current development projects and is an excellent fit with strongly rising cash flows Total ~725 • Fully funded from a combination of existing cash mmboe resources, facilities and cashflow from operations; commitment to fund dividend unchanged Pakistan & Mauritania Asia 9% 32% 23 August 2012 | Page 14

  16. Sea Lion – development plan • FPSO in 450m water depth; tanker offloading • Associated gas used as fuel or re-injected • 22 producers, 13 water injectors and a gas injector, drilled from 3 subsea centres • Insulated flowlines and risers • Hydraulic submersible pumps (HSPs) for artificial lift and flow assurance • Gross plateau rate of 80-85 kbopd – 120 kbopd produced fluids – 200 kbwipd – 140 kbwpd power fluid for HSPs – 60-90 mmscfd gas handling • Assumed capex to first oil of $3.2 billion (purchased FPSO) • Subsequent development of satellite fields 23 August 2012 | Page 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend