Topics McGuire Air Force Base Restoration Program Site # SS-24 - - PowerPoint PPT Presentation

topics
SMART_READER_LITE
LIVE PREVIEW

Topics McGuire Air Force Base Restoration Program Site # SS-24 - - PowerPoint PPT Presentation

McGuire Air Force Base Restoration Program Site # SS-24 Topics McGuire Air Force Base Restoration Program Site # SS-24 Interim Remedial Action History of McGuire Restoration Site # SS-24 FASTRAC SS-24 Interim Remedial Action


slide-1
SLIDE 1

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 1

1

John G. Pohl, Restoration Program Manager

NJDEP Triad Approach Meeting September 4th, 2003

McGuire Air Force Base Restoration Program Site # SS-24 Interim Remedial Action

2

Topics

History of McGuire Restoration

Site # SS-24

FASTRAC SS-24 Interim Remedial Action Summary

3

COOKSTOWN, NJ WRIGHTSTOWN, NJ MCGUIRE AFB, NJ

C-17 BED DOWN AREA

4

C-17 HANGAR DEVELOPMENT PLAN

slide-2
SLIDE 2

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 2

5

C-17 HANGAR MILCON

6

Dock 2240 Wash rack

PROBLEM

7

C-17 Hangar Footprint

N

FORMER 2240 FORMER 2250 FORMER 2227 APPROXIMATE HANGAR BOUNDARY APPROXIMATE AOC BOUNDARY

8

FORMER BUILDING 2240

Dock 2240 Wash rack

FORMER BUILDING 2227

Bldg 2227 Dock 40 Separator

slide-3
SLIDE 3

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 3

9

Building 2240 Demolition

10

ISSUES

FEB 03 - Geoprobe Sample taken at the former Building 2227 site, revealed high levels of organic contaminants & breakdown products in groundwater in this area. Tetrachloroethene (PERC) at a maximum concentration of 13,754 µg/L Regulatory Level 1µg/L

11

FORMER BLDGS 2240 &2227

FORMER 2227 BLDG FORMER BLDG 2240

12

FORMER BLDG. 2227 – THE PIT

slide-4
SLIDE 4

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 4

13

FAST TRACK PLAN

01 APR 03 - Expeditiously characterize this site and develop a remedy Proceed with constructing the hangar on the site.

14

SS-24 Interim Assessment and Remedial Action

Tasks

Secure/Realign Funding Develop SOW Award Contract Develop Work Plan Secure Regulator Approval of Work Plan Complete Characterization Develop Interim Removal Action Plan Secure Regulator Approval of IRA Plan Execute IRA

15 16

Incorporates key elements from other expedited assessment methods

  • High level of key

stakeholder interaction

Requires experienced

Technical Team (FTT) empowered to make decisions in the field

  • Completes projects faster,

cheaper, and with greater regulatory satisfaction

slide-5
SLIDE 5

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 5

17

Jan 03- Demolition

Jan 29th GW sampling Apr 28th Interim Remedial Investigation (IRI) begins Jun 6th MILCON Resumes

2003 Timeline

Sep 3rd ES&H Oversight

  • f

MILCON Aug 29th Interim Remedial Action Complete Feb 28th Stop Work

18

C-17 Interim Characterization &Interim Remedial Action

SS24 Interim Assessment and Remedial Action, McGuire AFB, NJ Fastrac Technical Team

Science Applications International (SAIC) Hayworth Engineering Science, Tri-Corder

19

Triad Approach

DQO process ideal for Systematic Planning Numerous field analytical methods available Data quality adequate to support decisions Effective data manage largest uncertainty: Contaminant heterogeneity

  • r sample representative ness

20

Triad approach requires a tool box of site assessment tools

Soil and groundwater sampling tools:

  • CPT discrete soil and GW samplers
  • Percussion direct push discrete soil and GW samplers
  • MIP subsurface VOC sampler

Soil and GW analytical tools

  • FID/PID/ECD for MIP VOCs
  • DSITMS for VOCs in

discrete soil and GW

  • Off site lab for VOCs in

selected discrete soil and GW

slide-6
SLIDE 6

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 6

21

McGuire AFB, NJ C17 Hanger Site Investigation

The problem: Construction of a new hanger for C17 aircraft delayed by recently discovered potential Cl solvent source. Very limited GW sampling indicated up to 1% of solubility limit PCE Same data indicated limited distribution of shallow dissolved phase Apparent dechlorination underway at site Construction to resume in June 03

22

FORMER BLDGS 2240 &2227

FORMER 2227 BLDG FORMER BLDG 2240

5.0 ppb DCE 6.8 ppb VC 13750 ppb PCE* 2360 ppb TCE 840 ppb DCE 67 ppb VC Sampling points Jan 19, 2003

CSM Jan 19, 2003

23

McGuire AFB, NJ C17 Hanger Site Investigation Sampling points March 12th, 2003 CSM Mar 12th, 2003

24

08 APR 03

slide-7
SLIDE 7

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 7

25

MIP Results

Boundary of MIP ECD Detects

Site work began 28 Apr 03 CSM Field day 05

26

CPT & DPT Soil Sampling with DSITMS Analysis

CSM Field day 09

27

SITE STRATIGRAPHY

FORMER 2227

G r

  • u

n d w a t e r F l

  • w

High conductivity zones

28

CPT & DPT Groundwater Sampling with DSITMS Analysis

GW CSM Developed Field day 09- 14

slide-8
SLIDE 8

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 8

29

Combined Soil & Groundwater Results

Low-probability plume zone High-probability plume zone

Likely source leak areas

14 field days 15 MIP penetration 15 Geophysical CPT penetrations >20 continuous soil core logged Data collected using DSITMS and EPA Method 8265 33 soil sampling locations, 234 discrete soil analyses 45 GW sampling locations, 162 discrete GW analyses 244 QC analyses

30

Jan 03- Demolition

Jan 29th GW sampling Apr 28th Interim Remedial Investigation (IRI) begins Jun 6th MILCON Resumes

2003 Timeline

Sep 3rd ES&H Oversight

  • f

MILCON Aug 29th Interim Remedial Action Complete Feb 28th Stop Work

Exclusion Area, Groundwater C17 Hanger Footprint

130 ft 140 ft 45 ft

50 100

Scale (ft) 270 ft 240 ft

GROUNDWATER EXCLUSION ZONE

North

32

Soil Excavation Zone Exclusion Area, Soil C17 Hanger Footprint

80 ft 40 ft 115 ft

North

50 100

Scale (ft)

SOIL REMOVAL LOCATIONS

slide-9
SLIDE 9

McGuire Air Force Base Restoration Program Site # SS-24 September 2003 9

33

Proposed NA Well Locations

High-probability plume zone Low-probability plume zone

X X X X

  • X Performance Evaluation Well Cluster

LTM Well Cluster

X

NA Wells installed inside Hangar floor

34

STATUS

Tasks (As of 2 AUG 03) Secure/Realign Funding Develop SOW Award Contract Develop Work Plan Secure Regulator Approval of Work Plan Complete Characterization Develop Interim Removal Action Plan Secure Regulator Approval of IRA Plan Execute IRA

35 36

SUMMARY

Keys to project success:

  • Total Restoration Approach

Outstanding teamwork Excellent communications Synergistic teaming between the AF, regulators and the FTT Common goal Trust

  • Motivated “A-Team” across the board
  • Top cover from command