2000 2008 and 2012 bond programs
play

2000, 2008 and 2012 Bond Programs San Francisco Clean and Safe Parks - PowerPoint PPT Presentation

2000, 2008 and 2012 Bond Programs San Francisco Clean and Safe Parks GO BONDS 2008 BOND Program Updates Mission Dolores: North side Open to the Public in June 2015. South side in construction and on schedule to open in early 2016. Raymond


  1. 2000, 2008 and 2012 Bond Programs San Francisco Clean and Safe Parks GO BONDS

  2. 2008 BOND Program Updates Mission Dolores: North side Open to the Public in June 2015. South side in construction and on schedule to open in early 2016. Raymond Kimbell Playground: Open to the Public June 2015. Beach Chalet Playfields Replacement: Construction is underway and expected to be Open to the Public in early 2016. Great Highway Restrooms: Construction complete and opened to the public in May 2015 San Francisco Clean and Safe Parks GO BONDS 2

  3. 2012 BOND Schedule Angelo J. Rossi Pool Balboa Park Pool Bldg Phase Description Planning Garfield Square – Pool Bldg Design George Christopher Playground Bid/Award Gilman Playground Construction Glen Canyon Rec Center Joe DiMaggio Playground Margaret S. Hayward Playground Moscone Rec Center Mountain Lake Playground Potrero Hill Rec Center South Park West Sunset Playground Willie “Woo Woo” Wong Playground January 2014 July 2014 January 2015 July 2015 January 2016 July 2016 January 2017 July 2017 January 2018 July 2018 January 2019 San Francisco Clean and Safe Parks GO BONDS 3

  4. 2012 2 nd Sale Schedule $80,000,000 $60,000,000 Balboa Pool $53.2 Million = 1st Sale West Sunset $40,000,000 2 nd Bond Sale Glen Canyon South Park Oct 2015 Mountain Lake Park $20,000,000 Gilman Playground Joe DiMaggio $0 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 FY 13/14 FY 14/15 FY 15/16 2012 Bond Spent/Encumbered Projects enter into construction contract San Francisco Clean and Safe Parks GO BONDS 4

  5. Challenges and Opportunities Phase 1 Projects : Construction environment is competitive, projects designed with Add Alternates to provide flexibility at bid and award. All concept plans approved at the Rec and Park Commission. Failing Playgrounds: Planning underway, construction strategy expected this fall. Leveraging Funds: Impact Fees and Grants to augment bond projects Staffing Resources: Hiring three PM positions, short-staffed in both Financial Unit and Planning Unit Asset Management: COMET and Deferred Maintenance Planning in 2016 San Francisco Clean and Safe Parks GO BONDS 5

  6. Port Update: 2008 Clean and Safe Parks Bond Complete: Brannan Street Wharf (above), Pier 43 Bay Trail Link, Bayfront Park, Heron’s Head Park, Blue-Greenway Design Guidelines, Bayfront Park Shoreline, Blue-Greenway Signage and Site Furnishings, Bayview Gateway Design/Environmental Review: Crane Cove Park (Construction January 2016) San Francisco Clean and Safe Parks GO BONDS 6

  7. Port Update: 2008 Bonds Schedule Initiation/ Planning Pln Pln 2008 2009 2010 2011 2012 2013 2014 2015 Design/ Bid & Award Des Des Construction/ Close Out Con Con J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Start Date End Date Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 PIER 43 BAY TRAIL LINK July 2008 November 2012 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesCon Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con BRANNAN STREET WHARF July 2008 July 2013 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesCon Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con BLUE GREENWAY PLANNING & DESIGN GUIDELI May 2008 September 2013 Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con BAYFRONT PARK January 2008 February 2012 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesCon Con Con Con Con Con HERON'S HEAD PARK January 2009 September 2012 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesCon Con Con Con Con Con Con Con Con Con TULARE PARK April 2011 January 1900 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPln BLUE GREENWAY PUBLIC ART July 2011 December 2016 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDes CRANE COVE PARK September 2011 May 2017 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDes BLUE GREENWAY SIGNAGE AND SITE FURNISHIN April 2011 March 2015 PlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesCon Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con Con BAYVIEW GATEWAY September 2011 July 2015 PlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesCon Con Con Con Con Con San Francisco Clean and Safe Parks GO BONDS 7

  8. Port Update: 2012 Clean and Safe Parks Bond Planning: Islais Creek Improvements, Agua Vista Park Des i gn/Environmental Review: Crane Cove Park Complete: Cruise Terminal Plaza (above) San Francisco Clean and Safe Parks GO BONDS 8

  9. Port Update: 2012 Bonds Schedule Initiation/ Planning Pln Pln 2011 2012 2013 2014 2015 2016 2017 2018 Design/ Bid & Award Des Des Construction/ Close Out Con Con J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Start Date End Date Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 AGUA VISTA PARK January 2016 September 2017 PlnPlnPlnPlnDesDesDesDesDesDesConConConConConConConConConConCon CRANE COVE PARK September 2011 November 2017 PlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnPlnDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesDesConConConConConConConConConConConConConConConConConConConConConCon ISLAIS CREEK IMPROVEMENTS November 2015 September 2017 PlnPlnDesDesDesDesDesDesDesDesDesDesConConConConConConConConConConCon San Francisco Clean and Safe Parks GO BONDS 9

  10. Comments and Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.