variable renewable energy integration and planning
play

Variable Renewable Energy Integration and Planning Results of Task - PowerPoint PPT Presentation

Public Disclosure Authorized Variable Renewable Energy Integration and Planning Results of Task 1: Dispatch Diagnosis & Task 2: Demand & Generation Forecast Analysis Public Disclosure Authorized Stakeholder Dissemination Event


  1. Public Disclosure Authorized Variable Renewable Energy Integration and Planning Results of Task 1: Dispatch Diagnosis & Task 2: Demand & Generation Forecast Analysis Public Disclosure Authorized Stakeholder Dissemination Event Islamabad, April 4, 2019 Public Disclosure Authorized x Confidential Public Restricted Internal A company of Public Disclosure Authorized

  2. OVERVIEW Task 1 Dispatch Diagnosis Chapter 1 Presentation of results and open discussion Task 2 Demand and Generation Forecast Analysis Chapter 2 Presentation of results and open discussion 2

  3. Comparison Approach Task 1 versus Task 2 Background: Task 1 and 3 follow different approaches due to different base and purpose VRE Modelling, Task Outcome input optimization For both generation profiles PLEXOS with existing and - Dispatch observing constraints / costs committed system Task 1: Fixed wind and Least-(variable) cost to serve - Technical and commercial constraints Dispatch PV shares demand for one year (2017, 2022) - Implications for variable costs of overall (5, 10, 14 GW…) system → variable cost reduction due to Analysis No: capex, expansion transmission (2017 & 2022) VRE Task 3: Cost assumptions Least-(all) cost for demand of 22 - Expansion paths generation sources Expansion Expansion years - Focus: VRE shares → optimal (least-cost) expansion with Exercise constraints All capex, transmission (up to 2040) (e.g. annual (but only links between zones) given assumptions for given scenarios** Expansion all sources (candidates) limits)* within limits* * Reducing complex regulatory/market frame for VRE to a set of parameters **Note: A fully fledged master plan would consider many more scenarios / sets of assumptions 3

  4. Task 1: Dispatch Diagnosis Task 1: Dispatch Diagnosis Chapter 1 Presentation of results and open discussion ▪ Results of Dispatch Simulation ▪ Results of Scenario Analysis ▪ Dispatch Constraints for the Integration of VRE 4

  5. Comparison of Energy Mixes Base Case (2.5 GW wind, 1.3 GW PV) 10 GW Case (5 GW Wind, 5 GW PV) Energy Mix Energy Mix PV, 1.3% PV, 4.8% STs, 6.6% STs, 6.4% Wind, 4.3% Wind, 8.3% Bagasse, 4.0% Bagasse, 3.6% CCGTs, 29.8% HPPs, 24.9% CCGTs, 32.7% HPPs, 24.8% CC DGUs, 0.0% Coal PPs, 17.5% CC DGUs, 0.1% DGUs, 0.0% Coal PPs, 13.5% DGUs, 0.0% Nuclear, 8.7% Total generation: 172.8 TWh Nuclear, 8.7% Total generation: 172.8 TWh 5

  6. Dispatch Comparison: Winter Base Case (2.5 GW wind, 1.3 GW PV) 10 GW Case (5 GW Wind, 5 GW PV) Bagasse Coal PPs Nuclear CCGTs OCGTs STs Gas engines HPP VRE CC DGUs 6

  7. Dispatch Comparison: Summer Base Case (2.5 GW wind, 1.3 GW PV) 10 GW Case (5 GW Wind, 5 GW PV) Bagasse Coal PPs Nuclear CCGTs OCGTs STs Gas engines HPP VRE CC DGUs 7

  8. Reserves Overview Secondary Primary Contingency Reserve Reserve Reserve e e • 30 sec • 15 sec • 10 sec Response: • 30 min e e • 30 min • 30 sec e • 5 min • scheduled Duration: • • • • • • • • • • 1/3 largest unit • • • 1/3 largest unit • • • Largest unit • Capacity: • • • • • • • • • • • • • • 200 MW • • 200 MW 600 MW • • • • • • • • • • • • • • • Requirement will pass to 367 MW (1,100 MW), when Karachi Coastal Nuclear will be online by the end of 2021 8

  9. Reserve Constraints: Secondary Reserve Secondary Reserve Requirement 500 450 400 Reserve Requirement [MW] 350 300 250 200 150 100 50 0 1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121 126 131 136 hour SecRes SecRes_SizInc SecRes_Wind SecRes_PV Secondary ResReq = ( 1 3 𝑇𝑗𝑨𝑗𝑜𝑕 _ 𝐽𝑜𝑑𝑗𝑒𝑓𝑜𝑢 ) 2 + 𝑋𝑗𝑜𝑒 _ 𝑆𝑓𝑡𝑆𝑓𝑟 𝑡𝑓𝑑−𝑛𝑗𝑜 ² + 𝑄𝑊 _ 𝑆𝑓𝑡𝑆𝑓𝑟 𝑡𝑓𝑑−𝑛𝑗𝑜 ² 9

  10. Reserve Constraints: Contingency Reserve Contingency Reserve Requirement 1400 1200 Reserve Requirement [MW] 1000 800 600 400 200 0 1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121 126 131 136 hour ContRes ContRes_SizInc ContRes_Wind ContRes_PV Contingency ResReq = 𝑇𝑗𝑨𝑗𝑜𝑕 _ 𝐽𝑜𝑑𝑗𝑒𝑓𝑜𝑢 2 + 𝑋𝑗𝑜𝑒 _ 𝑆𝑓𝑡𝑆𝑓𝑟 𝑆𝑓𝑕𝑣𝑚𝑏𝑢𝑗𝑝𝑜 ² + 𝑄𝑊 _ 𝑆𝑓𝑡𝑆𝑓𝑟 𝑆𝑓𝑕𝑣𝑚𝑏𝑢𝑗𝑝𝑜 ² 10

  11. Reserve Constraints: Primary Reserve Shortfall Shortfall Provision No large change between Base Case and 10 GW Case 11

  12. Reserve Constraints: Primary Reserve Provisioning Bagasse Coal PPs Nuclear CCGTs OCGTs STs Gas engines HPP VRE CC DGUs No large change between Base Case and 10 GW Case 12

  13. Reserve Constraints: Secondary Reserve Base Case Shortfall 2.5 GW Wind 1.3 GW PV Shortfall Provision 10 GW Case Provision 5.0 GW Wind 5.0 GW PV 13

  14. Reserve Constraints: Fuel Contracts Variable Generation Costs [MUSD] Category with Fuel without Fuel difference Contracts Contracts STs 2,119.1 2,137.4 18.3 0.9% CC DGUs 20.5 21.2 0.7 3.5% DGUs 4.9 5.3 0.4 8.7% Gas engines 0.1 0.1 0.0 3.0% CCGTs 4,822.6 4,615.5 -207.1 -4.3% Nuclear 134.2 134.2 0.0 0.0% Coal PPs 1,516.5 1,588.4 71.9 4.7% 8,617.9 8,502.2 TOTAL -115.7 -1.3% Simulations for 2022 have shown that without fuel contracts the around 116 MUSD could be saved. 14

  15. Task 1: Dispatch Diagnosis Task 1: Dispatch Diagnosis Chapter 1 Presentation of results and open discussion ▪ Results of Dispatch Simulation ▪ Results of Scenario Analysis ▪ Dispatch Constraints for the Integration of VRE 15

  16. Scenario Analysis: Analysed Cases Installed Capacity [MW] Cases PV Wind Total VRE Base 1,286 2,450 3,736 3 GW each 3,000 3,000 6,000 5 GW each 5,000 5,000 10,000 7 GW each 7,000 7,000 14,000 9 GW each 9,000 9,000 18,000 11 GW each 11,000 11,000 22,000 Bagasse capacity: 1,300 MW within all cases 16

  17. Scenario Analysis: Energy Mix Energy Mix per scenario 200,000 HPPs 180,000 STs 160,000 Generation [GWh] Nuclear 140,000 Coal PPs 120,000 CCGTs 100,000 CC DGUs 80,000 DGUs 60,000 PV 40,000 20,000 Wind 0 Bagasse Base 3 GW each 5 GW each 7 GW each 9 GW each 11 GW each 17

  18. Scenario Analysis: Generation per Scenario Generation per scenario 60,000 50,000 Generation [GWh] 40,000 30,000 20,000 10,000 0 STs CCGTs CC DGUs DGUs Nuclear Coal PPs HPPs VRE of which of which Bagasse Wind PV Base 3 GW each 5 GW each 7 GW each 9 GW each 11 GW each 18

  19. Scenario Analysis: VRE share and Curtailment Potential & Actual VRE share in energy mix 35.0% Potential VRE share 30.0% Actual VRE share 25.0% Share of VRE [%] Potential VRE share 20.0% VRE Generation & Curtailment per Scenario Actual VRE share 15.0% 60,000 30.0% Generation/Curtailment [GWh] 10.0% 50,000 25.0% Curtailment Rate [%] 5.0% 40,000 20.0% 0.0% 30,000 15.0% 0 5,000 10,000 15,000 20,000 25,000 Installed VRE capacity [MW] 20,000 10.0% 10,000 5.0% Same curtailment for wind and PV 0 0.0% Base 3 GW each 5 GW each 7 GW each 9 GW each 11 GW each VRE Generation VRE Curtailment Curtaiment Rate 19

  20. Scenario Analysis: Variable Generation Cost Variable Generation Costs [MUSD] Category Base 5 GW each difference STs 2,119.1 2,095.5 -23.5 -1.1% CC DGUs 20.5 2.9 -17.6 -86.0% DGUs 4.9 0.6 -4.3 -86.8% Gas engines 0.1 0.0 -0.1 -100.0% CCGTs 4,822.6 4,544.0 -278.6 -5.8% Nuclear 134.2 134.0 -0.2 -0.2% Coal PPs 1,516.5 1,215.7 -300.9 -19.8% 8,617.9 7,992.6 TOTAL -625.3 -7.3% 20

  21. Scenario Analysis: System Short Run Marginal Cost System Short-Run Marginal Cost (SRMC) 52.00 50.00 SRMC [USD/MWh] 48.00 46.00 44.00 42.00 40.00 0 5,000 10,000 15,000 20,000 25,000 Installed VRE [MW] ▪ Steep cost reduction for low VRE shares due to large savings of expensive thermal generation ▪ Declining cost reduction due to increased reserve requirements and curtailment 21

  22. Task 1: Dispatch Diagnosis Task 1: Dispatch Diagnosis Chapter 1 Presentation of results and open discussion ▪ Results of Dispatch Simulation ▪ Results of Scenario Analysis ▪ Dispatch Constraints for the Integration of VRE 22

  23. VRE Dispatch Constraints: Overview Commercial, Legal, Regulatory, Transmission Reserves Generation Policy • SCADA 3 • Primary • CCGTs • Take-Or-Pay Agreements • Capacity • Secondary • Coal Power limitations • Ramping • Contingency • Steam turbines • Reserves • Nuclear • Nuclear Power • Responsibilities • Bagasse • Hydro Power • Geographical • Policy • Combustion distribution framework: engines • NTDC <> DISCOs Federal <> • Bagasse Provincial legislation 23

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend