Victorian Renewable Energy Target 2017 Auction Industry Information - - PowerPoint PPT Presentation

victorian renewable energy target 2017 auction industry
SMART_READER_LITE
LIVE PREVIEW

Victorian Renewable Energy Target 2017 Auction Industry Information - - PowerPoint PPT Presentation

Victorian Renewable Energy Target 2017 Auction Industry Information Session Agenda Agenda Item Presenter 08:30 09:00 Tea and coffee - 09:00 09:10 Welcome and session introduction Simon Corbell 09:10 09:20 Auction overview Paul


slide-1
SLIDE 1

Victorian Renewable Energy Target 2017 Auction Industry Information Session

slide-2
SLIDE 2

2

Agenda

Agenda Item Presenter

08:30 – 09:00 Tea and coffee

  • 09:00 – 09:10

Welcome and session introduction Simon Corbell 09:10 – 09:20 Auction overview Paul Smith 09:20 – 09:50 Key contract features Matt Dickie 09:50 – 10:20 Questions Panel 10:20 – 10:50 Morning tea

  • 10:50 – 11:05

Eligibility / Evaluation Matt Dickie 11:05 – 11:20 Community engagement and benefit sharing Katrina Hermann 11:20 – 11:35 Economic development / VIPP Athena Andriotis 11:35 – 12:05 Questions Panel 12:05 – 12:15 Session recap and next steps Simon Corbell 12:15 Information session concludes

  • 12:15 – 13:00

Lunch

slide-3
SLIDE 3

Auction Overview

Paul Smith Deputy Secretary Energy, Environment and Climate Change

slide-4
SLIDE 4

4

  • The Renewable Energy (Jobs and Investment) Act 2017 (Vic) sets the

Victorian Renewable Energy Targets (VRET) into legislation:

– 25% renewable energy generation by 2020, and, – 40% renewable energy generation by 2025

  • In Victoria, by 2025, the VRET will result in up to:

– 10,000 jobs – $7.2 billion in new capital expenditure – $2.1 billion in additional economic activity

Auction Context

slide-5
SLIDE 5

5

  • The 2017 VRET Reverse Auction was officially opened on 14

November 2017, and will:

– deliver up to 650 MW (389,000 households), – incentivise up to $1.3 billion of investment – create 1,250 construction jobs over two years and 90 ongoing jobs

  • The auction offers long term Support Agreements (contracts) to

proponents, to create the investment certainty required to build new energy generation capacity. Auction Context

slide-6
SLIDE 6

6

  • The design of the auction has been informed by extensive

public and industry consultation by DELWP since the VRET targets were first announced in June 2016. Auction Context Auction Design

Commercial & Legal Advice VRET Scheme Stakeholder Consultation Paper June 2016 Summary Report of VRET Stakeholder Submissions December 2016 Industry Consultation Workshops 2016

slide-7
SLIDE 7

7

Auction Design

  • Bids for this competitive reverse auction from renewable energy

projects are submitted under a formal Request for Proposal (RFP) process on tenders.vic.gov.au

  • Successful proposals will be awarded a Support Agreement

(contract) with the State of Victoria, providing financial support

  • ver a 15-year period.
  • RFP opened 14 November 2017
  • Proponents can request further information on the auction until 31

January 2018.

  • The RFP will give proponents 3 months to submit their proposals,

closing on 14 February 2018. Evaluations will begin the next day.

  • It is estimated that successful proponents will be notified in July

2018.

slide-8
SLIDE 8

8

Auction Design

  • Under the Support Agreement, successful

proponents will be paid through a Hybrid payment mechanism, which is a mix of a fixed Base Amount and a variable Contract-for-Difference payment (CfD).

  • Proponents to bid the minimum Base Amount

payment ($/MW/year) and minimum Payment Cap ($) in two scenarios:

– LGCs transferred to State – LGCs retained by proponent

slide-9
SLIDE 9

9

  • 550 MW of large scale renewable energy

generating systems based on wind, solar or other energy sources declared by the Minister.

  • 100 MW of large-scale solar-specific renewable

energy.

