WASTEWATER COMMITTEE MEETING April 22, 2020 (Via Teleconference) - - PowerPoint PPT Presentation

wastewater committee meeting april 22 2020 via
SMART_READER_LITE
LIVE PREVIEW

WASTEWATER COMMITTEE MEETING April 22, 2020 (Via Teleconference) - - PowerPoint PPT Presentation

Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow WASTEWATER COMMITTEE MEETING April 22, 2020 (Via Teleconference) CLICK TO EDIT MASTER TITLE STYLE AGENDA Opening Remarks A. Chairman/Executive


slide-1
SLIDE 1

Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow

WASTEWATER COMMITTEE MEETING April 22, 2020 (Via Teleconference)

slide-2
SLIDE 2

CLICK TO EDIT MASTER TITLE STYLE AGENDA

Opening Remarks

A. Chairman/Executive Director/Committee Champion Status Report concerning legislation and regulatory matters, budgets, current projects and ongoing Wastewater System programs of the District

2

slide-3
SLIDE 3

Agenda

AGENDA

Action Items

A. Consider Approval of Wastewater Committee Meeting Minutes – February 26, 2020 Recommend Approval of Wastewater Committee Meeting Minutes

3

slide-4
SLIDE 4

Agenda

AGENDA

Action Items

B. Authorize engineering services agreement for Panther Creek Wastewater Treatment Plant Expansion to 15 MGD – Administrative Memorandum No. 5555

  • Consider recommendation on authorizing execution of engineering

services agreement with HDR Engineering, Inc., in the amount of $5,364,255 for preliminary and final engineering design for Project No. 307-0493-18, Panther Creek Wastewater Treatment Plant Expansion to 15 MGD

What: Authorize an engineering services agreement for design of the Panther Creek Wastewater Treatment Plant (WWTP) Expansion to 15 million gallons per day (MGD) project. Why: Coordination efforts with the City of Frisco identified the need to expand Panther Creek WWTP from the current 10 MGD to 15 MGD annual average daily flow (AADF) capacity to support the city’s growth and population projections. The design includes a preliminary engineering evaluation to recommend improvements to increase the peak flow capacity from 30 MGD to 52.5 MGD.

4

slide-5
SLIDE 5

PANTHER CREEK WWTP EXPANSION TO 15 MGD

5

Background

  • Panther Creek WWTP serves the City of Frisco and constructed in two

phases in 2006 and 2009.

  • Current permitted discharge capacity of 10 MGD annual average daily

flow (AADF) and 30 MGD peak two-hour flow.

  • Coordination with the City of Frisco indicate an expansion to the

treatment plant is required due to population projections.

  • Flow data indicates the peak two-hour flows at the plant are expected

to increase from 30 MGD to 52.5 MGD and an evaluation is necessary to recommend improvements to store or treat the additional peak flow.

  • Existing electrical system cannot be expanded and a new medium

voltage power yard, distribution loop, and back-up power generation is needed to support this expansion and future expansions.

slide-6
SLIDE 6

PANTHER CREEK WWTP EXPANSION TO 15 MGD

6

slide-7
SLIDE 7

PANTHER CREEK WWTP EXPANSION TO 15 MGD

7

Engineering Services

  • Basic Services
  • Preliminary engineering evaluation of peak flow alternatives
  • Pre-selection for filter and disinfection equipment
  • Final plans, specifications, and estimates
  • Bid phase services
  • Construction phase services will be requested at a future date
  • Special Services
  • Topographical survey
  • Geotechnical investigation
  • Permitting fee allowance
  • Frisco collection system odor control study
  • The planning level construction cost estimate is $62,500,000
slide-8
SLIDE 8

Agenda

RECOMMENDATION

8

Consultant: HDR Engineering, Inc. Scope: Preliminary and Final Engineering Design Project:

  • No. 307-0493-18, Panther Creek WWTP Expansion to 15 MGD

Amount: $5,364,255

slide-9
SLIDE 9

Agenda

AGENDA

Action Items

C. Authorize engineering services agreement for Forney Mustang Creek Lift Station, Phase II, and Forney Force Main Improvements Project – Administrative Memorandum No. 5556

  • Consider recommendation on authorizing execution of engineering

services agreement with Hazen and Sawyer in the amount

  • f

$1,331,400 for final engineering design for Project No. 509-0561-20, Forney Mustang Creek Lift Station Phase II and Forney Force Main Improvements

What: Authorize an engineering services agreement for the final design of the Forney Mustang Creek Lift Station Phase II and the Forney Force Main Improvements. Why: The existing 24-inch force main is limiting the capacity of Forney Mustang Creek Lift Station to 12 million gallons per day (MGD). A new force main and expansion of the lift station to 30 MGD are needed to meet the growth projections of the City of Forney.

