Workshop for RC_2014_03: Administrative Improvements to the Outage Process
25 October 2019
Workshop for RC_2014_03: Administrative Improvements to the Outage - - PowerPoint PPT Presentation
Workshop for RC_2014_03: Administrative Improvements to the Outage Process 25 October 2019 Overview Update on original proposal issues New related issues Focus on specific issues to inform call for further submissions ( CFFS ) Not
25 October 2019
Slide 2
the calculation of Outages (RCOQ vs Capacity Credits)
Non-Scheduled Generators
Available Capacity calculation
Slide 3
February 2018 straw man
Slide 4
2019 update
and potential replacement of SMMITS
advises SM by email that it has submitted a CO request (no authorised notice)
Slide 5
Revised straw man
proposed
Slide 6
Original problem
Original proposal
Balancing Gate Closure (based on reasonable expectations)
Slide 7
Concerns with original proposal
triggering outage – potential for a Market Generator to suffer a FO
potential to avoid tests by submitting and withdrawing requests
discussed in RC_2013_15)
Slide 8
Updated proposal (2018)
summarised at February 2018 MAC meeting
accepted, accepted with conditions, approved, rejected, withdrawn, cancelled, rescheduled, ends early, or ends late
requests
Slide 9
Updated proposal (2018)
COs
FO notifications into SMMITS
Slide 10
2019 update
(high automation requirement)
Outages that affect generators
bilateral cover, commitment decisions)
Facility availability, reliability of Forecast BMOs)
Slide 11
Revised proposal
information about triggering outages to interested stakeholders
the available capacity of a Scheduled Generator or Non-Scheduled Generator by a specific quantity for a specific period (foreseeable constraint)
per year
Slide 12
(Question: how big a problem is this?)
Slide 13
Revised proposal – options for notification mechanism Option 3 – AEMO has suggested
similar’
(magnitude uncertain) Question: Other options?
Slide 14
Revised proposal
affected participants about upcoming outages
controls timing)
constraints (Network Operator initiated)
times, MW output limits
Slide 15
Revised proposal
Balancing Submissions (as far as possible)
complying with TO notifications
Slide 16
Slide 17
Revised proposal – Network Operator obligations
foreseeable constraints
Slide 18
Revised proposal – Late changes to triggering outages
triggering outages, e.g.
Non-Scheduled Generators and Balancing Portfolio Facilities
Slide 19
TO notifications for ‘foreseeable constraints’ caused by FOs
FO from a specific time in the future, e.g.
to issue TO notifications
Slide 20
Original problem
impractical – in practice using Capacity Credits
temperature exceeds 41 degrees)
Scheduling Day)
Slide 21
Generators
in capacity-adjusted outage calculations
Slide 22
2019 update
during a Commissioning Test
non-zero RCOQ then could incur capacity refunds – Not OK
Slide 23
2019 update
Commissioning Test FOs
Slide 24
Updated proposal
Non-Scheduled Generators (Non-Intermittent Generators)
Capacity Credits * MSOC_45 / MSOC_41
Tests
Slide 25
appendix at end of slide pack
and Appendix 1(e)(iiiA))
Slide 26
Updated proposal – Non-Scheduled Generator outage quantities
maximum sent out capacity
Slide 27
Hybrid Non-Scheduled Generators - outage quantities and materiality threshold
RC_2013_15
MSOC = Declared Sent Out Capacity (DSOC) = 150 MW
the solar components are unavailable
Slide 28
Hybrid Non-Scheduled Generators
Slide 29
Hybrid Non-Scheduled Generators
rates
maximum sent out capacity
Slide 30
Hybrid Non-Scheduled Generators
supplementary details of partial outages
necessary for verifying the details of the outage requested by SM”
any distortion
Slide 31
Administrative burden of outage reporting for large Non-Scheduled Generators
RC_2013_15
turbines are large)
Slide 32
Administrative burden of outage reporting for large Non-Scheduled Generators
▪
Why should 4 x 3 MW units be reportable but 2 x 6 MW units not be reportable?
from outage scheduling requirements
Slide 33
Use of Outage quantities in the Market Rules
17 January 2018 workshop
adjusted) will be used for which purposes
Hours calculations
Clarification of timeframe for providing Outage information to SM
(see additional related issues)
Slide 34
Slide 35
and exceptions, e.g. for COs
advice)
Slide 36
Outage” of another Rule Participant’s equipment
Facility
systems or comms systems) that are not included on the Equipment List
system equipment that affects generators
Slide 37
Replacement of clauses 7A.2A.3 and 7A.2A.4
Balancing Submission where
an expanded definition of a CO?
constraints and TO notifications
Slide 38
Background
(Collgar submission on RC_2013_15)
Issues List issue 33) – end time and outage quantity
compensation, outage rates for certification
Slide 39
Background
Question: What deadline for revised decision?
▪
Question: How would this work?
Slide 40
Proposal – Scheduled and Non-Scheduled Generators
▪
Amendment or cancel/replace depending on cost
▪
Obligation to report updated information within 1 Business Day of receiving it
instead (and why)?
Slide 41
limit
these available to AEMO/ERA on request
payments (AEMO has advised negligible additional cost)
Slide 42
Options for SMMITS submission deadline
submission or approval
as for FOs)
Slide 43
Options for deadline for SMMITS submission
revise its decision if better information becomes available
Slide 44
Proposal for SMMITS submission
day limit
Slide 45
Proposal for SM processing
foreseeable constraint information provided in TO notifications
requirements
Slide 46
Proposal for SM processing
notifications) unless other information available
Slide 47
Generators
Slide 48
Rule Change Panel meeting
Slide 49
Slide 50
complex and include non-Market Rules steps (e.g. use of as-generated quantities)
Appendix 1(b)(iv) Scheduled Generator-specific
generator trips)
Slide 51
Original proposal
clause 3.21.5 (for both Scheduled and Non-Scheduled Generators)
Slide 52
ratio of Sent Out Capacity at 41 degrees to Sent Out Capacity at 15 degrees, based on Standing Data temperature dependence file provided under Appendix 1(b)(iv)
RCOQ) to determine capacity-adjusted outage quantities at 41 degrees
Slide 53
quantities and capacity-adjusted outage quantities and where each should be used
Slide 54
Concerns with original proposal
Scheduled Generator that fails to comply with the instructions given to it by SM (e.g. trips mid-Trading Interval, fails to synchronise when expected, fails to ramp fast enough or maintain expected output level)
compensation
exceeds 41 degrees and RCOQ reduced
Slide 55
Concerns with original proposal
Generators with Capacity Credits
Slide 56
Updated proposal – general principles
sustainable basis under optimal conditions, taking into account the physical limits
Market (may change for ETS)
Slide 57
Updated proposal – general principles
reductions from MSOC
MSOC - ∑OQ
may affect the outage quantity recorded
Slide 58
Example for discussion – Scheduled Generator X
dependence file) of
Slide 59
Example 1: partial PO, still able to provide 60 MW over the duration of the outage (no other Outages)
= MSOC – Available Capacity = 110 – 60 = 50 MW
= max(0, OQ – max(0, MSOC – CC)) = max(0, 50 – max(0, 110 – 90)) = 30 MW
temperature does not exceed 41 degrees
Slide 60
Example 2: FO – Scheduled Generator trips during Trading Interval, 25 degrees (no other outages)
sent out MW over the Trading Interval
= 30 MWh * 2 = 60 MW
= MSOC – Available Capacity = 110 – 60 = 50 MW
= max(0, OQ – max(0, MSOC – CC)) = max(0, 50 – max(0, 110 – 90)) = 30 MW
Slide 61
Example 3: FO – Scheduled Generator trips during Trading Interval, 43 degrees (no other outages)
(50 MW) because Available Capacity is still 60 MW
reduced obligation when max site temperature > 41 degrees
= max(0, OQ – max(0, MSOC – CC * MSOC_45 / MSOC_41)) = max(0, 50 – max(0, 110 – 90 * 97 / 100)) = 27.3 MW
Slide 62
Updated proposal – Available Capacity assumption for FOs (trips and
Slide 63
Updated proposal - Non-Scheduled Generator outage quantities
maximum sent out capacity
Slide 64