  • 13 mandatory eligibility criteria.
  • 5 evaluation criteria, that will assess value for

money of each proposal, in conjunction with bid prices. Auction Design

slide-10
SLIDE 10

Thank you

Paul Smith Deputy Secretary Energy, Environment and Climate Change

slide-11
SLIDE 11

Key Contract Features

Matt Dickie Director Renewable Energy Division

slide-12
SLIDE 12

12

Payment Mechanism

  • Successful proponents will be awarded a Support Agreement (contract)

with the State and paid through a Hybrid payment mechanism

  • Contract-for-Difference (CfD)
  • State will set the CfD ‘strike price’ in $/MWh of eligible electricity

generated

  • Two way payment mechanism, paid monthly in arrears
  • Base Amount
  • Proponents bid for this component to be paid by the State to the

Supplier on an annual basis ($/MW/Year)

  • Payment Cap
  • All projects will be subject to a project specific cap which applies to

the CfD and the Base Amount payments

  • Proponents bid for this component
slide-13
SLIDE 13

13

Contract-for-Difference

State pays proponent Proponent pays State

Floor price

How a Contract-for-Difference works

slide-14
SLIDE 14

14

  • Strike Price (referred to as ‘Contract Price’ in the

RFP) as set for eligible technologies:

– $56.52/MWh for wind projects; – $53.06/MWh for fixed plate solar projects; and – $56.85/MWh for single axis tracked solar projects.

  • Floor Price of $0/MWh.

Contract-for-Difference

slide-15
SLIDE 15

15

  • The Base Amount payment is a set price paid annually over

the life of the contract

  • Proponents will bid for this component in the form of

$/MW/year

  • The Base Amount payment is conditional on the facility having

met availability thresholds over the year: – 90% of nameplate capacity for wind projects – 95% of nameplate capacity for solar projects

Base Amount Payment

slide-16
SLIDE 16

16

  • All projects will be subject to a project-specific Payment Cap.
  • Once a project’s Payment Cap is reached, no further Support

Payments will be made by the State to that project until any net CfD payments made to the State result in the cumulative net amount paid being below the Payment Cap.

  • The CfD payment component will continue to be calculated

each month, and if the cumulative payments return to be below the cap, then payment from the State to proponents will resume.

  • Proponents are asked to bid the minimum Base Amount and

Payment Cap they would require to support their project.

Payment Cap

slide-17
SLIDE 17

17

  • Proponents bid the minimum Base Amount

payment ($/MW/year) and minimum Payment Cap ($) in two scenarios:

– 100% of LGCs transferred to State – 100% of LGCs retained by proponent

  • The State will select the option that presents the

best value for money Large-Scale Generation Certificates

slide-18
SLIDE 18

18

Support Agreement scope

  • Term

– A Support Agreement will be for a length of 15 years under the 2017 auction – The anticipated supply date will be a date prior to 30 September 2020, agreed between the State and the Supplier during the tender process

  • Commitments made under the VIPP and the Major

Projects Skills Guarantee will form a part of the Support Agreement Support Agreement

slide-19
SLIDE 19

19

  • The Support Agreement contains a number of

Conditions Precedent that must be satisfied, including:

– the State accepting the Supplier's Safety, Health & Environment Plan, Communications and Community Engagement and Benefit Sharing Plan, and Industrial Relations Management Plan; – The Supplier providing a Security to the State – the occurrence of financial close under the supplier’s financing documents.

  • Suppliers have 6 months to satisfy conditions

precedent Conditions Precedent

slide-20
SLIDE 20

20

  • The Supplier is obliged to meet the key Project

Milestones by specified Milestone Dates

  • The key Milestones are:

– financial close; – submission of a draft Safety Health & Environment Plan, Community Engagement and Benefit Sharing Plan and Industrial Relations Management Plan; – commencement of construction; and – execution of the Connection Agreement.

Project Milestones

slide-21
SLIDE 21

21

  • If there is a change in law which increases or

reduces the costs incurred or to be incurred by the supplier, the supplier is entitled to pass through 50% of the additional costs, and must pass through 50% of the reduced costs, as an adjustment to the Contract Price or the Base Amount.

  • This sharing mechanism is subject to a threshold of

$500,000

  • The Support Agreement also contemplates:

– Repeal/amendment of the Federal RET – no change – NEM Design Changes – good faith negotiations – Market Disruption Events – good faith negotiations

Change in Law

slide-22
SLIDE 22

Questions?

Matt Dickie Director Renewable Energy Division

slide-23
SLIDE 23

Eligibility and Evaluation Criteria

Matt Dickie Director Renewable Energy Division

slide-24
SLIDE 24

24

Proponent Eligibility Criteria

  • The eligibility criteria are designed to guarantee the capacity of

generating systems, and a minimum standard of proponent and project quality and viability

  • 13 eligibility criteria in total
  • Proponents must comply with all of the eligibility criteria
slide-25
SLIDE 25

25

Proponent Eligibility Criteria

EL 1: The proponent must be a non-tax exempt Australian company or subsidiary under the Corporations Act 2001 (Cth) or a wholly or majority owned Commonwealth or Australian state or territory government body. EL 2: The proponent must propose one contracted entity to be legally responsible for the proponent’s proposal and Support Agreement. EL 3: The proponent and/or the contracted entity must not be, or become, bankrupt, insolvent, or be in, or enter into, administration, receivership or liquidation, or take advantage of any statute for the relief of insolvent debtors at any time during the RFP process. EL 4: The proponent and/or the contracted entity must not have had a judicial decision relating to employee entitlements made against it (not including decisions under appeal) and not have paid the claim. EL 5: The proponent and/or the contracted entity must not have been named as an

  • rganisation that has not complied with the Workplace Gender Equality Act 2012 (Cth).
slide-26
SLIDE 26

26

Project Eligibility Criteria

EL 6: The proposal must be for a facility with a renewable energy generating system based on wind, solar or other energy sources declared by the Minister. EL 7: The proposal must be for a facility which establishes a single generating system that is able to qualify as a ‘large-scale’ renewable energy project under the Renewable Energy (Electricity) Act 2000 (Cth), and therefore be eligible to create and register LGCs. The capacity must be as determined at its point of connection to the NEM.

slide-27
SLIDE 27

27

EL 8: The facility in the proposal must:

  • be no less than 10 MW nameplate capacity at its point of

connection to the interconnected national electricity system;

  • have already registered, or have commenced registration

with AEMO, as an Intending Participant or as a Registered Participant; and,

  • have submitted a complete Connection Application to the

connecting Network Service Provider, including completed grid connection studies.

EL 9: The proposal must be for a new facility.

Project Eligibility Criteria

slide-28
SLIDE 28

28

EL 10: The proposal must be for a facility that is able to commence commercial operations in, or prior to, September 2020. EL 11: The proposal must be for a facility with a live planning permit from the relevant authority. EL 12: The proposal must be for a facility whereby a minimum of 10% of the Project Total Estimated Labour Hours, will be undertaken by Apprentices, Trainees, or Engineering Cadets under the Major Projects Skills Guarantee (MPSG). EL 13: The proposal must demonstrate local community support by satisfying the standards of the ‘involve’ spectrum level of engagement as described in the Community Engagement and Benefit Sharing Guide.

Project Eligibility Criteria

slide-29
SLIDE 29

29

  • The State intends to evaluate correctly submitted proposals, that

comply with all the Eligibility Criteria.

  • Key considerations in the State’s evaluation of proposals to determine

best value for money for the State will include:

– Bid prices with and without LGCs for:

1. the Base Amount, and 2. the Payment Cap.

– Performance against five Evaluation Criteria.

Project Evaluation

slide-30
SLIDE 30

30

  • Proponents must make a price bid by submitting a

completed Proponent Information Form, to reflect each

  • f the following:

– in the case that LGCs are transferred to the State:

1. Base Amount ($/MW/year – 30 June 2017) 2. Payment Cap ($ – 30 June 2017)

– in the case that LGCs are retained by the proponent:

1. Base Amount ($/MW/year – 30 June 2017) 2. Payment Cap ($ – 30 June 2017)

  • In the reverse auction, lower price bids will be favoured.
  • The State also retains the right to select its preferred

LGC treatment pathway for each proposal.

Bid Prices

slide-31
SLIDE 31

31

Evaluation Criteria

Number Criteria Weighting EV1 Financial capability and commercial viability 25% EV2 Technical capability and viability 25% EV3 Economic development 25% EV4 Community engagement and shared benefits 15% EV5 Impact on existing electrical network infrastructure 10%

  • While bid prices are a primary variable in the State’s

determination of value for money, the State requires other important factors to be considered in order to properly address the wider objectives of this scheme – this is achieved through evaluation of each proposal against the five criteria below.

slide-32
SLIDE 32

32

  • This criterion accounts for:

– progress in obtaining required financial approvals, – the financial capacity of the proponent, – the funding strategy to deliver the project.

  • It looks at the proponent’s detailed financial modelling, using the

financial spreadsheet template provided as part of the RFP. EV1 – Financial Capability and Commercial Viability

slide-33
SLIDE 33

33

  • This criterion evaluates all aspects of the Project’s technical

specifications with a view to determining its technological viability.

  • This will include all technology used, forecast production,

maintenance plans, and technical risk.

  • What is the feasibility of the project completing construction and

starting on time? EV2 – Technical Capability and Viability

slide-34
SLIDE 34

34

  • This criterion measures a proposal’s contribution to economic

development in Victoria and the renewable energy industry.

  • It will assess the positive impact of a project on the economic

development of services and manufacturing industries, regional development, demonstrable development of supply chains and broader economic benefits, such as headquarter locations, job growth and research and innovation activities. EV3 – Economic Development

slide-35
SLIDE 35

35

  • 1. Major Projects Skills Guarantee (MPSG)

Proponents are required to submit an MPSG Compliance Plan. The MPSG mandates that at least 10% of work carried out on Victoria’s major projects, valued at more than $20 million, must be undertaken by apprentices, trainees or engineering cadets. The 10% requirement applies to contract works in their entirety and extends to all of the works specified as part of contracts for those projects. Projects will be scored higher if they can exceed the 10% requirements.

  • 2. Local Investment Plan (LIP)

Proponents should submit a Local Investment Plan using the Local Investment Guide provided as part of the RFP, outlining their commitment and approach to increasing capital investment in the renewable energy industry, manufacturing and associated industries in Victoria, outside of the renewable energy facility bid into the auction.

EV3 – Economic Development

slide-36
SLIDE 36

36

  • 3. Victorian Industry Participation Policy (VIPP)

Proponents are required to provide a Local Industry Development Plan (LIDP) complying with VIPP Strategic Project Framework. Strategic Projects are projects with a total project value of $50 million or more, excluding maintenance and operational

  • costs. Strategic Projects are subject to rigorous local content requirements to help drive

additional economic activity and jobs. To assess how a Project will meet VIPP’s requirements, proponents will be required to attempt and meet local content figures of 64% for wind and solar projects. Projects will be scored higher if they can exceed the local content figure.

EV3 – Economic Development

slide-37
SLIDE 37

37

  • This criterion measures a proposal’s community engagement and will

be assessed against a best-practice approach that builds relationships with local communities and meaningfully empowers communities to participate in and shape a project’s development, construction and operation.

  • Shared benefits will be assessed on the project’s approach to the

distribution of financial benefits.

  • Proponents must submit documents as outlined in the Community

Engagement and Benefit Sharing in Renewable Energy Development – A Guide for Renewable Energy Developers EV4 – Community Engagement and Shared Benefits

slide-38
SLIDE 38

38

  • This criterion evaluates projects on their impact on transmission

networks and favours minimal direct and indirect transmission network connection and augmentation costs.

  • Where appropriate, projects that also assist with grid stability, grid

reliability, and network and energy security will be favourably evaluated. EV5 – Impact on Existing Electrical Network Infrastructure

slide-39
SLIDE 39

Thank you

Matt Dickie Director Renewable Energy Division

slide-40
SLIDE 40

Community Engagement and Benefits Sharing

Katrina Hermann Manager, VRET Implementation Renewable Energy Division

slide-41
SLIDE 41

41

Why embed community engagement into VRET criteria?

