Thomas Otto (TE DSO), Safety Officer in Charge of LS1. Thomas Otto, - - PowerPoint PPT Presentation

Thomas Otto (TE DSO), Safety Officer in Charge of LS1. Thomas Otto, Safety Officer in charge of LS1 1 37th LSC, 7. 2. 2014 25.1. Unauthorised entry in BA 1 A worker from a contractor company entered the BA1 site with a member of his


slide-1
SLIDE 1

Thomas Otto (TE DSO), Safety Officer in Charge of LS1.

37th LSC, 7. 2. 2014 Thomas Otto, Safety Officer in charge of LS1 1

slide-2
SLIDE 2

25.1. Unauthorised entry in BA 1

  • A worker from a

contractor company entered the BA1 site with a member of his family on a Saturday morning

  • He is identified by

the Guards and escorted off-site.

  • His hierarchy has

been notified

37th LSC, 7. 2. 2014 Thomas Otto, Safety Officer in charge of LS1 2

Access control = hazardous area Private Visits are not allowed in areas under access-control

slide-3
SLIDE 3

4.2.: Safety Barrier removed

  • A safety barrier

blocked PM 56 to prevent access into a cryogenic hazard area

  • An unknown,

unauthorised person removed the barrier

  • Later, an

unsuspecting staff member entered the hazard area by PM 56

37th LSC, 7. 2. 2014 Thomas Otto, Safety Officer in charge of LS1 3

Safety Barriers are for personal protection Do not risk your and other’s health or life

  • 4. 2. 18:00
  • 5. 2. 8:00
slide-4
SLIDE 4

LS1 A&T Accident Statistics

  • LS1 related accidents
  • A&T Sector personnel or on A&T worksites
  • Without road accidents
  • 62 accidents
  • 20 accidents with days of absence
  • 175 days of absence

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

4

slide-5
SLIDE 5

Who and where ?

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

5

Facility Total Minor With days

  • f absence

Total days** PS 1 1

  • SPS

3 3

  • LHC

20 14 6 27 Surface 34 22 12 134 Experiments* 4 2 2 14 Total 62 42 20 175

ENTC STAFF PJAS/COAS FELL/TRNE Total Minor 31 7 3 1 42 With absence 16 2 1 1 20 Total 47 9 4 2 62 TE EN BE PH* IT* Total 31 19 7 3 1 62

* On A&T Worksites * A&T Personnel

slide-6
SLIDE 6

Statistical Indicators

  • Most accident victims are contractor’s personnel, but

accidents are 6 times less severe as usual

  • The excellent preparation of the works and the

thorough training of the workers by the CERN LS-1 teams was worth the effort.

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

6

Frequency rate Severity rate Year MPE Contractor MPE Contractor 2009 4.78 29 0.1 0.53 2010 2.93 23.33 0.05 0.52 2011 2.5 21.33 0.04 0.45 2012 2.86 24.62 0.08 0.60 2013 (LS1) 9.1 0.08

slide-7
SLIDE 7

Causes of accidents

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

7

Description All Minor With days of absence Days of absence Falls of persons 6 2 4 74 Handheld tools 7 5 2 38 Striking against stationary objects, strenuous movements 18 13 5 19 Moving objects, manual handling 9 6 3 18 Means of Transport 3 1 2 12 Fixed tooling machines 3 1 2 10 Struck by moving objects or particles 10 8 2 4 Exposure to chemical products 2 2 Electricity 2 2 Exposure to extreme temperatures 2 2 Total 62 42 20 175

slide-8
SLIDE 8

Causes of accidents

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

8

Description All Minor With days of absence Days of absence Falls of persons 6 2 4 74 Handheld tools 7 5 2 38 Striking against stationary objects, strenuous movements 18 13 5 19 Moving objects, manual handling 9 6 3 18 Means of Transport 3 1 2 12 Fixed tooling machines 3 1 2 10 Struck by moving objects or particles 10 8 2 4 Exposure to chemical products 2 2 Electricity 2 2 Exposure to extreme temperatures 2 2 Total 62 42 20 175

Accident due to inappropriate footwear (thongs): 51 days absence

slide-9
SLIDE 9

Causes of accidents

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

9

Description All Minor With days of absence Days of absence Falls of persons 6 2 4 74 Handheld tools 7 5 2 38 Striking against stationary objects, strenuous movements 18 13 5 19 Moving objects, manual handling 9 6 3 18 Means of Transport 3 1 2 12 Fixed tooling machines 3 1 2 10 Struck by moving objects or particles 10 8 2 4 Exposure to chemical products 2 2 Electricity 2 2 Exposure to extreme temperatures 2 2 Total 62 42 20 175

Bump-caps for head-protection

slide-10
SLIDE 10

Causes of accidents

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1

10

Description All Minor With days of absence Days of absence Falls of persons 6 2 4 74 Handheld tools 7 5 2 38 Striking against stationary objects, strenuous movements 18 13 5 19 Moving objects, manual handling 9 6 3 18 Means of Transport 3 1 2 12 Fixed tooling machines 3 1 2 10 Struck by moving objects or particles 10 8 2 4 Exposure to chemical products 2 2 Electricity 2 2 Exposure to extreme temperatures 2 2 Total 62 42 20 175

Bicycle accidents in LHC. Is there a better means of transport for LS-2 and for future facilities ?

slide-11
SLIDE 11

37th LSC, 7. 2. 2014

Thomas Otto, Safety Officer in charge of LS1