visit to project allenby connaught by bondholders 15
play

Visit to Project Allenby/Connaught by Bondholders 15 March 2011 - PowerPoint PPT Presentation

Visit to Project Allenby/Connaught by Bondholders 15 March 2011 Programme 10:30 Arrive at Wellington House, Aldershot 10:45 - 12:15 Project briefing & presentation 12:15 - 13:15 Walking Tour of St Omer Barracks 13:15 - 14:00 Q & A


  1. Visit to Project Allenby/Connaught by Bondholders 15 March 2011

  2. Programme 10:30 Arrive at Wellington House, Aldershot 10:45 - 12:15 Project briefing & presentation 12:15 - 13:15 Walking Tour of St Omer Barracks 13:15 - 14:00 Q & A session and lunch 14:00 Close/Return to Farnborough 2

  3. Strategic Importance to MoD • The Project covers approximately 35% of Army UK Based Trained Manpower (20% of total manpower) • Salisbury Plain is the principle All Arms Manoeuvre Training Area in UK • The Project delivers two key objectives of the 1998 Strategic Defence Review: • Improving working and living accommodation • Identified as a major factor in morale, effectiveness, recruiting and retention • Providing accommodation for Units returning from Germany and reorganising within UK • 2nd Royal Tank Regiment in July 2007, a key deliverable which was met on time • 5 major units moving onto Salisbury Plain (2,500 soldiers) 3 Source: MOD

  4. 2010 Strategic Defence & Security Review • New Defence-wide organisation from April 2011 • Will include this contract, but detailed arrangements still to be determined • Means contract will no longer be answerable to Land Forces • Our joint intent is to ensure that well established working procedures are maintained • Detail of SDSR and its impact on the Project being considered 4

  5. Shared Purpose and Vision Purpose Together, MoD and Aspire will manage and deliver a modern, flexible living and working environment for soldiers in the Aldershot and Salisbury Plain area that will support military fighting power, enhance Army recruitment and retention and provide long-term value for the MoD and for Aspire Vision We will improve the quality of life of soldiers by delivering best in class service 5

  6. History • January 2002 Formed Aspire Joint Venture • 2002-2003 Bidding • July 2003 Selected as Preferred Bidder • January 2004 Pre-Contract Activities Letter – mobilised • April 2006 Financial Close • July 2006 Service Commencement • July 2007 2RTR delivered • 2014 Funding availability period • 2014 Construction complete • 2016 Benchmarking/market testing • 2041 End of contract 6

  7. 7 A 35 year contract to provide a service What is the Contract?

  8. 8 Project Locations

  9. Key Facts • £8Bn [£11.9Bn] 35 year PFI contract with Aspire Defence. • Construction Value £1.5Bn, Steady State Unitary Payment £240M pa • Provides living & working accommodation to 18,700 military personnel, with total dependency more that 21,000 • Originally 10 year, now 8 year construction phase. 375 new buildings and a further 192 refurbished. 457 buildings demolished • Previously 50+ support contracts. Aspire Defence Services manage/operate service provision – 50% self delivered 50% sub- contracted • Local Help Desks, available 24/7 365 days a year 9

  10. 10 Organisation and Structures

  11. Contractual Framework HSBC KBR Innisfree Carillion Infrastructure 45% 37.5% 12.5% 5% Aspire Defence Holdings 100% 100% Project Collateral Contract Aspire Defence Aspire Defence Lenders MoD The Authority Finance Limited Deed Services Works 50% 50% KBR KBR Subcontract Subcontract 50% KBR KBR Aspire Defence Services Aspire Defence 50% Capital Works Lifecycle Hard FM Lifecycle Lifecycle Hard FMSoft FM Hard FMSoft FM Soft FM Utilities Carillion Carillion Mowlem 50% Major FM Utilities Capital Works Utilities Infrastructure Upgrade Subcontract Sub-subcontracts Sub-subcontracts Service Subcontract Living Transport 11 Hard FM/some Soft FM Transport Thames Water/EDF Energy MUJV MUJV (Veolia/UKPNS Other Accommodation Other Sub Corus - Management Services (ADSL) (ADSL) Services( Sodexho ) Management ( Lex ) (Integrated Services & Works Utility) Sub-subcontractors (Babcock Land) (Sodexo)

  12. Working Relationships ADL ADS ADCW 12

  13. 13 Aspire Defence Capital Works

  14. Construction Overview • £1.5bn, 8 year construction programme • Construction of:- • large number low/medium rise low • not technically complex risk • but geographically spread accommodation • Management of Transition Programme key 14

