1
1 Namami Gange - Component wise Allocation Namami Gange Integrated - - PowerPoint PPT Presentation
1 Namami Gange - Component wise Allocation Namami Gange Integrated - - PowerPoint PPT Presentation
1 Namami Gange - Component wise Allocation Namami Gange Integrated Ganga Conservation Mission approved by Cabinet on 13/05/2015 With an outlay of 20,000 Cr upto Dec 2020 Component A Ongoing projects having remaining central
Namami Gange - Component wise Allocation
2
“Namami Gange – Integrated Ganga Conservation Mission” approved by Cabinet on 13/05/2015 With an outlay of 20,000 Cr upto Dec 2020
Component A Ongoing projects having remaining central liabilities of Rs.7,272 crore This includes 33 sewerage Projects (630 MLD STP) and 24 Ghats &Crematoria projects. Component B New initiatives at an estimated cost of Rs.12,728 crore with 100% central assistance This includes 102 sewerage Projects (3256 MLD STP) and 37 Ghats &Crematoria projects.
Salient Features
3
NAMAMI GANGE
100% Centrally funded programme O&M cost for 15 years included for new projects Comprehen sive integrated programme Non- lapsable fund 5 year dedicated Budget allocation Hybrid Annuity based PPP model adopted
Namami Gange Projects Overview
4
Sl No Projects Undertaken
- No. of Projects
Sanction Cost (Rs in Cr) Pollution Abatement Projects 1 Sewage Infrastructure (94 on Ganga, 8 on tributaries) 102 16984 2 Bioremediation 8 26.94 3 Modular STPs –Decentralised Treatment 20 410 4 Upcoming Projects on Tributaries (7 states, 31 tributaries, 68 towns) 68 Under estimation Sub total 198 17420.94 5 Rural Sanitation (4465 villages along Ganga) 1 1018 Total
199 18438.94
Namami Gange Projects Overview
5
Sl No Projects Undertaken
- No. of Projects
Sanction Cost (Rs in Cr)
River Front, Ghats & Crematoria Projects
1 Ghats & Crematoria (Old) 24 204.39 2 Ghats & Crematoria (New) 37 721.94 3 Ghats Cleaning 1 15.00 4 River Surface Cleaning 1 55.24 5 River Front Development 2 270.55 Sub-total 65 1267.12
Other Projects
6 Institutional Development 6 340.41 7 Project Implementation Support / Research & Study Projects 2 9.96 8 Biodiversity 4 31.91 9 Afforestation 11 113.28 10 Composite Ecological Task Force 1 167 Sub-total
24 662.56
Grand Total
288 20368.62
Status of Sewerage Projects
6 S. No. State Status as on May 2014 Status as on May 2018 Projec ts Comple ted Work- in- Progre ss Under Tendering Process Projects STP Capacity (MLD) Complet ed Work-in- progress Under Tenderin g Tender to be floated STP Capacit y (MLD) Tender Receive d & Finaliza tion in process Under Tendering Tender to be floated
Ganga Main stem
1 Uttarakhand
10 24 1 9
- 31
156 13 18
2 Uttar Pradesh
12 334
- 7
3 2 27 743.5 8 8 1 10
3 Bihar
4 55
- 4
19 529
- 10
3 6
4 Jharkhand
1 12
- 1
2 16
- 2
- 5
West Bengal
4 60
- 3
1 15 483.5 2 4
- 4
5
Sub Total 31 485 1 (18) 23 5 2 94 1928 23 42 4 14 11
Tributaries
6 Haryana
2 145
- 2
2 145 1 1
- 7
Delhi
- 2
1044
- 1
- 1
- 8
U.P
- 3
130.5
- 1
2
- 9
Bihar
- 1
9
- 1
- Sub Total
2 145 2 8 1328.5 1 3 3 1
- Total
33 630 1 (18) 25 5 2
102 3256 24 45 7 15
11
7
Initiatives taken up by NMCG
- “One City One Operator” - STPs in 7 towns (Kanpur, Allahabad, Mathura, Patna,
Kolkata, Howrah-Bally, Bhagalpur) are being integrated & tendered with Hybrid Annuity based projects – 4 already tendered during this period (Kanpur, Allahabad, Mathura & Kolkata)
- Focus on 10 major towns contributing almost 64% of total sewage discharge.
- Total STP capacity- 1109 MLD is being created at a cost of 9883 Cr in these
towns
- Performance evaluation of existing STPs completed in Uttarakhand, Uttar Pradesh and
Bihar.
- Project Engineers for Haridwar and Varanasi projects appointed by NMCG
- Annual inspection of GPIs through technical institutions in a time bound manner.
- Close monitoring of milestones. Field visits increased.
- Regular Follow-up with State Agencies
- Upcoming projects on tributaries- 68 towns in 7 states on 31 tributaries
150 457 234 310 45 320 60 615 160 41 63 456 270 102 589 82 15 72 310 35 200 30 26 150 65 45 40 100 200 300 400 500 600 700 Haridwar Kanpur Allahabad Varanasi Farrukhabad Patna Bhagalpur Kolkata Howrah Bally Sewage Generation (2035) Existing Treatment Capacity (Mld) Ongoing Projects Under Tendering Approved Projects
Focus on Large Cities of Ganga Main Stem
All figures are in Mld
10 towns with a total sewage generation of 1897 Mld contribute almost 64% of total sewage (2953 Mld) discharge from the 97 towns to river Ganga
8
- Awarded projects:
Status of Hybrid Annuity Sewerage Projects
9
Project Signing of Agreement Start of work 82 MLD STP at Haridwar 11/10/2017 01/02/2018 50 MLD STP at Varanasi 11/10/2017 01/02/2018
Progress of Works Contract Signing
Status of other Hybrid Annuity Sewerage Projects
10
S. No. Name of the Package Capacity in MLD Present Status Award Date (Tentative) (i) Mathura 30 Bids Received (14-03- 2018); Evaluated 14/05/2018 (ii) Allahabad - Jhusi, Naini, Phaphamau 72 NIT published (16/03/2018) 19/06/2018 (iii) Unnao, Shuklaganj and Kanpur 49 NIT published (08/03/2018) 02/06/2018 (iv) Farrukhabad 35 NIT published (12/04/2018) 02/07/2018 (v) Mirzapur and Gazipur 38 NIT published (14/04/2018) 02/07/2018 (vi) Digha & Kankarbagh in Patna* 150 Likely NIT date-14/05/2018 11/07/2018 (vii) Bhagalpur* 65 Likely NIT date-30/05/2018 16/07/2018 (viii) Kolkata (Tolly’s Nalla) 26 NIT published (27/04/2018) 12/07/2018 (ix) Howrah &Bally; Kamarhati & Baranagar * 165 Likely NIT date-14/05/2018
12/07/2018 *- Projects under World Bank funding
12
Sewerage Projects in Haridwar
Sewage Generation- 74 MLD Existing Capacity – 63 MLD Work in Progress – 82 MLD STP, I&D works, Arihant Vihar network All 20 drains being tapped
Uttarakhand– Completed Projects
13
- S. No.
Project 1 STP at Devprayag Cost - 3.66 Cr STP capacity – 1.4 MLD 2 Sewerage Scheme in Devprayag Cost – 4.50 Cr 3 I&D at Joshimath Cost – 9.61 Cr 4 I&D at Gopeshwar Cost – 10.18 Cr 5 Sewerage Scheme at Triveni Ghat, Rishikesh Cost – 7.23 Cr Triveni Ghat
Uttarakhand – Completed Projects
14
- S. No.
Project 6 Sewerage system & STP for Tapovan area, Rishikesh Cost – 24.12 Cr STP capacity – 3.5 MLD 7 Sewerage Scheme at Ahbab Nagar Jwalapur Zone E-2 at Haridwar Cost – 24.84 Cr 8 STP at Sarai, Haridwar Cost – 24.91 Cr STP capacity – 18 MLD Tapovan STP
15
- S. No.
Project 9 Sewerage Scheme in Gangotri Cost – 0.45 Cr 10 Sewerage System and STP for Gangotri Dham Cost – 10.48 Cr STP capacity – 1 MLD 11 I&D at Devprayag Cost – 7.27 Cr 12 I&D at Badrinath Cost – 7.26 Cr 13 Sewerage Scheme in Uttarkashi Cost – 4.84 Cr Total (13 projects) Cost – 139.35 Cr STP capacity – 23.9 MLD
Uttarakhand– Completed Projects
Gangotri Gangotri
16
S.No. Project 1 STP at Jagjeetpur & Sarai
Cost – 273.37 Cr STP capacity – 82 MLD Physical progress – 13.05 % Likely date of completion – Mar’19
2
Tertiary treatment of existing 27 MLD STP at Jagjeetpur & u/g of existing 18 MLD STP at Sarai Cost – 32.65 Cr Physical progress – 10 % Likely date of completion – Nov’18
3
I&D at Sarai & Jagjeetpur
Cost – 116.28 Cr Physical progress – 48.86 % Likely date of completion – Dec’18
4
Upgradation of STP at Tapovan Cost – 2.19 Cr Physical progress – 98 % Likely date of completion – May’18
Uttarakhand – Work in Progress
Kassawan SPS (I&D Sarai) STP Sarai
17
S.No. Project 5 STP at Kirtinagar
Cost – 4.23 Cr STP capacity – 0.06 MLD Physical progress – 70 % Likely date of completion – May’18
6 I&D and STP at Rudraprayag
Cost – 13.14 Cr STP capacity – 0.525 MLD Physical progress – 5 % Likely date of completion – Dec’18
7
I&D and STP at Karnaprayag
Cost – 12.09 Cr STP capacity – 0.35 MLD Physical progress – 12 % Likely date of completion – Dec’18
Uttarakhand – Work in Progress
Kirtinagar STP
18
- S. No.
Project 8 I&D with STP at Badrinath
Cost – 18.23 Cr STP capacity – 1.01 MLD Physical progress – 3 % Likely date of completion – Dec’18
9 I&D and STP at Nandaprayag
Cost – 6.46 Cr STP capacity – 0.15 MLD Physical progress – 14 % Likely date of completion – Dec’18
10 I&D and STP, at Chamoli
Cost – 61.83 Cr STP capacity – 4.38 MLD Physical progress – 11 % Likely date of completion – Dec’18
Uttarakhand – Work in Progress
Nandprayag Badrinath
19
- S. No.
Project 11 Upgradation of STP at Srinagar Cost – 15.40 Cr Physical progress – 5 % Likely date of completion – Nov’18 12 I&D and STP at Srinagar Cost – 22.51 Cr STP capacity – 1 MLD Physical progress – 8 % Likely date of completion – Nov’18 13 I&D with STP at Joshimath Cost – 48.42 Cr STP capacity – 3.78 MLD Physical progress – 10 % Likely date of completion – Nov’18 14 Upgradation of STP (Gyansu) Cost – 10.03 Cr Physical progress – 20 % Likely date of completion – Jun’18
Uttarakhand – Work in Progress
Srinagar STP Excavation Upgradation at Uttarkashi STP
20
- S. No.
Project 15 Upgradation of STP at Swargashram,(Rishikesh) Cost – 5.20 Cr Physical progress – 15 % Likely date of completion – Jun’18 16 Rising main and STP at Muni Ki Reti Cost – 80.45 Cr STP capacity – 12.5 MLD Physical progress – 12 % Likely date of completion – Mar’19 17 I&D at Arihant Vihar and New Vishnu Garden, Haridwar Cost – 4.68 Cr Physical progress – 11 % Likely date of completion – Oct’18 18 I&D with STP at Rishikesh Cost – 158 Cr STP capacity – 26 MLD Physical progress – 8 % Likely date of completion – Dec’19 Total (18 projects) Cost – 885.16 Cr STP capacity – 131.76 MLD
Uttarakhand – Work in Progress
Muni ki Reti SPS
Cost: Rs. 6538.62 Cr
Sewage Generation- 234 MLD Existing Capacity – 272MLD Under Tendering- 72 MLD All 20 drains being tapped
Uttar Pradesh- Completed projects
23
- S. No. Project
1 Sewerage & Non sewerage Schemes at District 'B' & 'E' of Allahabad Cost – 199.26 Cr STP capacity – 85 MLD 2 Sewerage work in District ‘E’ Cost – 142 Cr 3 Sewerage & Non sewerage Schemes at District 'A' of Alahabad Cost – 106.08 Cr STP capacity – 20 MLD 4 STP at Salori Cost – 42.4 Cr STP capacity – 14 MLD
Kodra STP- 25 MLD Salori STP- 14 MLD
24
- S. No. Project
5 Sewerage System & STP works (Phase II) at Kannauj (Kali)
Cost – 43.66 Cr STP capacity – 1 MLD
6 Sewerage Scheme at Narora, Bulandshahar
Cost – 34.87 Cr STP capacity – 4 MLD
Uttar Pradesh- Completed projects
Narora STP- 4MLD Kannauj STP- 13MLD
25
- S. No. Project
7 Sewerage System & STP works at Garhmuhteshwar Cost – 46.51 Cr STP capacity – 9 MLD
8 Sewerage works in Anupshahar, Bulandshahar
Cost – 75.79 Cr STP capacity – 2.5 MLD
Total (8 projects) Cost – 690.57 Cr
STP capacity – 135.5 MLD
Uttar Pradesh- Completed projects
26
S.No. Project 1 Sewerage System in District 'C' & Allahapur, Allahabad Cost – 146.87 Cr Physical progress –84% Likely date of completion – May’18 2 Sewerage works in Sewerage District 'A' of Allahabad Cost – 288.94 Cr Physical progress – 65 % Likely date of completion – Oct’18 3 Sewerage System with Sewer network in District 'B' of Allahabad Cost – 265.86 Cr Physical progress – 63 % Likely date of completion – Dec’18
Uttar Pradesh- Work in progress projects
Vivekanand Park SPS Chilla SPS Sewer Works in Dist-B
Sewage Generation- 310 MLD Existing Capacity – 102 MLD Work in Progress – 310 MLD STP All 37 drains being tapped
28
S.No. Project 4 Sewer network in District E of Allahabad - Part 2 Cost – 52.78 Cr Physical progress –88% Likely date of completion – May’18 5 JICA assisted Ganga Action Plan Phase II project at Varanasi Cost – 641.19 Cr STP capacity – 140 MLD Physical progress –82% Likely date of completion – Jul’18
Uttar Pradesh- Work in progress projects
Trenchless Sewerline Dinapur STP
- District I network
- Sisamau nala I&D works
- District IV Sewer network
Sisamau Nala
- District III Sewer network
Sewage Generation- 457 MLD Existing Capacity – 457MLD Work in Progress – 15 MLD Under Tendering- 30 MLD All 21 drains being tapped
30
S.No. Project 6 Sewerage System & STP works (Phase I) at Moradabad Cost – 279.91 Cr STP capacity – 58 MLD Physical progress – 87% Likely date of completion – Jun’18 7 I&D of Sisamau Nala of Kanpur city Cost – 63.8 Cr Physical progress – 20 % Likely date of completion – Oct’18 8 Sewerage works in District I of Kanpur Cost – 370.4 Cr Physical progress – 10 % Likely date of completion – Jul’20
Uttar Pradesh- Work in progress projects
Moradabad STP- 58MLD Guptar Ghat SPS
31
S.No. Project 9 STP for Assi-BHU District at Ramana Cost – 161.31 Cr STP capacity – 50 MLD Likely date of completion – Dec’19 TOTAL (9 projects) Cost – 2271.06 Cr STP capacity – 248 MLD
Uttar Pradesh- Work in progress projects
32
Uttar Pradesh – Tender received and under finalization
Sl No. Name of the project Date of Sanction Sanctioned Cost ( in Cr.) STP Capacity (MLD) Sewer Network (Km) Likely Date
- f Award
1 Interception, Diversion & Treatment works in Chunar, Dist. Mirzapur 02.08.2017 27.98 2 1.16 May-18 2 Rehabilitation of Sewage Infrastructure & Augmentation/ up gradation of Existing STP at Vrindavan 24.03.2017 33.82 5
- May-18
3 Mathura Sewerage Scheme (HAM) 17.10.2017 204.97 67.5
- May-18
Total 266.8 74.5 1.16
33
Uttar Pradesh – Under Tendering
Sl No. Name of Project Sanctioned Cost ( in Cr.)
