welcome
play

Welcome Opening Remarks Updates (schedule) Parking Site and - PowerPoint PPT Presentation

Welcome Opening Remarks Updates (schedule) Parking Site and Building Design Public Comments 1 June BLPC / PFRC Project Parameters 1. New Elementary School for the Henry Community 2. Support Strategic Plan Goal #4 Provide Optimal


  1. Welcome Opening Remarks Updates (schedule) Parking Site and Building Design Public Comments 1 June BLPC / PFRC

  2. Project Parameters 1. New Elementary School for the Henry Community 2. Support Strategic Plan Goal #4 – Provide Optimal Learning Environments 3. Address capacity by providing 725 seats 4. Open by start of school 2019 5. Multi-story building in northwest corner of site 6. Structured parking 7. Project cost $59 million 1 June BLPC / PFRC

  3. General Schedule | Timeline AUGUST 2016 AUGUST 2017 ARLINGTON COUNTY FAIR ARLINGTON COUNTY FAIR January 2017 March 2017 June 2017 September 2019 July 2016 October 2016 Early Construction Packages Concept Schematic Design Use Permit Review Construction Design Design Development (21 months) Construction Documents Use Final First Design Concept Schematic Permit Design Day of Dev. Design Design Approval Approval School Approval Approval Approval Net-Zero Energy & Water Year Starts! 1 June School Board Approval pushed back three weeks BLPC / PFRC

  4. General Schedule | Timeline 20 18 15 20 17 21 4 1 29 3 31 7 April May June July August Sept May June June August August Sept tentative Joint Joint Joint Joint Joint Joint BLPC BLPC BLPC BLPC BLPC BLPC BLPC BLPC BLPC BLPC BLPC BLPC PFRC PFRC PFRC PFRC PFRC PFRC Schematic Concept Design Design to Community to School listening School Board Board session 9/22 info | 10/6 approval 7/1 info | 7/19 or 20 approval 6/8 1 June School Board Approval pushed back three weeks BLPC / PFRC

  5. June 1st, 2016 NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL Parking Brief 1 June Parking Brief BLPC / PFRC

  6. Total existing on- campus parking spaces 364 213 61 62 22 6 Existing Parking Supply and Occupancy

  7. Since the last meeting=.. • Toole Design Group re-counted parking occupancy before and after arrival, mid-day and before and after dismissal • On-street parking availability counts were similar to those collected in 2014 and 2013 • Peak use of the community center during the school day was much lower than previous counts − 2016 counts indicate ~55 spaces used by Community Center patrons during the peak weekday period − As a conservative approach, our analysis continued to use the 2014 figure (95 spaces) as a maximum, peak use for the Community Center Existing Parking Supply and Occupancy

  8. Since the last meeting=.. • In total, parking data collected a total of 21 different times: - Before and after arrival, and before and after dismissal on four different typical school days (May, June, September, October) - A rainy day in October (when staff/community center drive rates would be the highest) - During Back-to-School-Night - On a typical weeknight at 5:00 and 8:00pm - On a Sunday with a theater event Existing Parking Supply and Occupancy

  9. Total Parking Need (based on counts): 1,086 student Middle School 1 153 725 student Elementary School 2 141 Total APS Need* 294 Community Center 3 95 Total Site Need* 389 *Assumes no on-street parking and no TDM 1 Based on projected # of staff and current rate of parking, as well as visitor data from other middle schools 2 Based on drive rate and visitor rates from other similar schools 3 Based on 2014 parking lot counts Parking Requirements and Needs

  10. If Parking is Shared on the Site) Future Parking Need, Adjusted: Parking need for APS uses minus 10% TDM reduction 267 Parking need for Community Center 95 Use of Available On-Street Parking on Old Glebe 1 -12 Use of Available On-Street Parking on 2 nd1 -6 Total Adjusted Site Need 344 1 Assumes school use of available on-street spaces on the blocks adjoining the school site, on the same side of the street as the school. Based on counts taken before and after school arrival and dismissal. Assumes a maximum of 85% occupancy. Parking Requirements and Needs

  11. Recommended total future on-campus parking spaces if school and community parking is shared 344 221 Note: This assumes 28 shared spaces on the east side of the site during the school day . 61 62 22 Shared parking vs. school parking on west side

  12. If Parking is Not Shared on the Site) Future Parking Need, Adjusted: Parking need for APS uses minus 10% TDM reduction 267 Use of Available On-Street Parking on Old Glebe 1 -12 Use of Available On-Street Parking on 2 nd1 -6 Total Adjusted APS Parking Need 249 1 Assumes school use of available on-street spaces on the blocks adjoining the school site, on the same side of the street as the school. Based on counts taken before and after school arrival and dismissal. Assumes a maximum of 85% occupancy. Parking Requirements and Needs

  13. Total future on- campus parking spaces recommended if school parking is all provided on west side only 372 249 Note: This would leave 28 surplus spaces on the east side of the site during the school day. 61 62 22 Shared parking vs. school parking on west side

  14. Parking Not Shared Parking Shared Spaces, Total Site 344 372 Spaces on west side of 221 249 the site Shared parking vs. school parking on west side

  15. SUMMARY • Unless parking is shared between the school and park/community center uses, APS will need to provide 249 spaces on the west side of the site • Strategies that could allow APS to provide less than 249 spaces include: − Shared parking between the east- and west-side uses − Increased use of on-street parking − More aggressive TDM programs to support staff carpooling, transit, walking and biking Parking Requirements and Needs

  16. Discussion 1 June New ES on Thomas Jefferson Site BLPC / PFRC

  17. 1 June Existing conditions BLPC / PFRC

  18. 18 May Schemes 1 – 4. Garage option of scheme 4 advanced BLPC / PFRC

  19. 1 June Schemes 4.1 / 4.2 / 4.3 / 4.4 BLPC / PFRC

  20. 1 June Scheme 4.1: Three story scheme, parking level BLPC / PFRC

  21. 1 June Scheme 4.1: Three story scheme. Drop off not desirable BLPC / PFRC

  22. 1 June Scheme 4.2: Four story scheme, parking level BLPC / PFRC

  23. 1 June Scheme 4.2: Four story scheme. Drop off worth exploring. BLPC / PFRC

  24. 1 June Scheme 4.3: Four story scheme. Combined drop-off in garage BLPC / PFRC

  25. 1 June Scheme 4.3: Four story scheme. Drop off worth exploring BLPC / PFRC

  26. 1 June Scheme 4.4: Three story scheme, parking level BLPC / PFRC

  27. 1 June Scheme 4.4: Three story scheme. Drop off not desirable. BLPC / PFRC

  28. 1 June Schemes 4.2 and 4.3 for further advancement BLPC / PFRC

  29. 1 June Scheme 4.2a BLPC / PFRC

  30. 1 June Scheme 4.2a BLPC / PFRC

  31. 1 June Scheme 4.2a BLPC / PFRC

  32. 1 June Scheme 4.2a 249 school parking spots, 372 total on site BLPC / PFRC

  33. 1 June Scheme 4.2a BLPC / PFRC

  34. 1 June Scheme 4.2a BLPC / PFRC

  35. 1 June Scheme 4.2a BLPC / PFRC

  36. 1 June Scheme 4.2a BLPC / PFRC

  37. 1 June Scheme 4.2a BLPC / PFRC

  38. 1 June Scheme 4.2a BLPC / PFRC

  39. 1 June Scheme 4.2a BLPC / PFRC

  40. 1 June Scheme 4.2a BLPC / PFRC

  41. 1 June Scheme 4.2a BLPC / PFRC

  42. 1 June Scheme 4.2a BLPC / PFRC

  43. 1 June Scheme 4.3a BLPC / PFRC

  44. 1 June Scheme 4.3a BLPC / PFRC

  45. 1 June Scheme 4.3a BLPC / PFRC

  46. 1 June Scheme 4.3a 252 total school parking spots, 375 total on site BLPC / PFRC

  47. 1 June Scheme 4.3a BLPC / PFRC

  48. 1 June Scheme 4.3a BLPC / PFRC

  49. 1 June Scheme 4.3a BLPC / PFRC

  50. 1 June Scheme 4.3a BLPC / PFRC

  51. 1 June Scheme 4.3a BLPC / PFRC

  52. 1 June Scheme 4.3a BLPC / PFRC

  53. 1 June Scheme 4.3a BLPC / PFRC

  54. 1 June Scheme 4.3a BLPC / PFRC

  55. 1 June Scheme 4.3a BLPC / PFRC

  56. 1 June Scheme 4.3a BLPC / PFRC

  57. Discussion 1 June New ES on Thomas Jefferson Site BLPC / PFRC

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend