WORK IN PROGRESS August 2011 Masonry and Concrete Improvements - - PowerPoint PPT Presentation

work in progress
SMART_READER_LITE
LIVE PREVIEW

WORK IN PROGRESS August 2011 Masonry and Concrete Improvements - - PowerPoint PPT Presentation

A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS August 2011 Masonry and Concrete Improvements Status: Contractor: Pioneer Masonry Restoration Inc., Seattle WA. Construction contract: $87,931 Work


slide-1
SLIDE 1

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT

WORK IN PROGRESS August 2011

slide-2
SLIDE 2

Masonry and Concrete Improvements

Status:

  • Contractor: Pioneer Masonry

Restoration Inc., Seattle WA.

  • Construction contract: $87,931
  • Work being performed at

eight facilities.

  • The work is substantially

complete.

School sign being rebuilt at Hazelwood Elementary School.

slide-3
SLIDE 3

Masonry and Concrete Improvements

New mortar bearing pad at top of concrete column at Cascade Middle School. Existing mortar at top of concrete column at Cascade Middle School.

slide-4
SLIDE 4

Masonry and Concrete Improvements

Removal of deteriorated mortar joints at the Pioneer Elementary School playshed.

slide-5
SLIDE 5

Masonry and Concrete Improvements

Mortar joint removal at the Pioneer Elementary School chimney.

slide-6
SLIDE 6

Masonry and Concrete Improvements

Filling mortar joints at the upper walls of Pioneer Elementary School gymnasium.

slide-7
SLIDE 7

Masonry and Concrete Improvements

Mortar joint restoration at Pioneer Elementary School.

slide-8
SLIDE 8

Energy Improvements

Status:

  • Design / Build Contractor:

Ameresco Quantum, Inc, Renton, WA under an ESCO (Energy Service Company) contract.

  • ESCO contract: $2,273,646

with partial funding from a $1,300,000 grant from OSPI.

  • Work being performed at

11 facilities and includes lighting, plumbing, irrigation system, and mechanical equipment upgrades.

  • Project 95% complete.

New lighting at classroom at Lake View Elementary School.

slide-9
SLIDE 9

Energy Improvements

New low-flow toilet fixtures at Rainier Middle School.

slide-10
SLIDE 10

Energy Improvements

New air handling unit being lifted onto roof at Alpac Elementary School.

slide-11
SLIDE 11

Energy Improvements

New heat pump chillers at Rainier Middle School.

slide-12
SLIDE 12

Hazelwood Elementary and Rainier Middle Schools Modernization

Status:

  • Contractor: Lincoln

Construction, Inc., Spanaway WA.

  • Construction contract:

$1,796,800.

  • Work includes

architectural, food service, mechanical and electrical improvements at Hazelwood Elementary and Rainier Middle Schools.

  • Project is 80%

complete.

New hot water heaters at Hazelwood Elementary School.

slide-13
SLIDE 13

Hazelwood Elementary and Rainier Middle Schools Modernization

New fire sprinkler system at Hazelwood Elementary School.

slide-14
SLIDE 14

Hazelwood Elementary and Rainier Middle Schools Modernization

New ramp for disabled access to stage at Hazelwood Elementary School.

slide-15
SLIDE 15

Hazelwood Elementary and Rainier Middle Schools Modernization

Wall framing at Storage Room addition at Rainier Middle School.

slide-16
SLIDE 16

Hazelwood Elementary and Rainier Middle Schools Modernization

Concrete floor patch where new electrical conduit was installed for computer lab in Library at Rainier Middle School.

slide-17
SLIDE 17

Hazelwood Elementary and Rainier Middle Schools Modernization

New carpeting in main office at Rainier Middle School.

slide-18
SLIDE 18

Hazelwood Elementary and Rainier Middle Schools Modernization

Installation of new sound system in Main Gym at Rainier Middle School.

slide-19
SLIDE 19

Hazelwood Elementary and Rainier Middle Schools Modernization

Installation of new roof shingles at Rainier Middle School.

slide-20
SLIDE 20

Hazelwood Elementary and Rainier Middle Schools Modernization

Roof at Rainier Middle School with new shingles.

slide-21
SLIDE 21

Pool and Stadium Improvements

Status:

  • Contractor: Jones &

Roberts Company, Olympia WA.

  • Construction contract:

$2,369,500.

  • Work includes a new

building addition and modernization of Auburn Pool; and miscellaneous improvements at Auburn Memorial Stadium.

  • Project is 90%

complete.

Installation of new sound system at Auburn Memorial Stadium.

slide-22
SLIDE 22

Pool and Stadium Improvements

New discus throw pad at Auburn Memorial Stadium.

slide-23
SLIDE 23

Pool and Stadium Improvements

Storage room and mechanical room addition at Auburn Pool.

slide-24
SLIDE 24

Pool and Stadium Improvements

Work being done to improve the electrical system at Auburn Pool.

slide-25
SLIDE 25

Pool and Stadium Improvements

New cabinets in staff area at Auburn Pool.

slide-26
SLIDE 26

Pool and Stadium Improvements

New overhead ductwork at Auburn Pool.

slide-27
SLIDE 27

Pool and Stadium Improvements

New pool surface material being installed at shallow end of Auburn Pool.

slide-28
SLIDE 28

Pool and Stadium Improvements

Installation of new pool surface material at Auburn Pool.

slide-29
SLIDE 29

Pool and Stadium Improvements

Auburn Pool filled with water that is being filtered and cleaned.

slide-30
SLIDE 30

Auburn High School Modernization and Reconstruction

Status:

  • Architect: NAC

Architecture, Seattle WA.

  • Estimated Construction

Cost: $76,000,000.

  • Work includes

replacement of existing buildings except Auto Shop and PAC. Auto Shop, PAC and site will be modernized.

  • Work continues on soil

investigations, utility surveying, and review of Design Development documents.

Drawing of existing sanitary sewer lines at Auburn High School.

slide-31
SLIDE 31

Auburn High School Modernization and Reconstruction

Ground penetrating radar equipment being assembled for use in identifying the depth of underground pipes.

slide-32
SLIDE 32

Auburn High School Modernization and Reconstruction

Ground penetrating radar being used to identify the depth of underground pipes at Auburn High School.

slide-33
SLIDE 33

Auburn High School Modernization and Reconstruction

Underground utility investigations at East Main Street.

slide-34
SLIDE 34

Auburn High School Modernization and Reconstruction

Preparation for film interview for the project information video.

slide-35
SLIDE 35

Auburn High School Modernization and Reconstruction

Film interview for the project information video.

slide-36
SLIDE 36

Auburn High School Modernization and Reconstruction

Design development drawing being reviewed by the Capital Projects Department.