  • Best practice community engagement and benefit sharing are

fundamental to generating community support;

  • it puts local communities at the centre of decisions that impact

them and builds trust;

  • the Government wants to be assured that successful projects

work with neighbours and the community, and understand local priorities;

  • it mitigates significant opposition

to a project; and

  • it minimises potential delays

caused by a loss of ‘social acceptance.’

Community Engagement and Benefit Sharing

slide-42
SLIDE 42

42

Community engagement is both an eligibility AND evaluation criteria

  • The eligibility requirement ensures

projects achieve a level of engagement necessary to mitigate an unacceptable level of ‘social’ risk

  • The evaluation criteria provides a

mechanism to reward projects that perform beyond the eligibility requirement Eligibility criteria The proponent must first meet a minimum level of engagement associated with the ‘Involve’ spectrum - as outlined in Table 1 (page 9) of the Guide

VRET Eligibility and Evaluation Criteria

slide-43
SLIDE 43

43

Table 1: Spectrum of Approaches to Community Engagement

slide-44
SLIDE 44

44

Table 1: Spectrum of Approaches to Community Engagement

slide-45
SLIDE 45

45

Table 1: Spectrum of Approaches to Community Engagement

slide-46
SLIDE 46

46

Evaluation criteria (EV4)

  • 1. Assesses the project’s approach to community engagement during

planning, construction and operation, over and above the eligibility criteria.

  • 2. Assesses how the project’s ‘financial’ benefits will be shared with

local and regional communities, over and above the eligibility criteria. Note: ‘financial’ includes in-kind contributions Four separate documents must be submitted (EL13)

  • 1. Social Risk Analysis
  • 2. Community Engagement Strategy
  • 3. Benefit Sharing Program
  • 4. Reporting, Monitoring and Evaluation Plan
  • 5. (optional) Letters of support, including community support

VRET Evaluation Criteria (EV4)

slide-47
SLIDE 47

47

Required Documentation (Part C of Guide)

  • 1. Social Risk Analysis
  • Context narrative – key aspects of local demographics, culture

and history

  • Social impact site map – generator location/s and associated

infrastructure in relation to local residents and the community

  • Social risk matrix – key social risks and mitigation strategies
  • Stakeholder mapping spreadsheet – identifies relevant

stakeholders etc. Designed to help developers with their own

  • planning. Remove private information for Government version.
slide-48
SLIDE 48

48

  • 2. Community Engagement Strategy – includes:

Required Documentation

  • possible engagement

activities by project phase

  • tailoring to the local context
  • starting engagement early in

the development process

  • community participation in

decision-making and design (fair process)

  • face-to-face interactions
  • complaint management

system.

slide-49
SLIDE 49

49

  • 3. Benefit Sharing Program
  • Requires a fair process that is tailored to the local context and scale
  • The Guide does not specify an approach – it’s up to the developer to

design it with their local community Key Issue: neighbourhood agreements should not void people’s rights to object or raise concerns

Required Documentation

  • Done correctly it can help build

support

  • Aims to provide flexibility e.g.

community funds, local procurement, neighbourhood payments, beyond compliance activities and employee volunteerism

Coonooer Bridge Wind Farm, Victoria

slide-50
SLIDE 50

50

  • 4. Reporting, Monitoring and

Evaluation Plan

  • refer to Part C, Section 4
  • 5. Optional letters of support,

including community support

Required Documentation

World’s largest turbine (credit: LM Power)

slide-51
SLIDE 51

51

Victorian Government does not expect:

  • the developer to do everything the community asks for; or
  • adopt an approach that is not balanced against other priorities, i.e.

value for money Practical approach

  • Despite the requirement to submit formal documents:

– they are designed to capture the activities many developers already do; and – they assist Government to assess different bids more transparently.

  • the key is to demonstrate understanding, consideration and response

to neighbours’ and host community’s priorities; and

  • demonstrate that these priorities have been considered across the

project life cycle.

Closing Remarks

slide-52
SLIDE 52

52

The following entities have endorsed the Guide:

Endorsement

slide-53
SLIDE 53

Thank you

Katrina Hermann Manager, VRET Implementation Renewable Energy Division

slide-54
SLIDE 54

Manufacturing Priorities and VIPP

Victorian Renewable Energy Target RFP Industry Information Session

28 November 2017

slide-55
SLIDE 55
  • 3rd largest industry in Australia - all major

Australian construction companies have

  • perations in Victoria
  • 3rd largest employer
  • Largest industry for R&D spending
  • Continue to grow into the future:

–State Government investments of over $38 billion in new infrastructure projects –Stream of private capital investments - $678 million in 2017 (20% increase from 2016)

Victoria’s Manufacturing Industry - overview 283,000 jobs

  • r 9% of Victoria’s

workforce

$25.9 billion value to the State or

7.5% of GSP

slide-56
SLIDE 56
  • Create new jobs and stimulate industry investment in high growth,

high value industries

Victoria’s priority industries and sectors

slide-57
SLIDE 57

Ensuring local SMEs are given a full and fair

  • pportunity to compete for government

contracts, while still achieving value for money:

– Creating local opportunities and building supply-chain capabilities – Over 72 VIPP Strategic Projects confirmed since December 2014 – include minimum local content requirements – Reforms introduced over last 2 years to strengthen VIPP Policy (DEDJTR) – www.economicdevelopment.vic.gov.au/victorian-industry- participation-policy Industry Capability Network (ICN) – www.icn.org.au/content/victoria/vipp

Victorian Industry Participation Policy

slide-58
SLIDE 58

Local content for VRET projects

Minimum local content requirements set by government:

64% for renewable energy facilities, including 90% steel products from locally milled steel 90% during operations phase

First auction delivering renewable energy and local industry opportunities:

– up to $1.3 billion of investment – create 1,250 construction jobs – stimulate manufacturing supply chain opportunities and jobs – create ongoing jobs.

slide-59
SLIDE 59

Local Industry Development Plan (LIDP) – reflecting the supply chain

Local Content commitments – VRET – current round

  • Minimum local content requirements
  • Local steel
  • Jobs, including apprentices and trainees

Identifying local products and capabilities

  • Industry consultation process
  • Alerting local industry
  • Liaising with international suppliers to engage locally

Assessing local products & capabilities with overseas equivalent Product or service selection policy or procedure Monitoring and reporting Statement of compliance / Statutory Declaration

slide-60
SLIDE 60

Engaging with Victoria’s supply chain – Industry Capability Network

To register: https://gateway.icn.org.a u/

  • Identifies local capability, products and

services

  • Evaluates ANZ value-added activity

commitments made in LIDPs

  • Monitors and reports on outcomes for

Victorian industry involvement

  • Links principal contractors and local

suppliers:

  • Liaising with bidders to identify local goods &

services

  • Local supplier advertising on ICN Gateway
  • Assisting bidders to complete their LIDP.
slide-61
SLIDE 61
  • Future Industries

Manufacturing Program

  • Sector Growth Program
  • New Energy Jobs Fund

Supporting industry growth – key funding initiatives

  • Local Industries Fund

for Transition

Metropolitan

  • Annick Pascal - CBD
  • David Hunter - West
  • Natasha Twigg - North
  • Bev Lyttle - East
  • Matthew McKean – South East

Regional

  • Kushiel Prasad - Geelong
  • Nigel Harper - Warrnambool
  • Ray Hortle - Hume
  • Tim McAuliffe - Gippsland
  • Carly Grigg - Loddon Mallee
  • Scott White - Grampians

DEDJTR contacts:

slide-62
SLIDE 62

Questions and Discussion

Thank you. Athena Andriotis A/Executive Director, Advanced Manufacturing Department of Economic Development, Jobs, Transport & Resources athena.andriotis@ecodev.vic.gov.au

slide-63
SLIDE 63

Session Recap and Next Steps

Simon Corbell Victoria’s Renewable Energy Advocate

slide-64
SLIDE 64

Thank you

Victorian Renewable Energy Targets – 2017 Reverse Auction