9

slide-10
SLIDE 10

FORNEY MUSTANG CREEK LS PH II & FORNEY FM IMPROVEMENTS

10

Background

  • The Forney Mustang Creek Lift Station is currently under construction

with a firm capacity of 12 MGD.

  • The existing 24-inch discharge force main conveys the flow to the

South Mesquite Creek RWWTP for treatment.

  • The City of Forney has requested to increase the capacity of the

Forney Mustang Creek Lift Station to 30 MGD to meet projected flows beyond 2030 due to growth in the service area.

  • A new 17,000 linear feet force main from the Forney Mustang Creek Lift

Station to the Buffalo Creek Lift Station is necessary to increase conveyance capacity to 30 MGD.

  • Planning level estimated construction cost is $14,700,000
slide-11
SLIDE 11

FORNEY MUSTANG CREEK LS & FORNEY FM IMPROVEMENTS

11

slide-12
SLIDE 12

FORNEY MUSTANG CREEK LS & FORNEY FM IMPROVEMENTS

12

Engineering Services

  • Basic Services
  • Preliminary design of pipeline
  • Final design of pipeline and upgrades to the lift station
  • Bid phase services
  • Construction phase services
  • Special Services
  • Topographic survey
  • Geotechnical investigation
  • Easement documents
  • National Environmental Policy Act (NEPA) clearance
  • Pipeline transient modeling
  • Odor modeling and odor control system design
slide-13
SLIDE 13

Agenda

RECOMMENDATION

13

Consultant: Hazen and Sawyer Scope: Final engineering design Project:

  • No. 509-0561-20, Forney Mustang Creek Lift Station Phase II

and Forney Force Main Improvements Amount: $1,331,400

slide-14
SLIDE 14

Agenda

AGENDA

Action Items

D. Authorize award of construction contract for Beck Branch Parallel Interceptor Improvements Project – Administrative Memorandum No. 5557

  • Consider recommendation on authorizing award of construction contract

to ARK Contracting Services, LLC, in the amount of $21,014.584 for Project No. 501-0439-16, Beck Branch Parallel Interceptor Improvements, Beck Branch Parallel Interceptor, Phase II, and Plano Spring Creek Force Main Parallel

What: Authorize award of a construction contract for the Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel portions of the Beck Branch Parallel Interceptor Improvements project. Why: Increase conveyance capacity from the Plano Spring Creek Lift Station No. 2 to the Rowlett Creek Regional Wastewater Treatment Plant to meet projected 2035 flow conditions due to population growth, inflow and infiltration in the cities of Plano and Richardson. Phase 1 of the Beck Branch Parallel Interceptor is currently under construction. This action will award construction of the final segments of the interceptor and force main to the lift station.

14

slide-15
SLIDE 15

BECK BRANCH PARALLEL INTERCEPTOR IMPROVEMENTS

15

Project Components

  • Beck Branch Parallel Interceptor, Phase I
  • Under construction by a separate contract
  • Along Los Rios Blvd. from Rowlett Creek RWWTP to Plano Parkway
  • Beck Branch Parallel Interceptor Phase II (this action)
  • 13,100 linear feet of 42-inch gravity interceptor
  • Along Plano Parkway from the intersection of Los Rios Blvd. to a

junction box east of K avenue

  • Plano Spring Creek Force Main Parallel (this action)
  • 4,900 linear feet of pressure rated 42-inch force main
  • Along PGBT (SH 190) from the junction box east of K avenue to the

Plano Spring Creek Lift Station No. 2

  • Includes replacement of 9 air release valves on the existing 36-inch

Plano Spring Creek Force Main

slide-16
SLIDE 16

BECK BRANCH PARALLEL INTERCEPTOR IMPROVEMENTS

16

slide-17
SLIDE 17

BECK BRANCH PARALLEL INTERCEPTOR IMPROVEMENTS

17

Tabulation of Bids

Bidder Base Bid Total Allowances Total Bid Recommendation ARK Contracting Services, LLC $20,869,584.00 $145,000.00 $21,014,584.00 Lowest responsible bid Recommended for Award McKee Utility Contractors, Inc. $25,805,000.00 $145,000.00 $25,950,000.00 Thalle Construction Company $26,607,935.00 $145,000.00 $26,752,935.00 S.J. Louis Construction

  • f Texas, Ltd.

$28,224,017.00 $145,000.00 $28,369,017.00 Mountain Cascade of Texas, LLC $29,692,580.00 $145,000.00 $29,837,580.00 BELT Construction, Inc. $35,399,359.00 $145,000.00 $35,544,359.00 ENGINEER’S OPINION OF PROBABLE COST $17,312,000.00

slide-18
SLIDE 18

BECK BRANCH PARALLEL INTERCEPTOR IMPROVEMENTS

18

Recommendation for Award

  • The Engineer and staff recommend acceptance of the lowest

responsible bid

  • Higher than expected costs are due to the work site restrictions

necessary to protect traffic, adjacent utilities, and roadway pavement in Plano Parkway that are not typical for NTMWD projects

  • r other projects of similar size.
  • Daytime work hours are between the morning and evening rush hour

which reduces the productivity rate and increases labor costs.

  • Some bidders proposed tunneling to mitigate work site restrictions,

but resulted in higher bids.

  • The low bidder, ARK Contracting Services was significantly lower than
  • ther bidders as their crews are flexible and available locally.
  • ARK’s proposal includes night work to improve productivity compared

to other bidders.

slide-19
SLIDE 19

Agenda

RECOMMENDATION

19

Contractor: ARK Contracting Services, LLC. (ARK) Scope: Construction Project:

  • No. 501-0439-16, Beck Branch Parallel Interceptor

Improvements, Beck Branch Parallel Interceptor Phase II and Plano Spring Creek Force Main Parallel Amount: $21,014,584.00

slide-20
SLIDE 20

Agenda

AGENDA

Action Items

E. Authorize legal services for Indian Creek Force Main No. 2 Project – Consent Agenda Item No. 20-04-04

  • Consider recommendation on authorizing legal services in the

amount of $20,000 with Saunders, Walsh & Beard, Attorneys & Counselors for Project No. 501-0454-17, Indian Creek Force Main No. 2

What: Authorize legal services with Saunders, Walsh & Beard, Attorneys & Counselors (SW&B) for the Indian Creek Force Main No. 2 project Why: Legal services to assist in determining the party(ies) legally responsible for the additional work created by the improper installation of the force main, as well as assisting in enforcing contractual rights against the responsible party(ies).

Executive Session

20

slide-21
SLIDE 21
  • Authorizes a government body to consult with its attorney in an

Executive Session to seek advice on legal matters regarding pending

  • r contemplated litigation or a settlement offer.
  • A government body may not invoke this Section to convene a closed

session and then discuss matters outside of that provision.

  • General discussion of policy, unrelated to legal matters, is not

permitted under the language merely because an attorney is present.

  • Items discussed during consultation with the District’s attorney are

privileged and should remain confidential.

EXECUTIVE SESSION

Section 551.071, Consultation with Attorney

21

slide-22
SLIDE 22

Agenda

RECOMMENDATION

22

Consultant: Saunders, Walsh & Beard, Attorneys & Counselors Scope: Legal Services Project:

  • No. 501-0454-17, Indian Creek Force Main No. 2

Amount: $20,000 Adjourn Executive Session

slide-23
SLIDE 23

Agenda

AGENDA

Discussion Items

A. Opportunity for Committee Members to Provide Feedback on Wastewater Committee Meeting

23

slide-24
SLIDE 24

CLICK TO EDIT MASTER TITLE STYLE AGENDA

Discussion Items

B. Opportunity for Committee Members to Request Potential Future Agenda Items

(No substantive discussion of items will take place at this time)

Adjournment

24