Tran ansportation: Con oncurrency an and 20 2019 19-2024 CIP IP - - PowerPoint PPT Presentation

tran ansportation con oncurrency an and 20 2019 19 2024
SMART_READER_LITE
LIVE PREVIEW

Tran ansportation: Con oncurrency an and 20 2019 19-2024 CIP IP - - PowerPoint PPT Presentation

Tran ansportation: Con oncurrency an and 20 2019 19-2024 CIP IP Kirkland Transportation Commission June 27, 2018 Concurrency and th the CIP IP Inter-related programs that: Balance growth with transportation capacity Implement


slide-1
SLIDE 1

Tran ansportation: Con

  • ncurrency an

and 20 2019 19-2024 CIP IP

Kirkland Transportation Commission June 27, 2018

slide-2
SLIDE 2

Concurrency and th the CIP IP

Inter-related programs that:

  • Balance growth with transportation

capacity

  • Implement multimodal policies of the

TMP

slide-3
SLIDE 3

3 In Interrela lated Programs

Impact Fees

Pay fair share

  • f System

impacts

Concurrency

Basic balance of development and transportation network

Capacity CFP and CIP

Capacity Projects in the transportation network

slide-4
SLIDE 4

Transportation Concurrency

slide-5
SLIDE 5

Transportation Concurrency

Basic Rules:

  • Adopt a Level of Service (LOS).
  • Add capacity at the same (or greater) rate as growth to

maintain (or improve) LOS.

  • Balance concurrency within each 6-year CIP.

Concurrency ledger provides policy-makers with a tool to monitor status and make informed decisions.

slide-6
SLIDE 6

Kirkland’s Transportation LOS

Defined by 20-year plan for multimodal capacity projects in CFP:

  • Informed by Kirkland 2035 community engagement
  • Assumes an additional trip capacity of 15,000 is needed to

keep pace with growth over 20 years.

  • Aligns with multi-modal policies in TMP
  • Achieves GMA goals more effectively than single-mode approach
  • Is within a reasonable 20-year funding forecast
slide-7
SLIDE 7

Trip ips are Added to th the Ledger

By completing capacity projects that are in the transportation CFP:

Built or Funded CFP $ 20-year CFP $

x

Forecast trips for 20 years

=

Person trips added

slide-8
SLIDE 8

Concurrency Ledger

Trips Available 1/1/2016 7,419 Trips Reserved as of 3/7/18 5,146 *3/7/18 Trip Balance 2,243

slide-9
SLIDE 9

Chall llenges

  • Project cost escalation
  • “Front-loaded” growth rates and the need to balance capacity within 6-year

CIP

  • New capacity projects added to CFP (e.g., 6th Street Corridor Projects,

132nd/108th)

  • Lag between concurrency certificate and receipt of impact fees
  • The Funded Transportation Capacity CIP is heavily reliant on unsecured

grants

slide-10
SLIDE 10

Reprioritizin ing Transportation CIP IP Proje jects

Based on:

  • Council-adopted CIP Policy Priorities
  • Number of trips added
  • Percent of design, acquisition, permitting complete
  • Risk Mitigation (Cost escalation, permitting, risk of design

grant payback requirement.)

  • Ability to meet other (non-capacity) priorities (Safety,

infrastructure preservation, urban center enhancement, multimodal network completion, transit access, etc.)

slide-11
SLIDE 11

Staff-Recommended Project Prio iorities

*Staff recommends highest priority segments.

slide-12
SLIDE 12

Project Description Local* External* Total* Trips TR136 NE 145th St Intersection 1.23 0.00 1.23 96 ST83103 Simonds to NE 145th St Roadway 1.40 2.15 3.55 276 TR135 Simonds Intersection 1.19 0.00 1.19 92 ST83104 NE 137th St to Simonds Roadway 4.00 3.50 7.50 583 SD124 Cedar Creek Culvert 2.10 0.00 2.10 North half sub-totals 9.92 5.65 ***15.57 **1,047 Project Description Local* External* Total* Trips TR134 NE 137th St Intersection 1.48 0.00 1.48 ST83105 Juanita-Woodinville to NE 137th St 3.50 0.00 3.50 TR133 Juanita-Woodinville Intersection 2.16 0.00 2.16 ST83106 NE 132nd St to Juanita-Woodinville 0.62 2.23 2.85 TR132 NE 132nd St Intersection 1.65 0.00 1.65 South half sub-totals 9.41 2.23 ***11.64 Total 18.43 8.78 ***27.21 1,047 * Amounts in 2019 dollars, by million ** Local cost per trip ($9,475) calculated by $9.92M / 1,047 trips (not including grant funding) *** Art [north]($291,800) [south]($112,600) not currently include in table totals

ST83103 SD124 TR133 TR135 TR136 TR132 TR134 ST83104 ST83105 ST83106

Future phase(s) Recommended project phase Simonds Rd

slide-13
SLIDE 13

Project Description Amount* I3 112th Ave NE left turn, bike, S/W 2.30 R5 NE 128th St Left turn, S/W, lights 0.38 NM4 NE 124th St ped crossing 0.17 I5 NE 120th St left turn, ped crossing 1.22 I6 NE 132nd St left turn, ped crossing 1.07 R7 S/W and bike 0.95 R8 S/W and bike 0.61 Sub total 6.70 I-7** NE 138th ST roundabout 1.23 Total 8.03

* Amount in 2019 dollars, by million ** optional cost when combined with R8 I3 NM4 R5 I6 I5 R8 R7 I-7