2010 Half Yearly Results Presentation 26 August 2010 - - PowerPoint PPT Presentation
2010 Half Yearly Results Presentation 26 August 2010 - - PowerPoint PPT Presentation
2010 Half Yearly Results Presentation 26 August 2010 Forward-looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events
26 August 2010 | Page 1
Forward-looking statements
This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject to known and unknown risks and uncertainties. A number of factors could cause actual results, performance or events to differ materially from those expressed or implied by these forward-looking statements.
26 August 2010 | Page 2
Agenda
Progress against strategy Simon Lockett Financial results Tony Durrant Exploration update Andrew Lodge Operations update Neil Hawkings Summary Simon Lockett
26 August 2010 | Page 3
Gajah Baru Wellhead platform jacket built and in place
Progress towards 75,000 boepd
Chim Sáo Development drilling under way Huntington Field development plan submitted
26 August 2010 | Page 4
Delivering Asian projects to meet growing demand
26 August 2010 | Page 5
Progress on the portfolio of development projects
Bream Evaluating tender responses Dua Concept selection completed Frøy Tender process under way Solan Project sanction by end 2010 Pelikan, Naga Concept selection completed North Sumatra Block A Progress towards PSC extension
26 August 2010 | Page 6
Progress towards 200mmboe of discoveries
Catcher Main and Catcher East 60-100mmboe (gross) Blåbaer 15-75mmbo (gross) Catcher Exploration >150 mmboe (gross) potential remaining
26 August 2010 | Page 7
Progress on acquisition / new ventures
West Orkney Basin, Solan & 15/26c South Darag
26 August 2010 | Page 8
Half yearly financial results
26 August 2010 | Page 9
Production and pricing
Working Interest Production (kboepd) Entitlement Interest Production (kboepd) Realised oil price ($/bbl) Realised gas price ($/mcf) 6 months to 30 Jun 2009 6 months to 30 Jun 2010 39.7 37.0 53.0 5.0 46.6 42.6 78.1 5.8 Average gas pricing ($/mcf) H1 2010 H1 2009 Singapore 13.8 8.9 Pakistan 3.3 3.7 Average Brent oil price was $77.3/bbl (H1 2009: $52.0/bbl) Highlights
30 5 10 20 25 Jan 05 15 Jul 05 Jan 06 Jul 06 Jan 07 Jul 07 Jan 08 Jul 08 Jan 09 Jul 09 Jan 10 Jul 10
Commodity price comparison $/mmbtu
Henry Hub West Natuna
Full-year 2010 guidance unchanged at around 44,000 boepd
26 August 2010 | Page 10
Income statement
Sales and other operating revenues Cost of sales Gross profit Excess of fair value over purchase consideration Exploration/New Business General and administration costs Operating profit Financial Items Profit before taxation Taxation Profit/(loss) after tax 6 months to 30 Jun 2009 6 months to 30 Jun 2010 $m 213 (116) 97 6 (25) (7) 71 (52) 19 (46) (27) $m 367 (189) 178
- (46)
(8) 124 (12) 112 (50) 62 Operating costs per barrel ($/bbl) H1 2010 FY 2009 UK $24.7 $23.2 Indonesia $7.1 $10.0 Pakistan $1.6 $1.9 Group $12.9 $12.2 Includes $20.5 million credit from mark to market revaluation of hedges Estimated UK tax allowances/losses of $1.05billion outstanding at 30 June 2010 Prior year comparatives are restated for acquisition fair value adjustments made in the 2009 year-end accounts
26 August 2010 | Page 11
Cash flow
Cash flow from operations Taxation Operating cash flow Capital expenditure (Acquisitions)/disposals Finance charges Pre-licence expenditure Net cash flow 6 months to 30 Jun 2010 $m
H1 2010 H1 2009 Development Exploration
Estimated Capex split ($m)
6 months to 30 Jun 2009 $m
69 42 111 142 70 212 Operating cash flow Capex Asia MEP
Estimated H1 2010 Regional split ($m)
118 14 80 49 29 144 North Sea 212 222
142 (29) 113 (111) (511) (18) (7) (534) 273 (51) 222 (212) 20 (27) (11) (8)
26 August 2010 | Page 12
Net debt and financial strength
6 months to June 2010 $m (316) (8) (12) (336) Movement in net debt Opening net debt Net cash out flow Purchase of shares Closing net debt*
Current outlook
- Cash $449 million, undrawn facilities $404 million
- Forecast 2010 full year spend of $430 million (development) and $170 million (exploration)
- At current prices net debt is expected to peak at around $700 million in mid-2011
* Excludes $65m of cash in escrow for abandonment obligations
At 30 Jun 2010 $m 449 (569) (216) (336) Balance sheet Cash and cash equivalents* Bank borrowings Convertible loan Net debt*
26 August 2010 | Page 13
Exploration update
26 August 2010 | Page 14
Year to date exploration highlights
Exploration and appraisal drilling
- Nine wells drilled, four successful
- Discoveries at Catcher, Catcher East
and Blåbaer
- Net estimated resource additions
>30mmbo New ventures
- New acreage awarded in West Orkney,
UK and South Darag, Egypt
- 11 applications in the UK 26th
Licensing Round
- Farmed into UK Block 15/26c (West
Rochelle)
200 100 50 2010 2011 150 2012 2013 2014 250
Target cumulative risked additions Actual cumulative risked additions
Global exploration: Forecast resource additions (mmboe)
2009
26 August 2010 | Page 15
Exploration – UK – Oates
Oates (P1620)
- Premier 50% equity and operator
- Well plugged and abandoned
- Pre-drill risk was trap integrity
- Post-drill analysis ongoing
– Focus on cause of amplitude response – Lessons learned will be captured and applied – Post drill analysis will be completed within 60 days of P&A
Oates Bowers
Forties Isopach Map Oates NW SE Amplitude Bloom on Far Stacks Oates
26 August 2010 | Page 16
Exploration – UK – Catcher
Catcher (P1430)
- Premier equity 35%
- 30° API oil discovery in high quality sands
- Catcher Main and Catcher East discoveries
- Catcher Main appraised by Catcher SW
- Gross reserve estimate: 60-85-100 mmbo
W Catcher Main Catcher East Varadero Prospect W E
2 Km
Depth Map on Top Reservoir Catcher Main Catcher North Prospect Catcher East
1 Km
Catcher
26 August 2010 | Page 17 26 August 2010 | Page 17
UK 28/9 (P1430)
- Premier equity 35%
- Overall block potential >300 mmbo recoverable
- Low risk, seismic amplitude support
- Three exploration wells are planned Q4 2010
Exploration – UK – 28/9 exploration potential
Catcher East Rapide Cougar Carnaby 65mmbo Bonneville Burgman 45 mmbo Catcher - Main Catcher North Varadero 40 mmbo
Eocene – Tay Amplitudes
Catcher - Main Discovery Carnaby Catcher North Varadero Burgman Catcher East
26 August 2010 | Page 18
Exploration outlook
Firm Wells: Rig Contracted Firm Wells: Rig TBC Contingent Wells Seismic Programme All well timings are subject to revision for
- perational reasons
Unrisked net potential new barrels over next 12 months of 300 mmboe
Anoa Deep Natuna Sea Block A Exploration well Appraisal Bhit/Badhra
Q2
K25, K18ST, K28 Kadanwari Pakistan
Middle East - Pakistan
Benteng Buton Exploration well West Rochelle P1298
2010
Bluebell P1466
Q1
CRD Appraisal
Q4 2011
Catcher P1430 UK Grosbeak Appraisal PL378 Gnatcatcher PL378 Gardrofa PL406 (8/3) Norway
North Sea
Biaawak Besar Belut Laut Gajah Laut Utara Tuna Indonesia Seismic 104/109-05 Seismic 07/03 Vietnam
Q3 Q3
Asia
Ocean General Ocean General Songa Delta Songa Delta
2010 full year expenditure $170million pre-tax
Geowave Voyager Viking II West Callisto West Callisto
Weatherford 812
Transocean Prospect
26 August 2010 | Page 19
Exploration – UK – West Rochelle
West Rochelle (P1298 & P1615)
- Premier equity 50% P1298 (15/26b), 25% P1615 (15/26c)
- Farmed into 15/26c to test western extension of the Rochelle
discovery along the Kopervik pinchout margin
- Potential gross reserves: 15-25-30 mmboe
- Well spudding – end August 2010
Rochelle P1298 (15/26b) P1615 (15/26c) West Rochelle well
West Rochelle West Rochelle S N
Plenus Marl Top Kopervik Base Kopervik Top Chalk Andrew Sst Lista BCU Base Zechstein
26 August 2010 | Page 20 26 August 2010 | Page 20
Exploration – Norway – Grosbeak, Gnatcatcher
Gnatcatcher/Grosbeak (PL378)
- Premier 20% equity (non-operated)
- Successful Grosbeak well completed in July 2009
– Close to nearby infrastructure – Oil in Middle Jurassic sandstones – Estimated reserves 35-80-190 mmboe
- Gnatcatcher resource estimate 31-40-60 mmboe
- Moderate to high risk for oil
- Q4 2010 Gnatcatcher exploration well and Q1 2011
Grosbeak appraisal
Gnatcatcher SW NE
26 August 2010 | Page 21
Appraisal – Vietnam – Block 07/03 – Cá Rồng Đỏ
Cá Rồng Đỏ
- Premier 30% equity, reserves estimate 10-60-80 mmbo
gross resource
- Appraisal well planned for Q1 2011
CRV NW CRD / CRD North East CRD Discovery SE
Anomalies associated with Hydrocarbons Anomalies associated with Hydrocarbons?
Gas above CRD
26 August 2010 | Page 22
Exploration – Vietnam – Block 07/03
2011 exploration well (Block 07/03)
- Premier 30% equity
- Two potential drilling candidates
identified on existing 3D, new 3D dataset available in Q1 2011
- Reserves estimate 10-45-70 mmbo
- Targeting multiple stacked Tertiary
reservoirs; moderate risk for oil
- One exploration well planned for
Q3 2011
26 August 2010 | Page 23
Exploration – Indonesia – Tuna – Belut Laut
Belut Laut (Tuna PSC)
- Premier 65% equity, reserves estimate 40-90-200 mmboe
- Targeting multiple stacked Tertiary reservoirs in fault dependent
closure – prospect is independent of Gajah Laut Utara
- Amplitude supported
- Moderate risk for oil
- Well planned for Q1 2011
PTD
Top Arang Depth C.I.=100 metres
2500m Belut Laut 2 Km
PRIMARY TARGET
SE
SECONDARY TARGET
Belut Laut
PTD 4300m MD (3870m TVD)
NW
26 August 2010 | Page 24
Exploration – Indonesia – Tuna – Gajah Laut Utara
Gajah Laut Utara (Tuna PSC)
- Premier 65% equity, reserves estimate 65-160-350 mmboe
- Targeting multiple stacked Tertiary reservoirs in major fault
dependent closure
- Amplitude supported at crest of trap
- Moderate risk for oil
- Well planned for Q4 2010
Top Arang Depth C.I.=100 metres
2500m 2 Km
PRIMARY TARGET
W E
SECONDARY TARGET PTD
Gajah Laut Utara
PTD 4250m MD (3550m TVD) Gajah Laut Utara
26 August 2010 | Page 25
Exploration – Indonesia – Natuna – Anoa Deep
Anoa Deep (WL-5 extension) (Natuna PSC)
- Premier 28% equity, reserves estimate 47-57-90 bcf
- Targeting Lama Formation reservoirs in faulted structural closures
directly underlying the West Lobe platform on Anoa field. Lama Formation produces oil and gas in nearby Kakap field
- Moderate risk for gas
- Well planned for Q2 2011
Top Lama Top H Top A PTD
Top Lama Depth C.I.=50 feet
5000m 1400 acre Lowest Closing Contour WL5
PRIMARY TARGET
SE
SECONDARY TARGET
Anoa Deep NW
5 Km
26 August 2010 | Page 26
Exploration – Indonesia – Natuna – Biawak Besar
Biawak Besar (Natuna PSC)
- Premier 28% equity, reserves estimate 66-79-92 bcf
- Targeting Arang formation reservoirs in a stratigraphic trap off
structure from the Iguana gas discovery. Seismic attribute analysis and 3D inversion supports presence of gas
- Play opening well – low risk for gas
- Well planned for Q3 2011
PTD
3D Seismic Inversion indicating gas pay
Top Arang Depth C.I.=100 metres
2000m Iguana Discovery Biawak Besar-1
Bison Iguana Biawak Besar
PRIMARY TARGET
500m
SE NW
26 August 2010 | Page 27 North Sea
- UK: Up to four wells planned in greater Catcher
area and a well on West Rochelle
- Norway: Gnatcatcher exploration and Grosbeak
appraisal wells. Gardrofa exploration well planned for Q3 2011 SE Asia
- Vietnam: Block 07/03 - CRD appraisal and an
additional exploration well. Commitment well on Block 104-109/5
- Indonesia: Two Tuna wells and near field
exploration wells in Natuna A. Exploration well on Buton Middle East-Pakistan
- Pakistan: Near field exploration wells
New Ventures
- Actively pursuing new opportunities for 2012-2014
drilling
Exploration – Outlook
18-22 exploration and appraisal wells planned over next 12 months
Firm wells Contingent wells
26 August 2010 | Page 28
Operations update
26 August 2010 | Page 29
Operations highlights
- 2010 production on track
- Gajah Baru 64% complete and
WHP jacket installed
- Chim Sáo 73% complete and
WHP installed
- Good progress on Huntington
- Catcher added to development
portfolio
26 August 2010 | Page 30
Production update
50,000
Production (working interest) (boepd)
30,000 25,000 10,000 5,000 2006 2007 2008 15,000 20,000 35,000
North Sea / W. Africa Middle East-Pakistan Asia
2009 40,000 45,000 H1 2010
- Full year production forecast
around 44,000 boepd
- Singapore gas demand
strong
- Pakistan production strong
and negligible impact from floods
- Burghley field will tie-in to
Balmoral in September reducing operating costs
26 August 2010 | Page 31
Natuna Block A gas sales forecast
450
Block A gas sales forecast
BBtud
400 350
Exploration potential Iguana Naga Gajah Baru Bison Gajah Puteri Pelikan Anoa Export capacity GSA2/3/4 GSA1
300 50 100 200 250
2006
150
2008 2010 2012 2014 2016 2018 2020 2007 2009 2011 2013 2015 2017 2019 2021
Double production over 3 years
Exploration to increase production Extra available export capacity
Block A development schematic
26 August 2010 | Page 32
- Wellhead platform installation is ongoing
- West Callisto rig will start drilling in September
- Central Processing Platform construction well under way
- Overall project 64% complete
Gajah Baru – on schedule for October 2011
Pics of WHP and CPP jackets and topsideses requested by 23rd Aug from Bryce Walker: “No problem Mary. FYI the GB wellhead jacket is due to load out on 8 August so we will definitely have photos of that but the deck is not due to load out until 28 August. Regarding installation, based upon the Castoro Otto finishing up on or ahead of schedule on the Topaz work the jacket installation could be done in late August. Again if that happens we’ll have photos and a
- movie. “
26 August 2010 | Page 33
- WHP jacket and topsides installed
- ENSCO 107 currently drilling
development wells
- Gas export pipeline laid and tie-in
under way
- FPSO mooring and mid-water
arches installed
- FPSO conversion on track
- Premier equity 53.125%
Chim Sáo – on schedule for first oil in July 2011
26 August 2010 | Page 34
Huntington – on schedule for 2012
- Letter of Intent signed with Sevan for provision of Voyageur FPSO
- Field development plan submitted to DECC
- Target date for project sanction 1 October 2010
- Long-lead items being purchased
- Rig bids have been received
- Earliest possible first oil is late 2011
26 August 2010 | Page 35
North Sumatra Block A (Indonesia)
- PSC extension approval process remains ongoing
- Optimisation of development plan has continued
- First gas 2013
Asia developments
Dua
- Internal concept selection complete
Cá Rồng Đỏ
- 2009 discovery
- Development studies will commence after
upcoming appraisal well
26 August 2010 | Page 36
Norway developments
Frøy
- Tenders received for production facilities
- Leading option is a Sevan FPSO
bridge-linked to a wellhead platform
- Impact of nearby exploration wells being assessed
Bream
- Evaluating responses to ITT for production unit
Grosbeak and Blåbær
- 2009/2010 discoveries
- Development studies will commence after
upcoming appraisal and exploration wells
26 August 2010 | Page 37
UK developments
Catcher
- Preliminary studies will commence later this
year leading to concept selection in 2011
- Multiple stand-alone facilities options exist
–Fixed platform –FPSO Solan
- Option to participate in a 45 mmbbls fast track
(2012) development at 40% equity
- Project sanction decision scheduled for year-end
Catcher
Other possible UK developments
- Scott satellites
- Caledonia
- Ptarmigan
- Moth
26 August 2010 | Page 38
A path to 100,000 boepd
120
Production (kboepd net)
40 20 60 80 100
Development capex ($m)
2010 2011 2014 2012 2013 2015
Future Asia developments Future Norway developments Future UK developments Huntington Chim Sáo, Gajah Baru On production
600 200 100 300 400 500 2010 2011 2014 2012 2013 2015
Future Asia developments Future Norway developments Future UK developments Huntington Chim Sáo, Gajah Baru On production
26 August 2010 | Page 39
Summary
26 August 2010 | Page 40
Summary: delivering against strategy
Progress
- Chim Sáo and Gajah Baru on
schedule for 2011, Huntington for 2012.
- Solan, Frøy, Bream, Dua
progressing towards development sanction in 2011.
- Blåbaer and Catcher successes in
- 2010. Active second half drilling
programme.
- Solan option. Value to be found in
financing smaller companies through development and will be pursued.
- Committed investment programme
fully funded; acquisition capacity. Strategy
- Attain 75 kboepd from
existing projects
- Commercialise contingent
resource base
- Add 200 mmboe of
2P reserves from the exploration portfolio
- Make value-adding
acquisitions in three core areas
- Maintain a conservative
balance sheet Target
- Build three quality businesses which deliver 100 kboepd
from 400 mmbbls of reserves
Production by region H1 2010 (kboepd)
15.2 20.1 11.3 46.6
North Sea / West Africa Asia Middle East-Pakistan
Cashflow by region H1 2010 ($million)
49 29 144 222
26 August 2010 | Page 41
Appendix
26 August 2010 | Page 42
HSE performance – a top priority
- Recordable Incident Rate trend is
downwards
- Performance is top quartile in the industry
- Challenge for staff is to sustain this
performance
- TRIF = Lost Time Injury (LTI) + Reduced Work Day Case (RWDC) +
Medical Treatment Case (MTC) frequency per million man-hours
- There was 1 LTI and 0 RWDC incidents in 2008
- There were 2 LTI and 0 RWDC incidents in 2009
- Association of Oil and Gas Producers
Benchmarking Survey, 2009
6
Total recordable injury frequency (TRIF)
5 4 3 2 1 2003 2004 2005 2006 2007 2008 2009
Premier TRIF
12
Total recordable injury rate
Per million hours worked by company with contractors 11 9 10 8 7 6 5 4 3 2 1
Top Quartile
26 August 2010 | Page 43
Strike Line
P1181 Lacewing Prospect
- Equity: Premier 57%
- Reservoir: Triassic
- Reserves range: 21-71-135 mmboe
- Net well cost: $35 million
- Plan to drill Q3/Q4 2011 subject to further peer review
Exploration – UK – Lacewing
Lacewing 23/22b-4 Lacewing
26 August 2010 | Page 44
P1466 Bluebell Prospect (15/24c,15/25f)
- Equity: Premier 100%
- Reservoir: Palaeocene Forties reservoir
- Reserves range: 9 -19 - 31 mmboe
- Net well cost: $12.5 million
- Well spud date: has to be drilled by March 2011
- Valuable tieback opportunity for Brenda/Balmoral – could help
unlock Ptarmigan discovery
Exploration – UK – P1466 Bluebell
Top Forties Depth SS, CI=5 m Top Forties Lambda Rho Extraction Top Forties Lambda Rho Extraction Near Offset Lamda Rho, HC Indicator Bluebell Bluebell
Bluebell Well Location Bluebell Site Survey
Bluebell
26 August 2010 | Page 45 26 August 2010 | Page 45
Exploration – UK – West Orkney Basin
P1577: West Orkney Basin
- Premier 100%
- 1,700 km2 acreage covering West Orkney Basin depo-centres
- Shallow water, low cost environment
- Frontier Rift Basin exploration opportunity
- Target is Pre-rift Devonian system preserved in Mesozoic rifts
- Petroleum system proven - exhumed oil accumulations on Orkney
- Key uncertainty is presence and preservation of traps
- Material unrisked play potential, presently high risk
- Work programme commensurate with risk reduction
- 6 year concession with a drill or drop option
- Purchase 6,000 km of existing 2D data
- Reprocess selected lines
- Go Forward plans
- Firm: Purchase, reprocess and interpret data 2010/2011
- Optional: Acquire 3D seismic data 2012 and Drill 2013
- PhD studentship starting September 2010
