w m tpc update observa4ons discussion topics
play

W&M TPC update, observa4ons & discussion topics 15 Dec, - PowerPoint PPT Presentation

W&M TPC update, observa4ons & discussion topics 15 Dec, 2016 Jeff Nelson (Ciaran Buteux, Will Henninger, Mike Kordosky, Devin Moore, Marco Colo, and John Bensel) 12/15/16 1 The Al profiles arrived IMG_20161209_1405 16748 12/15/16


  1. W&M TPC update, observa4ons & discussion topics 15 Dec, 2016 Jeff Nelson (Ciaran Buteux, Will Henninger, Mike Kordosky, Devin Moore, Marco Colo, and John Bensel) 12/15/16 1

  2. The Al profiles arrived IMG_20161209_1405 16748 12/15/16 2

  3. Notes on the Al profiles • A number of the profiles have bends at the ends (below) – CuYng process? Don’t think shipping because the crate was in great shape (although carried under the driver arm when delivered) Laterally they fit nicely in the slots • They are a bit tall for the slots • – It takes force to put them in and they get scratches (right) The nuts and M4 hardware work nicely • Lighter is going to make installa4on in the 4ght space • much easier! The first 3 extrusions we pulled out 12/15/16 3

  4. Ground plane notes Stand by the my statement that these are • beau4ful! A couple small things • – Each part has a copper colored region on the side flange – We guess it was the welder connec4on; could get around that by using stainless sandwich for the connec4on between the welder clamp and the ground – Loca4on where the pla4ng seems to have been etched or tarnished – The bends for the sides are rounded a bit and you cannot snug them up 1-2mm level 12/15/16 4

  5. SloYng the ground planes • Since the holes (1/4”) are about the size of the perfora4ons, the holes had to be cuYng out sec4ons between the holes in most cases • Rotary tool and carbide tools for most holes – loud, but it works – Deburr the backsides aher ini4al cut 12/15/16 5

  6. APA cleaning Water aher first cleaning Tools of the trade • Water from first pass on insides of tubes (clockwise from upper right) • Deionized water tank – luckily can get bulk from Chemistry; straight tube brush • Cable brush pulled through the bent regions • Cleaning trough w/wash & rinse sides Four stage cleaning: • Rough clean with acetone – Could not get all marker off – some baked in welds • Alconox scrub – 100 passes min to get a white cloth to come up clean – Many hours of scrubbing each – Soak rinse • Simple green – Soak for 15 min – Scrub with brush/drill/cable brush • Flowing water rinse with agita4on • Flowed methyl rinse with agita4on Aher process op4mized 4 person days for final cleaning – Parts were two-person lihs 12/15/16 6

  7. Cleaned* mock APAs * Prior to final methyl wipe 12/15/16 7

  8. Divider chain notes • Make a quick connec4on set up for tes4ng divider chains (Mike/Marco) – All of the divider chains survived shipping • Aher talking to the Lariat crew (Kearns @ BU) they inly used a flux cleaner and not an ultrasounds for cleaning – Planned to adopt that program unless people object • That cleaning is happening today • Since moun4ng hardware has to change form M5 to M4 when the Al profiles, need to add a washer to the board-side connec4on 12/15/16 8

  9. Clean room geYng full – 4me to assembly 12/15/16 9

  10. Added CPA and placed on ground 12/15/16 10

  11. Add APAs The lower FC takes the load but don’t stop to admire un4l capture by top FC frames 12/15/16 11

  12. Add top FC (captures APAs) 12/15/16 12

  13. CPA-FC connec4on Temp hardware (will be M4 profile bolts) These inner most profiles will be bolted with shorter temp bolts for shipping and replaced in the pit 12/15/16 13

  14. Issue with 1 of 8 APA weldments causing alignment issues welded with outward angle; bent it => berer 12/15/16 14

  15. Tolerance build-up issue: floa4ng box beams should nest around CPA frame – too 4ght; Need to open up the gap today 12/15/16 15

  16. Add FC walls frames Notes • The missing pins are due to the set of offset holes– will mark and slot out the holes today now that we know the right spots in the full assembly • Also tolerance build-up issues with the box beam and APA connec4on. We will slot these slightly to make this work berer in the field • Part of this was the 4lted APA weldment but not all • Remember this will be bad ergonomics when sliding this between the cryostat wall and the TPC so make it work simply • Bolts on ends are stainless – metal OK there? • Structural so need to be metal… 12/15/16 16

  17. All but the top ground 12/15/16 17

  18. Top ground set in place 12/15/16 18

  19. Top ground set in place – planning to modify small center bits to fit new hanger block at FNAL when part in hand 12/15/16 19

  20. All together now… 12/15/16 20

  21. To-do list Today Through the weekend Make the fixes noted and Final soak and vacuum bake for • • reassemble fiberglass parts Photo op! Load profiles and divider chains • • Load profiles into one FC wall and Vacuum/Purge/Bag and over-bag • • look for deflec4on (Vic’s ask) parts Tag and bag parts as we Add travellers (bags opaque) • • disassemble Upgrade the failed ground plane • Cold test of APAs (for deflec4on crate (wall separated from base) • at midline) Monday Get lumber and make the FC • Loading crates • crates (2 of these) Tuesday Add endcaps to profiles • Ship! • 12/15/16 21

  22. APA to diver to ground connec4on 12/15/16 22

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend