WIRAB Webinar: Introduction to Remedial Action Schemes (RAS) in the - - PowerPoint PPT Presentation

wirab webinar introduction to remedial action schemes ras
SMART_READER_LITE
LIVE PREVIEW

WIRAB Webinar: Introduction to Remedial Action Schemes (RAS) in the - - PowerPoint PPT Presentation

WIRAB Webinar: Introduction to Remedial Action Schemes (RAS) in the West September 29, 2017 1 Presenters Gene Henneberg NV Energy Principal Engineer System Protection North Evan Paull WECC Associate Engineer Sarma (NDR)


slide-1
SLIDE 1

WIRAB Webinar: Introduction to Remedial Action Schemes (RAS) in the West

1

September 29, 2017

slide-2
SLIDE 2

Presenters

  • Gene Henneberg – NV Energy

– Principal Engineer System Protection North

  • Evan Paull – WECC

– Associate Engineer

  • Sarma (NDR) Nuthalapati, Ph.D – Peak Reliability

– Principal EMS Network Applications Engineer

2

slide-3
SLIDE 3

Outline

1. What are RAS and why do we use them in the Western Interconnection? 2. Western vs Eastern Interconnections 3. RAS Results, Actions, and Triggers 4. RAS classifications: LAPS, WAPS, SN 5. The WECC Remedial Action Scheme Reliability Subcommittee (RASRS) 6. RAS Modeling and EMS 7. Simple RAS Example 8. Explanation of WECC-1 9. Event #1: April 14, 2017 WECC-1 event

  • 10. Event #2: January 20, 2017 PAC Bonanza Generation Tripping
  • 11. Conclusion
  • 12. Questions?

3 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-4
SLIDE 4
  • 1. What are Remedial Action Schemes (RAS)?

4 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

NERC Glossary Definition A scheme designed to detect predetermined System conditions and automatically take corrective actions that may include, but are not limited to, adjusting or tripping generation (MW and Mvar), tripping load, or reconfiguring a System(s). RAS accomplish objectives such as:

  • Meet requirements identified in the NERC Reliability Standards;
  • Maintain Bulk Electric System (BES) stability;
  • Maintain acceptable BES voltages;
  • Maintain acceptable BES power flows;
  • Limit the impact of Cascading or extreme events.
slide-5
SLIDE 5
  • 1. Why do we use RAS in the WI?

5 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Often used to comply with NERC reliability requirements without building new transmission lines or other large electrical equipment. RAS are often installed to

  • Increase system transfer capacity
  • Meet project schedules

RAS are generally designed to mitigate three types of power system problems and time scales:

  • Thermal (minutes)
  • Voltage Stability (seconds to minutes)
  • Transient Stability (cycles to seconds)
slide-6
SLIDE 6

6

  • 2. Western vs Eastern Interconnection

Western vs Eastern Interconnection * Higher load (160GW vs 550GW) * Geography and population * History

slide-7
SLIDE 7
  • 2. Western vs Eastern Interconnection

7 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-8
SLIDE 8
  • 3. RAS Results

8 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

RAS actions are intended to bring the system back into balance and may include:

  • Changes in demand
  • Changes in generation
  • Changes to system configuration to maintain system stability,

acceptable voltage, and/or power flows

slide-9
SLIDE 9
  • 3. RAS Triggers and Actions

9 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

RAS Triggers

  • Line or Transformer Loss – 148
  • Protection Trip – 29
  • Overcurrent / MW / MVA – 89
  • Thermal – 28
  • Directional – 1
  • Under Frequency – 3
  • Acceleration – 1
  • Under / Over Voltage – 31
  • Out of Step ‐ 2

RAS Actions

  • Trip Generation – 134
  • Island the System – 8
  • Brake Insertion – 3
  • Multiple Actions – 77
  • Series Capacitor or Reactor Switching – 8
  • Shunt Capacitor or Reactor Switching – 23
  • Configuration Changes – 95
  • Load Shed or Rejection – 59
  • HVDC Ramp – 8
  • Excitation Forcing ‐ 1
slide-10
SLIDE 10
  • 4. RAS Classifications: LAPS, WAPS, and SN
  • LAPS – Local Area Protection Scheme (185)
  • WAPS – Wide Area Protection Scheme (75)
  • SN – Safety Net (19)
  • Approximately 279 RAS in the Western Interconnection

10 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-11
SLIDE 11
  • 4. LAPS, WAPS, and SN Flow Chart

11 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Start Safety Net? (Used for TPL)

RAS Failure could lead to load loss >= 300MW? RAS Failure could lead to generation loss >= 1,000MW?

Violate WECC TPL Criteria? Safety Net WAPS LAPS NO NO NO NO YES YES YES YES

slide-12
SLIDE 12
  • 5. WECC RASRS RAS Review

12 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

WECC’s Remedial Action Scheme Reliability Subcommittee (RASRS):

  • Reviews and approves all RAS in WECC, including their classifications
  • Provides outside feedback and comment on entity schemes
  • Develops of WECC RAS Criteria (PRC‐(012‐014)‐WECC‐CRT)
  • Maintains the RAS Database
slide-13
SLIDE 13
  • 6. RAS Modeling in EMS

13 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

  • Energy Management System (EMS)
  • Need to model RAS in EMS to study the impact

in Real‐Time Contingency Analysis

  • EMS Network Applications (NetApps) Group at PEAK

Reliability is responsible for all RAS model build and maintenance

  • NetApps group is also responsible for RAS model

update in other real‐time applications‐V&R Peak‐ ROSE Voltage Stability Analysis (VSA) and PowerTech Transient Stability Analysis Tool (TSAT)

slide-14
SLIDE 14
  • 7. Simple Illustration of RAS
  • RAS

– Loss of Line2, may overload Line1 – Need to trip G1 to protect line1 under loss of line2 – This scheme (referred to RAS scheme) is wired in the field to protect the line1

14 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

G1

Line1 Line2

Max Capacity 700 MW Max Capacity 700 MW

G2 G3

Line3

Load : 1000 MW Max Capacity 500 MW

Limit 500 MW Limit 500 MW

X X

slide-15
SLIDE 15
  • 7. Simple Illustration of RAS
  • RAS

– Loss of Line2, may overload Line1 – Need to trip G1 to protect line1 under loss of line2 – This scheme (referred to RAS scheme) is wired in the field to protect the line1

15 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

G1

Line1 Line2

Max Capacity 700 MW Max Capacity 700 MW

G2 G3

Line3

Load : 1000 MW Max Capacity 500 MW

Limit 500 MW Limit 500 MW

X X

slide-16
SLIDE 16
  • 8. Explanation of WECC‐1

16 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

WECC‐1 (the big one!)

slide-17
SLIDE 17
  • 8. Why WECC – 1

17 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

THE DOUGHNUT Major load center in California, especially around the LA basin Major generation in the Pacific Northwest and coal generation in Montana, Wyoming and

  • Utah. Nuclear in Arizona

and empty space in Nevada, Western Utah, and the area surrounding where Transmission lines swing through

slide-18
SLIDE 18
  • 8. WECC‐1 Names

18 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

WECC – 1 is also known as:

  • COI RAS (in the WECC database, California Oregon Intertie)
  • PACI RAS (primarily PG&E, Pacific AC Intertie)
  • AC RAS (primarily BPA)
  • Four Corners Scheme
  • NE / SE Separation scheme
  • Pacific Intertie Transfer Trip Scheme (PITT)