A’ A Orkney Islands; Inverted Devonian basins, with Breached oilfields Metamorphic highs; exposed at seabed Half grabens with possible Devonian source and reservoirs and proven Zechstein seal Terraces with probable Devonian source and reservoirs and probable Zechstein seal
West Orkney Basin Structure Top Devonian Orkney Isles
Half grabens with Pre-rift section: Potenential for Devonian source and reservoirs plus Zechstein seal
26 August 2010 | Page 46 26 August 2010 | Page 46
Exploration – Norway – Bream, Gardrofa
Bream (PL406)
- Brent age oil discovered 1971, close to Yme Field
- In 2009,17/12-4 and its sidetracks wells appraised
this discovery, testing 2,516 boepd
- Operated by BG, Premier equity 20%
- Estimated reserves 39-50-63 mmboe
- Plan of development under review
Gardrofa (PL407)
- Premier’s first operated licence in Norway
- Premier equity 40%
- Untested trap flanking a Salt dome feature
- Estimated reserves 15-70-115 mmboe
- Moderate risk for oil
- Well planned for third quarter 2011
9/1-1 Gardrofa Prospect Well Location
Success at Gardrofa will lead to a new core area for Premier in Norway
26 August 2010 | Page 47 26 August 2010 | Page 47
Blåbaer
Blåbaer (PL374)
- Premier 15% equity, operated by BG
- Well 34/5-1 proved 65m of gross oil bearing Cook
Formation
- The 34/5-1 Sidetrack, drilled into a separate fault
block was dry
- The gross resource range remains within the
15mmbo to 75mmbo predicted pre-drill
- A decision on the future delineation of the
discovery is subject to ongoing evaluation
Exploration – Norway – Blåbaer
C.I. 10m
Sidetrack
2 Km 2 Km
26 August 2010 | Page 48
Exploration – Vietnam – Block 104-109/05
2011 Exploration Well (Block 104-109/05)
- Premier 50% equity
- 445km² of 3D acquired Q3 2010
- Potential drilling candidates to be matured on
new 3D
- Reserves estimates to be determined
- Targeting multiple stacked Tertiary reservoirs
- High risk for oil
- 1 Exploration well planned for Q3 2011
Area of acquired 3D coverage
W NE Leads E
Faulted Structures to be imaged by 3D
26 August 2010 | Page 49
Exploration – Indonesia – Buton
meters
‘B’
Buton PSC
- Premier equity 30%
- Japex operator
- Lead B reserve estimates 35-100-300 mmboe
- High risk for oil, in fold belt theme
- Benteng prospect first to be drilled
- Drilling planned Q1 2011
Benteng NW SE
0 5000
26 August 2010 | Page 50 26 August 2010 | Page 50
K28
2010/2011 drilling in Pakistan
SW NE E-Sand
K25 Compartment:
- Premier 15.79% equity
- Reserves estimate
1-2-4 mmboe
- Targeting E-sand reservoir in
step-out compartment north of K-19 producing compartment
- Lateral seal risk on the
northern plunge
- Well spudded on 2nd August
2010
K18 K18ST
K18ST Compartment:
- Premier 15.79% equity
- Reserves estimate
0.5-2-5 mmboe
- Targeting E-sand reservoir in
adjacent step-out compartment east of K-18 depleted compartment
- Moderate fault seal risk
present
- Well planned in Q4 2010
K28 Compartment:
- Premier 15.79% equity
- Reserves estimate
9 mmboe
- Targeting E-sand
reservoir in step-out compartment south of K10 block
- Moderate fault seal risk
present
- Well planned in 2Q 2011
Badhra Area-B Appraisal well:
- Premier 6% equity; Reserves
estimate 22 mmboe
- Targeting Mughalkot reservoir
channel sands
- Moderate to high reservoir
presence and quality risk
- Reprocessing is ongoing to
improve image to mitigate reservoir risk
- Well is contingent upon
reprocessing results
- Well planned in Q2 2011
K25
SW NE E-Sand
K18ST
SW NE E-Sand
Badhra Area-A Badhra Area-B
26 August 2010 | Page 51 www.premier-oil.com