Tsilhqotin Solar Farm Pembina Institute Clean Future Forum - - PowerPoint PPT Presentation

tsilhqot in solar farm
SMART_READER_LITE
LIVE PREVIEW

Tsilhqotin Solar Farm Pembina Institute Clean Future Forum - - PowerPoint PPT Presentation

Tsilhqotin Solar Farm Pembina Institute Clean Future Forum February 28, 2019 Dolly Kershaw Economic Opportunities Coordinator Economic Development Sub Table Co-Manager T silhqotin National Government - 6 Communities Where we are


slide-1
SLIDE 1

Tsilhqot’in Solar Farm

Pembina Institute Clean Future Forum February 28, 2019

slide-2
SLIDE 2

Dolly Kershaw

Economic Opportunities Coordinator Economic Development Sub Table Co-Manager

slide-3
SLIDE 3

Tsilhqot’in National Government -

6 Communities

slide-4
SLIDE 4

Where we are located

slide-5
SLIDE 5

The Project

TSILHQOT’IN 1.25 MW Solar Farm

slide-6
SLIDE 6

WL Substation Solar Farm End of the line

The Chilcotin is served by a weak 250 Km-long power line that runs from Williams Lake to Tatla Lake. The low capacity of the grid throttles economic activities and must be supplemented by diesel generators.

slide-7
SLIDE 7

The Solar farm is installed on the brownfield land of the former Riverwest

  • sawmill. It is bringing new life to an abandoned industrial site.

Located 90 Km west of Williams Lake

slide-8
SLIDE 8

BC Hydro 34.5 kV Distribution line runs next to the site

slide-9
SLIDE 9

The Chilcotin region is amongst the top five solar hot spots in BC.

slide-10
SLIDE 10

Expected Outcomes

  • generation of clean energy;
  • redevelopment of a closed sawmill and adjacent brownfield into a

solar farm;

  • support to the local communities;
  • creation of jobs and business opportunities;
  • Ongoing revenue source.
slide-11
SLIDE 11

How Long to get to where we are?

slide-12
SLIDE 12

2015 2016 2017 2018 Solar Farm Time Line

Pre- Feasibility Study Completed

Council of Chiefs approve the development

  • f a 1MW

Solar Farm Pre work and seek Government Funding

  • March BC Hydro Application Accepted
  • Summer BC Hydro SOP under review
  • December BC Hydro notifies us that no

more EPA’s will be issued

  • Dialogue and Discussions between both

parties March - BC Hydro announces to pursue negotiations with 5 First Nations clean energy projects August 8 Dually signed EPA received Order equipment and construction period

slide-13
SLIDE 13

Trainees

slide-14
SLIDE 14

Once completed the Solar Farm will be the first large-scale solar power plant 100% owned and

  • perated by a First Nations in

Western Canada.

slide-15
SLIDE 15
slide-16
SLIDE 16

Sechanalhyagh