The scheme primarily watches loading and line conditions on COI

slide-19
SLIDE 19
  • 8. WECC‐1 Parameters

19 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

slide-20
SLIDE 20
  • 8. WECC – 1 Separation Map

20

WECC‐1 has the potential to split the interconnection in half The complete remedial action scheme for loss of the California- Oregon AC Intertie encompasses detection schemes, control logic, communication paths, and tripping schemes involving utilities in almost all states and provinces in the Western Interconnection. If the system was split, the scheme would then trip load in California and generation around the northwest to try and balance the two systems

slide-21
SLIDE 21
  • 9. Event #1

21 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

April 14, 2017 WECC‐1 Event

slide-22
SLIDE 22
  • 9. April 14, 2017 WECC‐1 Event

22

System conditions at the time of the event Two 500kV lines in COI out of service for scheduled work

  • 500kV Malin – Round Mountain #2 and
  • 500kV Round Mountain – Table Mountain #2

The Event 09:34 PPT: Round Mountain‐Table Mountain #1 500kV line relayed. No estimated time of return.

  • North to South: 600 MW
  • South to North: 2450 MW
slide-23
SLIDE 23
  • 9. April 14, 2017 WECC‐1 Event

23

With Path 66 (COI) now severely restricted, this immediately caused path 49 to run up to its System Operating Limit (SOL)

EP1

slide-24
SLIDE 24

Slide 23 EP1

Paull, Evan, 6/1/2017

slide-25
SLIDE 25
  • 9. April 14, 2017 WECC‐1 Event

24 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

To alleviate the flows on path 49 and 66 (and likely other areas as well) the WECC‐1 controller chose to trip generation in the Pacific Northwest The WECC‐1 operating procedure for tripping generation in the pacific northwest includes generation plants at:

  • Carty
  • Chief Joseph
  • GM Shrum (BCHA)
  • Grand Coulee
  • John Day
  • McNary
  • Mica (BCHA)
  • Peace Canyon (BCHA)
  • Revelstoke (BCHA)
  • Various Wind Plants (a dozen plus)
  • Wells (DCPUD)

The controller immediately tripped 1,300 MW somewhere in the Pacific Northwest

slide-26
SLIDE 26
  • 9. April 14, 2017 WECC‐1 Event

25

At 09:34 PPT, system frequency in the Western Interconnection dropped to 59.830 Hz due to the loss of generation the Pacific Northwest Frequency returned to normal in 10 minutes

slide-27
SLIDE 27
  • 10. Event #2

26 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

January 20, 2017 PAC Bonanza Generation trip

slide-28
SLIDE 28

27 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

  • 10. PAC Bonanza Gen shed
  • 10. PAC Bonanza Gen shed
slide-29
SLIDE 29
  • 10. PAC Bonanza Gen shed

28 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

Path 30 (AKA TOT 1A) rated at 650 MW East to West Path 33 (AKA Bonanza West) rated at 785 MW East to West Coal generation at Bonanza ~ 500 MW

slide-30
SLIDE 30

29 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

  • 10. PAC Bonanza Gen shed

At about 5AM the Bonanza ‐ Mona 345kV line trips This creates a potential line and equipment overload situation for the Flaming Gorge 115/230kV XFMRS and the Upalco to Carbon 115kV line RAS immediately trips generation at Bonanza to reduce flows on the Upalco – Carbon line and Flaming Gorge XFMR

slide-31
SLIDE 31
  • 10. PAC Bonanza Gen Shed

30 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

When the Bonanza plant tripped off this tripped the frequency down to about 59.935 but recovered quickly. Because of the RAS action there were no stability issues and the system returned to normal in minutes (namely ACE and Frequency)

slide-32
SLIDE 32
  • 11. Conclusion

31 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

  • RAS are used in the west because they are much cheaper than

building long, high voltage transmission lines and they help increase the transfer capabilities of lines.

  • They act as a smart controller, watching system conditions and

taking calculated actions in order to prevent a credible threat to the grid.

  • About 280 RAS in the Western Interconnection of differing sizes

and complexities.

slide-33
SLIDE 33

Questions?

32 W

E S T E R N

E

L E C T R I C I T Y

C

O O R D I N A T I N G

C

O U N C I L

?