STP Capacity (MLD)
Sewer Network (Km) Likely Date
- f Award
1 Sewerage Scheme & STP at Bithoor, Kanpur Nagar 13.4 2
- June-18
2 Interception, Diversion of drains & Sewage Treatment works at Ramnagar 71.26 10 0.44 July-18 3 Interception, Diversion of drains & Sewage Treatment works at Unnao (HAM) 102.2 13 3.3 July-18 4 Interception, Diversion of drains & Sewage Treatment works at Shuklaganj, Dist. Unnao (HAM) 65.18 6 0.15 July-18 5 STP at Pankha, Kanpur and integration with existing STPs 967.23 30 16.5 July-18 6 Interception, Diversion & Treatment works for Naini (District G), Phaphamau (District F) & Jhusi area District in Allahabad (HAM) 767.59 72 13.21 July-18 7 Integrated project for development of STPs in Allahabad alongwith existing Assets 904.00
- July-18
Uttar Pradesh State Project Overview
34
Sl No. Name of Project Sanctioned Cost ( in Cr.)
STP Capacity (MLD)
Sewer Network (Km) Likely Date
- f Award
8 Farrukhabad I&D and STP works (HAM) 213.62 35
- Jul-18
9 I&D works and STP, Mirzapur (HAM) 114.93 17
- Jul-18
10 I&D works and STP, Gazipur (HAM) 90.81 21
- Jul-18
Total 3310.22 206 33.6
Uttar Pradesh – Under Tendering
35
Namami Gange Projects (20 Towns) in Bihar
Projects – 20 Work in Progress – 10 Tender under evaluation-4 Under tendering- 6
Cost: Rs. 4629.12 Cr
Sewerage Projects in Patna
Sewage Generation- 286 MLD Existing Capacity – 109 MLD Work in Progress – 200 MLD Tender to be Floated- 150 MLD All 33 drains being tapped
37
PM Laying Foundation Stone for Patna Sewerage Schemes (at Mokama)
38
- S. No.
Project 1 Sewer Networks, SPS and STP at Buxar Cost – 74.95 Cr STP capacity – 16 MLD Physical progress – 39 % Likely date of completion – Feb’19 2 Sewage Treatment Plant - Beur for Patna, Bihar Cost – 68.16 Cr STP capacity – 43 MLD Physical progress – 23 % Likely date of completion – Dec’19 3 Sewerage system with Sewer network, Patna Beur Cost – 225.77Cr Physical progress – 22% Likely date of completion – Mar’20
Bihar– Ongoing projects
Beur STP, Patna Beur Network, Patna
Bihar State Project Overview
39
- S. No.
Project
4 Sewage Treatment Plant - Karmalichak for Patna, Bihar Cost – 77.04 Cr STP capacity – 37 MLD Physical progress – 24 % Likely date of completion – Dec ‘ 19
5 Saidpur STP and adjoining Network for Patna, Bihar Cost – 184.93 Cr STP capacity – 60 MLD Physical progress – 22% Likely date of completion – Dec’19 6 Saidpur Sewer Network, Patna, Bihar Cost –Cr STP capacity –6 MLD Physical progress –% Likely date of completion – 7 Sewerage scheme at Pahari Zone V, Patna, Bihar Cost – 356.37Cr (Agreement signed on 25-4-2018) Likely date of completion – Apr’21
Bihar– Ongoing projects
Saidpur STP, Patna
Bihar State Project Overview
40
S.No.
Project 8 Sewerage scheme at Pahari (Zone IVA (S)), Patna, Bihar Cost – 184.86 Cr (Recently Awarded) Likely date of completion – Apr’21
9
Sewerage Treatment Plant at Pahari - Patna, Bihar Cost – 191.62 Cr STP capacity – 60 MLD (Agreement signed on 9-5-2018) Likely date of completion – April’21
10
Sewerage system with Sewer network ,Patna Karmalichak Cost – 277.42 Cr (Recently Awarded) Likely date of completion – Aug’20 Total Cost (10 projects) – 1909.75 Cr STP capacity – 216 MLD
Bihar– Ongoing projects
Karmalichak STP, Patna
Abstract - Under Tendering Process projects Projects Cost Tender Under Evaluation Tender to be floated 10 2719.12 4 6
41
Sl No. Name of Project Sanctioned Cost ( in Cr.) STP Capacity (MLD) Sewer Network (Km) Likely Date of Award 1 Sultanganj I&D and STP works 60.22 10
- May-18
2 Mokama I&D and STP works 53.81 8
- May-18
3 I&D and STP for Barh town 58 11
- May-18
4 I&D and STP works for Naugachia 60.79 9
- May-18
Total 232.82 38
Bihar– Tender Received and Finalisation in Process:
42
Sr. No Project Name Approved Project Cost ( in Cr.) STP capacity (MLD) Sewer Network (Km) NIT Publication Date 1 Sewerage System and STP for Digha zone, Patna (HAM) 824.00 100 288 May-18 2 Sewerage System and STP for Kankarbagh zone, Patna (HAM) 578.89 50 150 May-18 3 I&D and STP works for Bhagalpur (HAM) 254.13 65
- Jun-18
4 Sewer Networks, SPS and STP, Munger 294.02
30 174.75
May-18 5 Sewer Network, SPS and STP, Begusarai 230.07
17 114
May-18 6 Sewer Networks, SPS and STP, Hajipur 305.19
22 189.3
May-18 Total 2486.3 284 916
Bihar– Tender to be floated
43
Namami Gange Projects (2 Towns) in Jharkhand
Sahibganj- 12 MLD STP, 55 km Sewer, 99.36 Cr,32% progress; likely completion- December 2018 Rajmahal- 3.5 MLD STP, 34 km Sewer, 50.23 Cr, recently awarded; likely completion by June 2019
Projects – 2 Work in Progress – 2 Cost: Rs. 149.59 Cr
44
Sahibganj STP
45
Namami Gange Projects in West Bengal
Projects – 15 Completed –2 Work in Progress – 4 Under Tendering -4 Tender to be floated-5
Cost: Rs. 2606.58 Cr
West Bengal State Project Overview
46
Sl No. Project 1 Sewerage Scheme & STP works at Gayeshpur Cost – 168.67 Cr STP capacity – 8.23 MLD 2 Sewerage Scheme & STP works at Kalyani Cost – 57.87 Cr STP capacity – 4+17 MLD Total Cost – 226.54 Cr STP capacity – 29.23 MLD
West Bengal – Completed projects
West Bengal State Project Overview
47
S.No. Project 1 Sewerage Scheme & STP works at Bhatpara Cost – 228.52 Cr STP capacity – 31 MLD Physical progress – 91% Likely date of completion – Jun’18 2 Sewerage System & STP works at Halishahr Cost – 274.76 Cr STP capacity – 16 MLD Physical progress – 28 % Likely date of completion – Dec’18
West Bengal –Ongoing Projects
West Bengal State Project Overview
48
S.No. Project 3 Sewerage System & STP works at Budge-Budge Cost – 145.98 Cr STP capacity – 9.3 MLD Physical progress –35 % Likely date of completion – Oct’19 4 Sewerage System with sewer network at Barrackpore Cost – 272.32 Cr STP capacity – 24 MLD Physical progress – 24 % Likely date of completion – Dec’19 TOTAL (4 projects) - Cost 921.58 Cr STP capacity – 80.3 MLD
West Bengal – Ongoing Projects
49
Sl No. Name of Project Sanctioned Cost ( in Cr.)
STP Capacity (MLD)
Sewer Network (Km) Likely Date
- f Award
1 Interception, Diversion & treatment works at Behrampore 51.20 3.5 5.25 Jun-18 2 Interception, Diversion & treatment works at Nabadwip 54.30 20 4 Jun-18 3 Interception, Diversion & treatment Works at Tolly's Nullah (Adi Ganga) (HAM) 307.12 26.10 114 Jul-18 4 Integration of STPs with rehabilitation and O&M of existing Assets 165.16
- Jul-18
Total 577.78 49.6 123.25
West Bengal – Under Tendering projects
West Bengal State Project Overview
50
Tender to be floated:
Sl
- No. Name of Project
Date of AA&ES Sanctione d Cost ( in Cr.) STP Capacity (MLD) Sewer Networ k (Km) NIT Publicatio n 1 Interception, Diversion & treatment works at Howrah (HAM) 02.08.2017 185.22 65 May-18 2 Interception & Diversion with STP at Bally (HAM) 10.10.2017 164.93 40 May-18 3 Interception, Diversion & treatment works at Baranagar & Kamarahati (HAM) 17.01.2018 172.10 60 9 May-18 4 Interception & Diversion with STP at Hugli- Chinsurah
- 160
29.3 20 Jun-18 5 Interception & Diversion with STP at Maheshtala
- 198.43
28.1 Jun-18 TOTAL 880.68 222.4 29
West Bengal – Tender to be floated
Status of Existing Sewerage Infrastructure & Interventions
- 97 towns on Ganga Main Stem
- Sewage Generation : 2953 MLD (Yr. 2016), 3603 MLD (Yr 2035)
- Available Treatment Capacity (01/11/2017) : 84 STPs – 1584 MLD in 46 Towns
Status of Existing 84 STPs
51
Recently commissioned, working fine alongwith long term O&M (733 MLD) - 39 STPs Operational and non compliant & under utilized (581 mld) - 14 STPs Defunct (270 mld) - 31 STPs
46% 17% 37%
39 STPs- Working satisfactorily 12 STPs (91 MLD)- Up-gradation & O&M Sanctioned 8 STPs (530 MLD)- Integrated under One City One Operator 23 STPs – Tender for upgradation 2 STPs discarded;
Present Status of Existing STPs
52
State Working fine – Necessary Interventions taken
- Nos. (MLD)
Up-gradation & O&M Sanctioned
- Nos. (MLD)
Integrated under One City One Operator
- Nos. (MLD)
Up- gradation through Atkins Nos. (MLD) Discarded
- Nos. (MLD)
Total
- Nos. (MLD)
Uttarakhand 9 (91.9) 2 (9.5) Lakkar Ghat Srinagar 11(101.4) Uttar Pradesh 17 (437.31) 4 (343) Jajmau 130 Bingawan 210 Shantipuram Trivenipuram 1 (27) Jajmau CETP 2 (7.5) Kalindipuram Jajmau 5 24(814.81) Bihar 3 (84) 3 (38) Pahari, Buxar Bhagalpur (BP) 1 (2) Chhapra 7(124) West Bengal 10 (119.42) 7 (43.25) Bhatpara– 4nos. Budge-Budge Barrackpore Maheshtala (BP) 4 (187) Anupara (BP) Gardenreach Keorapukur Kamarhati (BP) 21 (194.27) 42(543.94) Total 39 (732.63) 12 (90.75) 8 (530) 23 (223.27) 2 (7.5) 84 (1584.15) Implementati
- n Status
Operating Execution- 10 (75.27) Bid prep – 2 (15) Bidding- 6 (445) Bid prep- 2 (85) Bid prep- 23(223.27) Execution- 10 (75.27) Bidding – 6 (445) Bid prep – 27 (323.27)
Sr. No. State
- No. of
Tributaries
- No. of
Towns 1 Uttarakhand 1 1 2 Uttar Pradesh 10 33 3 Bihar 7 15 4 Jharkhand 2 2 5 West Bengal 1 3 6 Rajasthan 3 4 7 Madhya Pradesh 7 10 TOTAL 31 68
Upcoming Projects on Tributaries
Decentralised Treatment of 20 drains in 15 cities through Modular Treatment System
- 20 drains which are not covered in sewerage projects have
been identified
- Pollution flowing in 20 drains in 15 cities (about 60 MLD) to be
contained & treated using modular STPs,
- First of its kind offered on services contract model and include
removal of trash, solid waste and pollution load.
- Bhudana, Muzaffar nagar, Gajraula, Moradabad, Hapur,
Gulaothi, Kasganj, Unnao, Bhadohi, Kunda in UP and Titagarh, Jangipur, Champdani, Chandannagar and Belur in West Bengal.
- Tenders on services model are under process
- Award of work by May’2018 end.
- Modular STPs are ready to install tailored systems and will be
- perational in six months time.
- After successful response to the tenders, the model will be
replicated in other untapped drains.
Ministry of Drinking Water and Sanitation has taken up construction of IHHLs, liquid waste management for all 1662 Gram Panchayats.
Rural Sanitation
55
- S. No.
State Completed IHHL Villages (Near Ganga) Declared as ODF 1 Bihar 321324 468 2 Jharkhand 24977 66 3 U.P 388340 1604 4 Uttarakhand 9540 222 5 W.B 339507 2105 Total 1083688 4465 Total Cost – Rs. 841.3 Crores
Ghats and Crematoria
- No. of
Projects
- No. Of
Cost ( in Cr) Status Ghats (G) Crematoria (C) Total (T) Completed Under Progress Under Tendering G C G C G C 37 151 54 205 721.94 32 6 104 22 15 26
Proposed Present
56
Original site Present Proposed Original site GHATS CREMATORIA
Rudraprayag Alaknanda River Bathing Ghat - 1 Srinagar Nathaini Cremation ghat
57
- No. of
Projects
- No. Of
Cost ( in Cr) Status Ghats (G) Crematoria (C) Total (T) Completed Under Progress Under Tendering G C G C G C 9 22 22 44 175.08 8 6 13 16 1
Ghats and Crematoria - Uttarakhand
RAMKUND GHAT DEVPRAYAG RHS RUDRAPRAYAG
Chandi Ghat RFD
58
Development of Chandi Ghat (Adjacent to Chandi Ghat Bridge, Haridwar) Project cost- 50.36 Cr Physical progress- 55% Expenditure- 26.17 Cr Likely Date of Completion- Dec-18 Main Component of Chandi Ghat Project-
- Bathing Ghat- 630 m long
- Cremation Ghat- 140 m long
- STP- 25 KLD
- Water & Sewer Network- 1.5 km
- Overhead Water Tank- 70 KLD
PRE - PROJECT SCENARIO PRESENT SCENARIO
59
- No. of
Projects
- No. Of
Cost ( in Cr) Status Ghats (G) Crematoria (C) Total (T) Completed Under Progress Under Tendering G C G C G C 11 87 25 112 397.70 23 61 1 3 24
Ghats and Crematoria – Uttar Pradesh
Bhairav, Kaushalya, Bharat & Pandav Ghats Bithoor Sarsaiya ghat, Kanpur Ravani katiri Ghat, Balawali to Anupshahr
60
- No. of Projects
- No. Of
Cost ( in Cr) Status Ghats (G) Crematoria (C) Total (T) Completed Under Progress G C G C 5 14 1 15 40.86 14 1
Ghats and Crematoria - Bihar
Pul Ghat, Sonepur Gola ghat, Buxar Konhara Crematoria, Hajipur
61
Patna RFD
Patna RFD
Cost: 243.27 Crore Expenditure: 167 Crore
- No. of Ghats: 20 Complete: 16
Promenade: 6.6 km Complete: 4.7 km Crematoria : 1 Civil Work complete
- verall 85% complete
62
- No. of
Projects
- No. Of
Cost ( in Cr) Status Ghats (G) Crematoria (C) Total (T) Completed Under Progress Under Tendering G C G C G C 4 12 2 14 62.07 1 7 1 4 1
Ghats and Crematoria - Jharkhand
Sarkanda Ghat Sahibganj to Rajmahal Maskaliaya Crematorium
63
- No. of
Projects
- No. Of
Cost ( in Cr) Status Ghats (G) Crematoria (C) Total (T) Completed Under Progress Under Tendering G C G C G C 7 15 4 19 44.24 9 3 6 1
Ghats and Crematoria – West Bengal
Bhatpara Crematorium Babughat, Garulia Girish ghat, Garulia
- Trash skimmers are deployed in 11 cities.
- Delhi, Haridwar, Garhmukteshwar, Kanpur, Allahabad,
Varanasi, Patna, Sahibganj, Howrah, Mathura- Vrindavan, and Nabadwip.
River and Ghat Cleaning
64
Trash Skimmers IL&FS Environmental Infrastructure and Service Ltd. (IEISL) to clean 84 Ghats in Varanasi for 3 years at the cost of Rs.5.0 Crores per year under tripartite agreement between NMCG, Varanasi Nagar Nigam & IEISL.
Man Mandir Ghat
- Similar Ghat Cleaning activities are
being taken up for other major towns such as Haridwar, Kanpur- Bithoor, Allahabad ,Mathura-Vrindavan Ghat Cleaning
Afforestation
FRI, Dehradun has prepared afforestation plan of 1,34,106 hectare areas at an estimated cost of INR 2294 crores.
65
2016-2018 STATE Area in ha. Rs crore Uttarakhand 5369 35.497 Uttar Pradesh 831 18.652 Bihar 600.5 24.924 Jharkhand 396 13.428 West Bengal 3588 19.64 Total 10785 112.141
66
Biodiversity
- Biodiversity conservation to study restoration & rehabilitation of the aquatic environment of
River Ganga
- Assessment of Fish & fisheries in Ganga river system for developing sustainable
conservation & restoration plan
Thank You
67