Using HDD to Install Sewers Council of Oak Bay David OSullivan Of - - PowerPoint PPT Presentation

using hdd to install sewers council of oak bay david o
SMART_READER_LITE
LIVE PREVIEW

Using HDD to Install Sewers Council of Oak Bay David OSullivan Of - - PowerPoint PPT Presentation

Trenchless 101 in General Using HDD to Install Sewers Council of Oak Bay David OSullivan Of PW Trenchless Construction Inc. And NASTT-BC May 16 2016 Questions as we proceed David OSullivan Owner of PW Trenchless Const. Inc


slide-1
SLIDE 1

Trenchless 101 in General Using HDD to Install Sewers Council of Oak Bay

David O’Sullivan Of PW Trenchless Construction Inc. And NASTT-BC

May 16 2016 Questions as we proceed

slide-2
SLIDE 2

David O’Sullivan Owner of PW Trenchless Const. Inc

  • Experience in Horizontal Directional Drilling
  • Queensborough sewer system 3 contracts 5 t0 6km 200

to 300mm

  • Coquitlam 300m of 250mm in late 90’s
  • North Surrey 400m of 900mm
slide-3
SLIDE 3

Purpose of this Presentation

We will introduce you to various methods of trenchless construction. We will demonstrate the benefits / limitations of HDD As they are used in a Municipal situation. 1 The working area required for various pipe sizes 2 The limitations based on geotechnical considerations. 3 The limitations on economically delivering a small section of a project using HDD.

slide-4
SLIDE 4

TT in BC

slide-5
SLIDE 5

Cured in Place Pipe (CIPP)

Rehabilitation

  • Flexible resin-impregnated tube installed into an existing

pipe then cured to a solid finish – new pipe in an old.

slide-6
SLIDE 6

CIPP

slide-7
SLIDE 7

Slip Lining

slide-8
SLIDE 8

More Sliplining in Delta 2012

slide-9
SLIDE 9

Pipe Jacking

slide-10
SLIDE 10

Pipe Bursting Replacement / Upgrading

  • Bursting the existing pipe while pulling new pipe in place

behind – new pipe in the same trench.

slide-11
SLIDE 11

North Van Pool main drain replacement using pipe bursting

slide-12
SLIDE 12

Lateral pipe bursting

slide-13
SLIDE 13

Horizontal Directional Drilling

  • 1 Space requirements to complete a HDD operation.
  • 2 Limitations of HDD due to geotechnical issues.
  • 3 Contractual ability to entice contractors to complete

HDD competitively.

slide-14
SLIDE 14

Horizontal Directional Drilling

New construction /Replacement

  • Installation of pipes in a shallow arc using a surface

launched drilling rig.

slide-15
SLIDE 15

How HDD works

slide-16
SLIDE 16

HDD in Richmond

slide-17
SLIDE 17

Drilling of laterals Gravity or force main

THRUST 13,200 lbs PULL BACK 8,800 lbs TORQUE 442 ft lbs THRUST SPEED 606 ft / min BACKREAMING-DIAMETER 3″ / 4″ mm OUTER PIPE-DIAMETER >3″

slide-18
SLIDE 18

Limitations of HDD

  • Entrance slope and stabilization of “on grade” section
  • Ability to maintain grade due to equipment and

experience.

  • Ability to maintain grade due to soil conditions
slide-19
SLIDE 19

Working space Entrance/Exit slopes

  • The driller needs to get the drill head on line/grade and

level.

  • Required distance about 6X( 12 deg) depth plus 10m plus

the rig footprint 10 m, total about 38m .

  • Total length before usable “tunnel”
  • The exit needs almost the same working area. The rig

area is slightly smaller ,say 33m.

  • This is based on installing a 400mm pipe using a 65,000 lb

rig.

slide-20
SLIDE 20

HDD Machine in the Pit

  • In some cases the HDD rig can be taken apart and

lowered into the pit.

  • Need 2nd pit to capture drilling muds.
  • Large danger of destroying machine from flooding.(2

flooding in BC in 4 years)

  • Entrance length still needs to be 15 to 20m
  • Still need exit pit to be conventional 30 to 40m long
slide-21
SLIDE 21

Bore path using HDD

slide-22
SLIDE 22

Soil conditions

Ideal Drilling Soils All the particle size is uniform and fairly cohesive

Here we have a silt/ clay / peat and sandy type soil.

slide-23
SLIDE 23

th

Soils Not Suitable to Drilling Note the soil particles are not uniform in size and not cohesive

slide-24
SLIDE 24

Soil conditions at a central location

  • HDD most suited to

humongous type ground.

  • Cobbles in gravel or a till type

matrix cause problems.

  • Sewers do not allow

variations of horizontal alinement.

  • Roots cause problems to

small rigs.

slide-25
SLIDE 25

Existing utilities and Project Limitations

  • HDD drills will tend to go towards the softest ground.
  • No control of reamer locations see above
  • Curved HDD uses large horizontal swath.
  • Pipe reamers are toothed cones turning at 40,000lb of

torque and will destroy anything in path.

slide-26
SLIDE 26

Governing conditions in Oak Bay

  • We need to install manholes approximately every 120m.
  • We need to install sewer pipes from 150mm to 600mm in

Dia

  • Roads are curved
  • Easements contain mature trees
  • Easements are relatively short and non-linear
  • Easements terminate perpendicular to some property

lines

  • Variable ground conditions
slide-27
SLIDE 27

Contractual Constraints

  • 400 mm pipe requires a 60,000 lb rig.
  • 300mm pipe required a 45,000lb rig
  • Limited availability in B.C.
  • Each mobe /demobe costs $35,000.00
slide-28
SLIDE 28

TT Research Conclusion

Each Mile of open cut trench produces 1600 truckloads

  • f material.
  • Thank You