  15. Three Pricing Categories • Firm, Fixed and Competed: • Firm – £481m • Fixed – uplifted for inflation/change in law – £296m • Competed – subject to benchmarking or competition in the market with agreed multiplier – £670m • Appropriate allocation of risk over 8 year construction period (2006 - 2014) 15

  16. Capital Works – number of units, by building type New Build, Demolished, 375 457 Refurbished/ Altered, 192 16

  17. Capital Works - building space by type and use Dining 13% Technical 21% Other Living 5% 61% 17

  18. Pre-Construction Progress to 31 January 2011 Scheme Design Reports Full Design Assets Completed, 512 Complete, 502 Assets to Remaining, 2 complete, 12 Planning Consents Procurement Granted, 366 Procured, 435 Remaining , 79 Required, 4 18

  19. Construction Progress to 31 January 2011 180 160 140 120 100 Assets 80 Remaining 60 In Progress 40 20 0 h d n l r t l e o t r w i r h o h o t o k s f s w l n u D r r a i e d B L m m d i T r l a a A Construction h W r e P AIS, 347 In Progress 61 Remaining 106 19

  20. Construction Summary • Construction not complex • Lessons learned/continuous improvement • Appropriate pricing risk – Firm, Fixed and Competed • Shorter programme • On programme • 65% complete 20

  21. 21 Aspire Defence Services

  22. Hard and Soft FM Services • £4.2bn over 35 years • Management and administration • Assets facilities maintenance • Living accommodation services • Transport services • Stores services • Office services • Welfare services • Support to security 22

  23. Services Support to Supply, Transport Living Management & Assets and Office Welfare Security and Equipment Accommodation Services Administration Facilities Services Services Support Services Services Performance Maintenance: Mailroom Leisure Security Weapons & Domestic Monitoring M&E Services Passes Ammunition Services Building Fabric Archiving Management QA Admin Grounds Civilian Reception Parking Space Ducting Admin and Catering Stores Management Helpdesk Civil Eng Clerical Vetting Furniture Fuel & Mess MIS Fixtures & Typing Lubricants Management Fittings HS&E PA Services Laundry & Dry Military Estate Cleaning Catering HR Management Media Services Tailoring Bar Services Reporting Pest Control Model Making Shoe Repairs Function Data Utilities Reprographics Services Management Maintenance & Travel Booking Management Visitor Fleet Management Cleaning Management Black – Self delivered Red – MUJV Waste Logistics Management Green – Sodexo Vehicle Blue – Babcock 23 Window Cleaning Servicing

  24. Direct Delivery/Sub-Contract Revenue – averages over years 1- 10 at Financial Close prices Sodexo, £28m ADSL, £54m VT Land, £9m MUJV, £13m 24

  25. Service Delivery • High customer satisfaction • 24/7 Help Desks successful • 100% of Retained Estate now in availability regime • 4 year transitional period has now ended • Minimal performance/availability deductions • 0.06% of revenue since FC • Changes in ownership in supply chain but no material impact • IiP accreditation (top 3%) 25

  26. 26 Lifecycle

  27. Lifecycle • ProjCo budgetary risk, except for utilities • Pre FC surveys and due diligence • Cyril Sweet pricing model:- • Gross Floor Area • Cost /m 2 • Age of building • E C Harris opinion as to adequacy 27

  28. Lifecycle Catering Equipment External Areas New & Refurbished Buildings FF&E Retained Buildings Total £613 million Real 2004 28

  29. Lifecycle • Post FC • Retained Estate (circa ⅓ of total) • Extensive surveys • 69 assets • 16 space types • Detailed pricing :- • Individual quantities • Cost per element • Remaining life of each component • Extrapolated 29 • Reconfirms adequacy of Retained Estate estimate

  30. Lifecycle 1,400 1,200 1,000 £M nominal 800 600 400 200 0 6 8 0 2 4 6 8 0 2 4 6 8 0 2 4 6 8 0 0 0 1 1 1 1 1 2 2 2 2 2 3 3 3 3 3 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 year 30 Estimate Actual

  31. 31 6 1 0 2 5 1 0 2 4 1 0 2 3 1 0 2 Actual 2 1 0 2 year Estimate 1 1 Lifecycle – early years 0 2 0 1 0 2 9 0 0 2 8 0 0 2 7 0 0 2 6 0 0 2 140 120 100 80 60 40 20 0 £M nominal

  32. 32 Financial

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend