Los Angeles County Metropolitan Transportation Authority
Westside Subway Extension
Community Update Meeting
August 2009
Westside Subway Extension Community Update Meeting August 2009 - - PowerPoint PPT Presentation
Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonights Meeting Summary of Comments from Public Scoping Update on Alternatives Construction
Los Angeles County Metropolitan Transportation Authority
August 2009
Wilshire Subway Wilshire/West Hollywood Subway
– Service improvements to existing Metro Red/Purple Lines by 2035 – Assumes new rail lines with Measure R funding identified through 2035 Exposition LRT Phase 2, Crenshaw, Regional Connector, etc.
Management (TSM)
– Lower-cost improvements to maximize efficiency of existing road & transit networks
Draft EIS/EIR
Final EIS/EIR/PE
Months 18 21 33 Months
Final Design Construction*
Approved Alternatives Analysis Study
Selects LPA
Approval for Preliminary Engineering (PE)
Record of Decision (Certification)
Availability
Grant Agreement
for subway
lengthen initial segment(s) of subway
future rail
mitigations
Crenshaw, West LA)
– Santa Monica Boulevard – Constellation Boulevard – Avenue of the Stars
– Alignment under golf course – Longer route, more travel time & higher cost – Under many private properties
– Santa Monica Boulevard – Constellation Boulevard – Alignments
– Le Conte – Westwood (N/S) – Wilshire/Westwood (on-street) – Wilshire/UCLA (off-street)
eliminated
– require alignment under cemetery – greater construction impacts in Westwood Village
Boulevard station options & alignments
– Veterans Administration (VA) Hospital – Federal – Barrington – Bundy
– Close to Barrington – Impact on sensitive property
– VA Hospital
– Barrington
– Too far west for MOS 3 – Potentially part of further westward subway extension
alignment selected over La Cienega Boulevard
– Allows a station west of La Cienega – Better located in commercial & activity center of West Hollywood
evaluate possible transfer station at Wilshire/La Cienega
– Optional Crenshaw station – Alternative locations at:
Westwood, Century City, West LA & Wilshire/La Cienega
– Location-specific details
Station entrance(s), station urban design, parking & engineering
– Identify best possible alignments – Define alignment details
Metro riders boarding Red Line Metro Purple Line: Wilshire/Western Station
the Final EIS/EIR
– Eligible & highly competitive for federal “new starts” funding – Able to be built & operated within projected available funding
Segments (MOS)
Measure R Expenditure Plan identifies $4.1 billion for the Westside Subway Extension
Measure R Expenditure Plan identifies $4.1 billion for the Westside Subway Extension
testing & gathering soil samples at about 70 locations throughout study area
Drill rig along Wilshire Boulevard
– Identify how project will be constructed and its impacts
– Adopt construction mitigation plan
– Engineering/Technical – Cost – Timing – Community Input
– Use tunnel boring machines (TBMs)
– Excavated under “decked-over” streets
Twin Tunnels on Eastside Extension
maintain pressure in surrounding earth
settlement
and operate a subway along the Wilshire Corridor safely” (APTA Peer Review, 2005)
TBM maintains pressure in surrounding earth as it tunnels
subsidence
damage claims
Soto Street Station Under Construction Gold Line Eastside Extension Tunnel
1. Prepare site & excavate shaft where TBMs lowered into ground 2. Lower TBMs using cranes 3. Excavate two parallel tunnels (22 ft. diameter) 4. Install precast, gasket-lined, concrete tunnel lining 5. Install rails, electrical & other systems 6. Remove excavated soil at shaft
Boring can proceed on each tunnel simultaneously Machines excavate about 50 feet per day Boring can proceed on each tunnel simultaneously Machines excavate about 50 feet per day
Cross-section of tunnel lining
maintain service
perimeter at edge of roadway
existing roadway
roadway
Concrete Decking Street Excavation
Decking is flush with existing street level so traffic continues to flow Decking is flush with existing street level so traffic continues to flow
depth of station
Construction below ground while traffic continues to flow above
1. Drill “soldier piles” on station box perimeter 2. Excavate station box 3. Construct station box in excavated area 4. Install station elements & architectural features 5. Cover station box & restore area
Wood beams installed between soldier piles Off-street station box excavation
– Drill soldier piles along roadway or around station site – Install decking
– Excavate & support station area – Construct cast-in-place concrete station & add station elements
– Remove decking & restore street *Most disruptive activities to local community for on-street stations
Total = 48-54 Months
Typical Cross Section Station box 600’ long x 60’ wide x 60’ deep (approx.)
isolate gas from workers & public
separated and treated appropriately
system ensures tunnel & station safety
lining or other methods as appropriate
Soil slurry contains excavated soil in pipe thru tunnel. Gassy soil & tar sands separated & treated as necessary.
surface
designated disposal sites
beforehand
Soil is stockpiled at tunnel shaft before hauling to disposal site Soil hauled away by dump trucks
– Typically leased for time needed
immediately adjacent to station box preferred
where sites not available
Off-street construction area on Eastside Extension On-street construction area used for 7th/Metro station
major streets & highways where possible
all construction steps
where possible
construction site
attractive fencing materials)
Construction during night hours may reduce traffic impacts
Community input is an important factor
tunnels & stations
– Survey property condition – Photographic record
community stakeholders & businesses
campaign
response protocols
EIS/EIR
– Provide signage & marketing assistance to businesses – Parking alternatives – Other
EIS/EIR determine impacts
during Final EIS/EIR
sites & from soil removal
construction
Cut & Cover Station Construction on Eastside Extension
– Locally focused topics – “Working” meeting format – Watch for notices
– Refinement of alternatives – Station details
Updates
– Continued refinement of alternatives
Community Meeting
– Study recommendations – Recommendation of Locally Preferred Alternative (LPA) – Formal Public Hearings
Consideration
– Draft EIS/EIR – Adoption of LPA – Direction to proceed into Final EIS/EIR
Community Meeting
Meetings 6 – 8 PM Materials presented identical at each meeting
www.metro.net/westside Jody Litvak, Regional Communications litvakj@metro.net 213.922.1240 David Mieger, Project Director miegerd@metro.net 213.922.3040 Information line: 213.922.6934 Find us on Facebook: Metro Westside Subway Extension