THE NTTF 2.3 SEISMIC WALKDOWNS OF US NPPS Lessons and Insights
SMiRT 22 Special Session
- n Seismic
reevaluation of
- perating US
NPPs based on NRC Fukushima Task Force Topics 2.1 & 2.3 August 2013
WALKDOWNS OF US NPPS operating US NPPs based on Lessons and - - PowerPoint PPT Presentation
SMiRT 22 Special Session THE NTTF 2.3 SEISMIC on Seismic reevaluation of WALKDOWNS OF US NPPS operating US NPPs based on Lessons and Insights NRC Fukushima Task Force Topics 2.1 & 2.3 August 2013 PRESENTATION TOPICS Background
SMiRT 22 Special Session
reevaluation of
NPPs based on NRC Fukushima Task Force Topics 2.1 & 2.3 August 2013
3
4
Ongoing Near term Long term 2.3 2.1 2.2 Walkdowns Hazard evaluation Risk evaluation Regulatory Actions 10 year update
Walkdowns to assure plants are meeting licensing basis and to look for potential seismic
equipment delayed until outages. Hazard evaluation due in 18 months for NPPs within the CEUS SSC model area. 3 years for western US NPPs performing SSHAC level 3
Risk results due 3-4 years after hazard. SMAs
allowed for all exceedances, but required for large exceedances. After receiving the information from the SPRA and SMA analyses, the NRC will determine appropriate regulatory actions. Rulemaking to require a reevaluation every 10 years. 11/2012 (+outages) 9/2013 (CEUS) 3/2015 (WUS) 3 years after hazard Depends on findings Rulemaking timeline
Based on the 50.54(f) letter:
5
¡ 50.54(f) RFI Letter issued March 12, 2012 ¡ Enclosure 3 Seismic Walkdowns “T “The walkdown will verify current plant conf configur iguration with the ation with the curre current lice nt licensing nsing basis, v basis, verify the rify the ade adequacy of curre quacy of current nt st stra rategies, maintenance plans, and identify degr degraded, ded, nonconf nonconform
ing, or una
naly lyzed zed conditions.” conditions.” ¡ The R2.3 seismic walkdowns provide a level of confidence in plant capabilities as new seismic hazard and risk assessment is ongoing.
6
§ EPRI 1025287 (SPRA) § NRC ISG JLD-ISG-2012-04 (SMA) § EPRI/NP-6041-SLR1 (SMA)
7
8
¡ As per 50.54(f) letter, report should include
eliminate or reduce them
potential vulnerabilities
§ Licensing basis reviews, CAP submittals
9
10
§ Specific attributes are listed in the guidance
§ Equipment Selection Personnel § Plant Operations Personnel
§ General support and asked to sign the SWEL along with the equipment selection personnel
§ Seismic Walkdown Engineers
§ Required to attend a (2 day) EPRI or (5 day) SQUG training on the guidance
§ Licensing Basis Reviewers § IPEEE Reviewers § Peer Reviewers
§ Minimum of 2 for each element, with one acting as lead reviewer and performing review of all elements as described in guidance
11
12
13
Figure 1-1 Figure 1-2
14
Figure 1-1 Figure 1-2
§ Variety of systems (examples in App E) § Major new or replacement equipment § Variety of types of equipment (list in App B) § Variety of environments § Equipment enhanced due to IPEEE program
¡ Sampling a pragmatic approach to limited time to conduct the walkdowns
15
16
17
18
19
20
21
22
Figure 1-3
23
24
25
26
27
and associated walk-bys
form independently and check against the licensees checklist. 28
29
Items submitted to LBR or CAP ~1900 Items submitted to CAP ~1700 Plants reported putting items directly into CAP and not performing LBEs ~70% Items closed out of CAP at time of reporting ~50% CAP items coming from area walk-bys versus equipment walkdowns ~50% Mean number of CAP items 19 Median number if CAP items 15
30
Equipment ¡Classifica1on # ¡Items % ¡of ¡Items # ¡of ¡NPPs ¡(of ¡104)
32 4% 26
60 7% ¡ 37
29 4% ¡ 21
10 1% ¡ 10
24 3% 17
54 7% 30
24 3% 19
44 5% 26
53 7% 41
24 3% 19
24 3% 21
13 2% 10
7 1% 5
2 <1% 2
Switches 43 5% 24
22 3% 15
42 5% 26
12 1% 9
57 7% 34 19 ¡Temperature ¡Sensors 5 1% 4
151 19% 52
71 9% 42
31
Issue ¡from ¡Walk-‑by # ¡Items % ¡of ¡Items # ¡of ¡NPPs ¡(of ¡104) Adverse ¡anchorage ¡condiMons 91 12% 42 Degraded ¡equipment/hardware ¡(examples ¡ are ¡missing ¡parts, ¡corrosion, ¡lighMng ¡fixture ¡ issues, ¡leaks) 158 21% ¡ 52 Seismic ¡interacMon ¡(spaMal, ¡fire, ¡flooding) 206 28% ¡ 57 Other ¡housekeeping ¡issues ¡(temporary ¡ installaMons, ¡portable ¡equipment) 136 18% ¡ 47 Cable/conduit ¡raceways ¡and ¡HVAC ¡ducMng 9 1% 7 Other ¡issues 14 2% 11 Nature ¡of ¡issue ¡idenMfied ¡during ¡the ¡walk-‑by ¡ could ¡not ¡be ¡determined ¡from ¡report 134 18% ¡
32
33
¡ CAP Corrective action program ¡ EPRI Electric power research institute ¡ IPEEE Individual Plant Examination for External Events ¡ NTTF Near term task force ¡ SFP Spent fuel pool ¡ SSEL Safe shutdown equipment list ¡ SWE Seismic walkdown engineers ¡ SWEL Seismic walkdown equipment list ¡ SQUG Seismic Qualification Utility Group ¡ TI Temporary instruction
34
35
¡ NTTF Report published July 2011 ¡ SECY-11-0124 recommended actions w/o delay - September 2011 ¡ SRM for SECY-11-0124 issued October 2011 ¡ SECY-11-0137 establishes prioritization of activities - issued October 2011 ¡ SRM for SECY-11-0137 issued December 2011 ¡ SECY-12-0025 authorizes 50.54(f) ¡ The 50.54(f) letter
§ Issued March 12, 2012 § To all operating power reactor licensees § Establishes a timeline and actions
¡ EPRI Guidance 1025286 issued May 2012