westend 25
play

WestEnd 25 Outline Project Background Concrete Faade WestEnd 25 - PDF document

Charles Miller WestEnd 25 Construction Option Spring 2009 Dr. Riley WestEnd 25 Outline Project Background Concrete Faade WestEnd 25 Background WestEnd 25 LEED Conclusions Concrete Placement Acknowledgement


  1. Charles Miller WestEnd 25 Construction Option Spring 2009 ‐ Dr. Riley WestEnd 25

  2. Outline � Project Background � Concrete � Façade � WestEnd 25 Background WestEnd 25 � LEED � Conclusions � Concrete Placement � Acknowledgement � Questions � Precast Façade � LEED Charles Miller Spring 2009 ‐ Dr. Riley � Conclusions Construction Option � Acknowledgements � Questions WestEnd 25

  3. Outline � Project Background � Concrete � Façade WestEnd 25 � LEED � Conclusions � Function: Residential Apartments � Acknowledgement � Questions � Size: 324,000 sq. ft. / 10 stories � Project Cost: $76 Million Charles Miller Spring 2009 ‐ Dr. Riley � Construction Period: March 2007 – January 2009 Construction Option WestEnd 25 � Owner: Vornado ‐ Charles E. Smith � Contractor: James G. Davis Construction � Architect: Shalom Baranes Associates Architects WestEnd 25

  4. Outline � Project Background � Concrete � Façade WestEnd 25 � LEED � Conclusions � Existing: � Acknowledgement � Questions � Two 6 story office buildings Structural Concrete Slabs: � Precast Façade Added Levels: 6” Post ‐ Tensioned Exterior Façade: � Concrete Structural System Charles Miller Spring 2009 ‐ Dr. Riley Metal Panels Connection: 7.5” Post ‐ Tensioned Construction Option Brick Facade Curtain Wall � New Construction: Existing: 7.5” Conventionally Reinforced � One 10 story apartment building � Curtain wall and Brick Facade � Concrete Structural System WestEnd 25

  5. Outline � Structural System: � Project Background ▪ Existing: � Concrete � Façade ▫ 6 Stories Concrete � Placement Method: WestEnd 25 � LEED � Conclusions ▪ Crane and Bucket � Acknowledgement � Questions � Suggested Placement: ▪ Concrete Pump ▪ New Construction: Charles Miller Spring 2009 ‐ Dr. Riley ▫ Faster Installation Construction Option ▫ 6 Connectors � Schedule ▫ 4 Stories Concrete � Cost WestEnd 25

  6. Outline � Project Background � Concrete � Façade � Schedule Comparison: WestEnd 25 � LEED � Same Connector Slab Duration � Conclusions � Acknowledgement � Pump Saves 2 Days per Full Slab � Questions Charles Miller Spring 2009 ‐ Dr. Riley Construction Option WestEnd 25

  7. Outline � Project Background � Concrete � Façade � Placement Schedule Effects Timeline: WestEnd 25 � LEED Crane and Bucket: � Conclusions � Acknowledgement 9/1/08 10/1/08 11/1/08 12/1/08 1/1/09 7/1/08 8/1/08 � Questions Charles Miller Spring 2009 ‐ Dr. Riley Construction Option 7/3/08 10/14/08 8/15/08 10/8/08 12/1/08 12/11/08 4 Days 8 Days 10 Days 7/18/08 12/26/09 1/9/09 1/1/09 7/1/08 8/1/08 9/1/08 10/1/08 11/1/08 12/1/08 Pump: WestEnd 25

  8. Outline � Project Background � Concrete � Façade � Cost: � Conclusion: WestEnd 25 � LEED � Conclusions ▪ Connecting Slabs Limit Efficiency Item Quantity Cost Basis Total Cost � Acknowledgement Crane and Bucket 4,106 CY Equipment = ▪ Pump Benefits on Full Slabs � Questions Placement $7,000/week $193,375 Labor = $13/ CY ▪ Limited Overall Savings Pump Placement 4,106 CY $18.20/ CY $74,750 Charles Miller Spring 2009 ‐ Dr. Riley Cost Difference $118,625 Familiar but slower method is acceptable Construction Option Supplemental $650/day ($85,150) Crane: For 131 days Net Savings: $33,475 General Conditions $5,925/day $59,250 Savings For 10 days Total Savings: $92,725 � Potential savings of $92,725 � .12% of Project Cost WestEnd 25

  9. Outline � Project Background � Concrete � Façade � Original Façade WestEnd 25 � LEED ▪ Precast � Conclusions � Acknowledgement � Questions � Specified Façade ▪ Brick Cavity Wall ▪ Poor Slab Edges Charles Miller Spring 2009 ‐ Dr. Riley Construction Option � Precast Façade ▪ Schedule ▪ Cost ▪ Thermal Performance ▪ Structural Loads WestEnd 25

  10. Outline � Project Background � Concrete � Façade � Productivity Analysis � Precast Benefits: WestEnd 25 � LEED ▪ CE 533 – Construction Productivity Analysis and Performance � Conclusions ▪ Faster Installation � Acknowledgement Evaluation ▪ Less Delays due to Weather � Questions Activity in Progress Charles Miller Spring 2009 ‐ Dr. Riley � Analysis Expectations Construction Option ▪ Late Winter Weather Delays Report Quantities Report Workhours Calculate Productivity Performance Evaluation WestEnd 25

  11. Outline � Project Background � Concrete Brick Productivity � Façade � Productivity Chart WestEnd 25 � LEED 0.30 � Conclusions ▪ 3 Peaks of Decreased Productivity 0.25 � Acknowledgement � Questions ▫ One Weather Related 0.20 wh / sq. ft. ▫ Two Delays from Other Trades Uncompleted Work 0.15 ▪ Data Point Majority Below Baseline 0.10 Charles Miller Spring 2009 ‐ Dr. Riley Construction Option 0.05 ▫ Better than Expected Productivity 0.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Day Productivity Baseline Productivity � Analysis Shows Limited Benefits due to Weather Delays = Weather Delay = Other Trade Delay WestEnd 25

  12. Outline � Project Background � Concrete � Façade � Precast Sequencing: � Brick Sequencing: WestEnd 25 � LEED � 1 st floor North � Conclusions � North Facade � Schedule Comparison: � Acknowledgement � 1 st floor East � East Facade � Questions � 1 st floor South � South Facade � 2 nd floor North Charles Miller Spring 2009 ‐ Dr. Riley � 2 nd floor East Construction Option � Etc… WestEnd 25

  13. Outline � Project Background � Concrete � Façade � Cost: WestEnd 25 � LEED � Conclusions Item Quantity Cost Basis Total Cost � Acknowledgement � Questions Budget Estimate: Labor = $489,000 Brick Façade 23,030 sq. ft. Material Estimate = $416,000 $1,036,250 Equipment = $131,250 Precast Facade 23,030 sq. ft. $35/sq.ft. $806,050 Charles Miller Spring 2009 ‐ Dr. Riley Construction Option Difference: $230,200 Demolition Extra Work: $77,000 Total Savings: $307,200 � Conclusion: ▪ Cost Savings Must be Weighed Against Risk of Difficult Installation ▫ Feasibility Depends on Crew WestEnd 25

  14. Outline � Project Background � Concrete Precast Façade: Traditional Brick Façade: � Façade � U ‐ Value Comparison WestEnd 25 � LEED Layer R – Value ((hr*ft 2 * o F)/Btu ) R ‐ Value ((hr*ft 2 * o F)/Btu ) Layer � Conclusions ▪ Coefficient of Heat Transfer � Acknowledgement Exterior Air Film 0.17 � Questions Exterior Air Film 0.17 ▪ Lower Value Better 4 in. Face Brick 0.80 6” Concrete 0.60 2” Rigid Insulation 10.00 1.5” Air Space 0.93 5/8” Gypsum Board 0.56 Charles Miller Spring 2009 ‐ Dr. Riley 2” Rigid Insulation 10.00 � Precast Option is Thermally Feasible Construction Option Framing Cavity 9.0 5/8” Gypsum Board 0.56 1/2" Gypsum Board 0.45 Framing Cavity 9.0 Interior Air Film 0.68 1/2” Gypsum Board 0.45 Total 21.46 Interior Air Film 0.68 U ‐ Value 0.047 Total 22.59 U ‐ Value 0.044 WestEnd 25

  15. Outline � Project Background � Concrete � Façade � Structural Analysis WestEnd 25 � LEED � Conclusions ▪ pca Column � Acknowledgement � Questions Load Calculation Total 150lbs/ft 3 (.5ft)(1ft)(10.6ft)=795lbs/ftwidth Panel 9,540 lbs Charles Miller Spring 2009 ‐ Dr. Riley 795lbs/ftwidth(12ftwidth) Construction Option (0.625ft)(150lb/ft 3 )=93.75lbs/ft 2 Concrete 22,089 lbs 93.57lb/ft 2 (200ft 2 )+(22.5ft 3 )(150lbs/ft 3 ) Wind 43psf(1ft)(10.6)=455.8lbs/ftwidth 5,469.6 lbs 455.8lbs/ftwidth(12ftwidth) Floor 40psf + 20psf =60psf 12,000 lbs 60psf(200 ft 2 ) � Precast Structurally Feasible WestEnd 25

  16. Outline � Project Background � Concrete � Façade � Façade Conclusion WestEnd 25 � LEED � Conclusions ▪ Thermal Analysis and Structural Analysis Prove the � Acknowledgement � Questions Precast Façade is Feasible ▪ Cost Savings Must be Weighed Against Risk of Difficult Installation Charles Miller Spring 2009 ‐ Dr. Riley Construction Option ▫ Feasibility Depends on Crew WestEnd 25

  17. Outline � Project Background � Concrete � Façade � Critical Industry Issue: 2008 PACE Roundtable Breakout WestEnd 25 � LEED � Conclusions Session: LEED Evolution � Acknowledgement ▪ Increase Owner Involvement � Questions � Interviews of Industry Professionals ▪ Series of Open Ended Questions Charles Miller Spring 2009 ‐ Dr. Riley Construction Option ▪ Interesting Results WestEnd 25

  18. Outline � Project Background � Concrete � Façade � What do owners need to do differently? WestEnd 25 � LEED � Conclusions ▪ Few Felt that Owners Need to Increase Knowledge Base � Acknowledgement Owner Improvement � Questions ▪ Owners Need to Accept Costs and Improve Integration 45% 40% Charles Miller Spring 2009 ‐ Dr. Riley 35% Construction Option 30% 44% 25% 20% 33% 15% 10% 11% 5% 0% Accept Up ‐ Front Increase Improve Costs Knowledge Planning/Team Intergration WestEnd 25

  19. Outline � Project Background � Concrete � Façade � What mistakes do owners typically make that cause WestEnd 25 � LEED � Conclusions problems for a project attempting a LEED Certification? Owner Mistakes � Acknowledgement ▪ Indecisiveness is a Major Problem � Questions 45% ▫ Owners Need to Set Clear Goals and Maintain Sustainability 40% Commitment 35% Charles Miller Spring 2009 ‐ Dr. Riley 30% ▪ Indecisiveness is a Larger Problem than Accepting Costs Construction Option 43% 25% 20% 29% 15% 10% 14% 5% 0% Change Waiting First Cost WestEnd 25

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend