1 San Leandro Bay Bridge PM 18.5 2 Perform needed maintenance - - PowerPoint PPT Presentation

1 san leandro bay bridge
SMART_READER_LITE
LIVE PREVIEW

1 San Leandro Bay Bridge PM 18.5 2 Perform needed maintenance - - PowerPoint PPT Presentation

1 San Leandro Bay Bridge PM 18.5 2 Perform needed maintenance Keep the bridges safe for users Mechanical components and Electrical equipments need to be repaired and upgraded 3 SAN LEANDRO BAY BRIDGE Pressure wash, spot blast


slide-1
SLIDE 1

1

slide-2
SLIDE 2

2

San Leandro Bay Bridge

PM 18.5

slide-3
SLIDE 3

Perform needed maintenance Keep the bridges safe for users Mechanical components and Electrical

equipments need to be repaired and upgraded

3

slide-4
SLIDE 4

SAN LEANDRO BAY BRIDGE

 Pressure wash, spot blast clean, and paint all of the steel

members in the movable truss span

 Replace 4 traffic gates and one pedestrian gates  Install I-Beam  Refurbish and rebuild electrical end lock system  Catwalk Modifications

4

slide-5
SLIDE 5

SAN LEANDRO BAY BIKE BRIDGE

 Provide accessible performance platform for future

repair and maintenance

 Install access gates, ladder, and hand winch  Service the hydraulic system

5

slide-6
SLIDE 6

 End Environmental Phase

  • Sept. 2014

 Complete Contract Documents Mar. 2015  Advertise

  • Jun. 2015

 Start Construction

  • Oct. 2015

 End Construction

May 2016

6

slide-7
SLIDE 7

Inform yacht club about the project Meet and coordinate with Coast Guard,

City staff, and other Caltrans functional units for contract plan review

7

slide-8
SLIDE 8

Night time bridge closures to motorists No bridge opening for mariners during

Jan 2 to May 15

Night work to minimize impacts to traffic

and businesses

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

Include project information and

construction schedule on City, County, and Caltrans websites

After the contract is awarded and

contractor provides the work schedule:

  • Notify the residents by mail of work schedule
  • Install Electronic Message Signs before the start
  • f construction work
  • Continue coordination with Coast Guard, City,

County and others during construction

12