A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS August 2011 Masonry and Concrete Improvements Status: Contractor: Pioneer Masonry Restoration Inc., Seattle WA. Construction contract: $87,931 Work
Masonry and Concrete Improvements
Status:
- Contractor: Pioneer Masonry
Restoration Inc., Seattle WA.
- Construction contract: $87,931
- Work being performed at
eight facilities.
- The work is substantially
complete.
School sign being rebuilt at Hazelwood Elementary School.
Masonry and Concrete Improvements
New mortar bearing pad at top of concrete column at Cascade Middle School. Existing mortar at top of concrete column at Cascade Middle School.
Masonry and Concrete Improvements
Removal of deteriorated mortar joints at the Pioneer Elementary School playshed.
Masonry and Concrete Improvements
Mortar joint removal at the Pioneer Elementary School chimney.
Masonry and Concrete Improvements
Filling mortar joints at the upper walls of Pioneer Elementary School gymnasium.
Masonry and Concrete Improvements
Mortar joint restoration at Pioneer Elementary School.
Energy Improvements
Status:
- Design / Build Contractor:
Ameresco Quantum, Inc, Renton, WA under an ESCO (Energy Service Company) contract.
- ESCO contract: $2,273,646
with partial funding from a $1,300,000 grant from OSPI.
- Work being performed at
11 facilities and includes lighting, plumbing, irrigation system, and mechanical equipment upgrades.
- Project 95% complete.
New lighting at classroom at Lake View Elementary School.
Energy Improvements
New low-flow toilet fixtures at Rainier Middle School.
Energy Improvements
New air handling unit being lifted onto roof at Alpac Elementary School.
Energy Improvements
New heat pump chillers at Rainier Middle School.
Hazelwood Elementary and Rainier Middle Schools Modernization
Status:
- Contractor: Lincoln
Construction, Inc., Spanaway WA.
- Construction contract:
$1,796,800.
- Work includes
architectural, food service, mechanical and electrical improvements at Hazelwood Elementary and Rainier Middle Schools.
- Project is 80%
complete.
New hot water heaters at Hazelwood Elementary School.
Hazelwood Elementary and Rainier Middle Schools Modernization
New fire sprinkler system at Hazelwood Elementary School.
Hazelwood Elementary and Rainier Middle Schools Modernization
New ramp for disabled access to stage at Hazelwood Elementary School.
Hazelwood Elementary and Rainier Middle Schools Modernization
Wall framing at Storage Room addition at Rainier Middle School.
Hazelwood Elementary and Rainier Middle Schools Modernization
Concrete floor patch where new electrical conduit was installed for computer lab in Library at Rainier Middle School.
Hazelwood Elementary and Rainier Middle Schools Modernization
New carpeting in main office at Rainier Middle School.
Hazelwood Elementary and Rainier Middle Schools Modernization
Installation of new sound system in Main Gym at Rainier Middle School.
Hazelwood Elementary and Rainier Middle Schools Modernization
Installation of new roof shingles at Rainier Middle School.
Hazelwood Elementary and Rainier Middle Schools Modernization
Roof at Rainier Middle School with new shingles.
Pool and Stadium Improvements
Status:
- Contractor: Jones &
Roberts Company, Olympia WA.
- Construction contract:
$2,369,500.
- Work includes a new
building addition and modernization of Auburn Pool; and miscellaneous improvements at Auburn Memorial Stadium.
- Project is 90%
complete.
Installation of new sound system at Auburn Memorial Stadium.
Pool and Stadium Improvements
New discus throw pad at Auburn Memorial Stadium.
Pool and Stadium Improvements
Storage room and mechanical room addition at Auburn Pool.
Pool and Stadium Improvements
Work being done to improve the electrical system at Auburn Pool.
Pool and Stadium Improvements
New cabinets in staff area at Auburn Pool.
Pool and Stadium Improvements
New overhead ductwork at Auburn Pool.
Pool and Stadium Improvements
New pool surface material being installed at shallow end of Auburn Pool.
Pool and Stadium Improvements
Installation of new pool surface material at Auburn Pool.
Pool and Stadium Improvements
Auburn Pool filled with water that is being filtered and cleaned.
Auburn High School Modernization and Reconstruction
Status:
- Architect: NAC
Architecture, Seattle WA.
- Estimated Construction
Cost: $76,000,000.
- Work includes
replacement of existing buildings except Auto Shop and PAC. Auto Shop, PAC and site will be modernized.
- Work continues on soil
investigations, utility surveying, and review of Design Development documents.
Drawing of existing sanitary sewer lines at Auburn High School.
Auburn High School Modernization and Reconstruction
Ground penetrating radar equipment being assembled for use in identifying the depth of underground pipes.
Auburn High School Modernization and Reconstruction
Ground penetrating radar being used to identify the depth of underground pipes at Auburn High School.
Auburn High School Modernization and Reconstruction
Underground utility investigations at East Main Street.
Auburn High School Modernization and Reconstruction
Preparation for film interview for the project information video.
Auburn High School Modernization and Reconstruction
Film interview for the project information video.
Auburn High School Modernization and Reconstruction
Design development drawing being reviewed by the Capital Projects Department.