third annual carnegie mellon conference on the
play

Third Annual Carnegie Mellon Conference on the Electricity Industry - PowerPoint PPT Presentation

Third Annual Carnegie Mellon Conference on the Electricity Industry Enhancing IGCC economics with a diurnal syngas storage scheme Adam Newcomer and Jay Apt Carnegie Mellon University March 14, 2007 1 Preliminary data. Do not cite or quote


  1. Third Annual Carnegie Mellon Conference on the Electricity Industry Enhancing IGCC economics with a diurnal syngas storage scheme Adam Newcomer and Jay Apt Carnegie Mellon University March 14, 2007 1 Preliminary data. Do not cite or quote without permission of the authors.

  2. Research Question What is the value of adding gas storage capabilities to a coal gasification facility? or, put another way Can syngas storage lower the carbon price at which IGCC enters the generation mix? 2 Preliminary data. Do not cite or quote without permission of the authors.

  3. Project overview and methodology Gas Turbine Syngas Coal Electricity Current gasification operations: End use (turbine) coupled with gasifier Gas Turbine Coal Syngas Electricity Compression and Storage Storage scenario: Turbine can operate independently of gasifier Storage allows for additional flexibility in facility configuration and operation 3 Preliminary data. Do not cite or quote without permission of the authors.

  4. Example: Producing Peak Electricity with Stored Syngas Electricity Generated: Valve setting: Valve setting: to gasifier Valve setting: to storage Valve setting: to gasifier 2x 1x 0 LMP $/MW: average high low 4 Preliminary data. Do not cite or quote without permission of the authors.

  5. Scenarios Baseline: No Storage Diurnal Syngas Storage 5 Preliminary data. Do not cite or quote without permission of the authors.

  6. Scenario Data Sources Integrated Environmental Control Model (IECM) www.iecm-online.com Engineering Economic Model Historical and Future Prices 6 Preliminary data. Do not cite or quote without permission of the authors.

  7. Storage Options • Examined only compressed gas storage options • Diurnal storage • Storage technologies considered – Above ground • Low pressure (gasometers) • High Pressure • (cylindrical bullets, gas spheres) – Underground • Rock caverns • Salt caverns • Explored the costs and tradeoffs between – storage pressures and storage volumes – storing low energy density syngas versus storing methanated syngas (synthetic natural gas or SNG) 7 Preliminary data. Do not cite or quote without permission of the authors.

  8. Economic Data Sources • Input Coal Historical (Aug 05-06) : Monthly average FOB prices for Illinois Basin coal Future (2007): EIA AEO forecast, EIA AEO forecast with accuracy factor, NYMEX futures • Output Electricity Historical (Aug 05-06) Locational marginal price (LMP) data from Midwest ISO (MISO) • CDFs of all price data were created for input into the engineering economic model Source: Adapted from Midwest ISO 8 Preliminary data. Do not cite or quote without permission of the authors.

  9. Coal Price Data 1.00 0.80 Cumulative Probability 0.60 2007 EIA AEO NYMEX futures 0.40 2005-06 historical 2007 EIA with 0.20 accuracy factor 0.00 1.1 1.3 1.5 1.7 1.9 2.1 2.3 $/MMBtu 9 Preliminary data. Do not cite or quote without permission of the authors.

  10. Electricity Price Data $ / MW Price duration curve. Cinergy node, Aug 05 - Aug 06 10 Preliminary data. Do not cite or quote without permission of the authors.

  11. Scenario Analysis Details 11 Preliminary data. Do not cite or quote without permission of the authors.

  12. Scenario Analysis Details annual revenue ROI = total levelized annual expenses where 8760 ⋅ ∑ + ⋅ (MW MW ) LMP annual revenue = availability 1 i 2 i i = 1 i total levelized annual expenses = levelized capital costs + fixed O&M costs + (availability • variable O&M costs) 12 Preliminary data. Do not cite or quote without permission of the authors.

  13. Scenario Analysis Details 12 hour storage 12 hour storage 180 Turbines running / storage discharging 160 Turbines off / storage filling 140 120 100 ($/MW) 80 60 40 20 0 Dec 10, 2005 Dec 11, 2005 Dec 12, 2005 Dec 13, 2005 Dec 14, 2005 Dec 15, 2005 13 Preliminary data. Do not cite or quote without permission of the authors.

  14. Scenario Analysis Details 8 hour storage 8 hour storage 180 2 Turbines running / storage discharging 1 Turbine running 160 Turbines off / storage filling 140 120 100 ($/MW) 80 60 40 20 0 Dec 10, 2005 Dec 11, 2005 Dec 12, 2005 Dec 13, 2005 Dec 14, 2005 Dec 15, 2005 14 Preliminary data. Do not cite or quote without permission of the authors.

  15. Preliminary Results: Gasifier + Turbine (baseline) 1.00 Baseline 0.90 (no storage) Cumulative Probability 0.80 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0.00 0.85 0.9 0.95 1 1.05 1.1 1.15 1.2 Return on Investment ROI Key financial parameters: 30 year economic/loan life, 100% financing, 8% interest rate, Cinergy node, historical coal prices Key operating parameters: 80 percent availability, 1 operating gasifier and 1 spare gasifier (1+1) 15 Preliminary data. Do not cite or quote without permission of the authors.

  16. Preliminary Results: Syngas Storage 1.00 Baseline Syngas Storage 0.90 (no storage) Cumulative Probability 0.80 0.70 0.60 0.50 0.40 Storage Time (hours) 0.30 0 + 16% for 12 hour storage 0.20 4 8 + 11% for 8 hour storage 0.10 12 0.00 0.85 0.9 0.95 1 1.05 1.1 1.15 1.2 Return on Investment ROI Key financial parameters: 30 year economic/loan life, 100% financing, 8% interest rate, Cinergy node, historical coal prices Key operating parameters: 80 percent availability, 1 operating gasifier and 1 spare gasifier (1+1) 16 Preliminary data. Do not cite or quote without permission of the authors.

  17. Preliminary Syngas Storage NPV 150 Net Present Value ($ millions) 2005-6 historical coal price 100 2007 EIA AEO forecast with accuracy factor 50 0 -50 -100 -150 0 4 8 12 Storage Hours Key financial parameters: 30 year economic/loan life, 100% financing, 8% interest rate, Cinergy node Key operating parameters: 80% availability, 35 bar pressure, above ground storage, 2000 hp compressor, 1 operating gasifier and 1 spare gasifier (1+1) 17 Preliminary data. Do not cite or quote without permission of the authors.

  18. Preliminary Syngas Storage NPV 400 Storage Time (hours) Increase in NPV ($ millions) 4 hours 350 8 hours 12 hours 300 250 200 150 100 50 0 Cinergy Hub First Energy Illinois Hub Michigan Hub ALTE.ALTE AMRN.MOBCTG1 ALTW.PRARC1 ALTE.UPP Hub MISO node Key financial parameters: 30 year economic/loan life, 100% financing, 8% interest rate Key operating parameters: 80% availability, 35 bar pressure, above ground storage, 2000 hp compressor, 1 operating gasifier and 1 spare gasifier (1+1) 18 Preliminary data. Do not cite or quote without permission of the authors.

  19. Sensitivity Analysis Syngas storage scenario, + 10% variation in parameters ROI is most sensitive to : Availability, Financing and Coal Price Note: ROI is also sensitive to facility size and gasifier configuration 12 hours of syngas storage at a larger 800 MW facility (with 3 operating gasification trains and 1 spare) increases ROI by 14 percentage points (from 1.06 to 1.14) 19 Preliminary data. Do not cite or quote without permission of the authors.

  20. 3+1 analysis 1.00 Increased ROI due to: 0.90 Syngas Baseline • Economy of scale Storage (no storage) 0.80 • Less idle capital (with the 3+1, only Cumulative Probability 0.70 25% of the gasifier capital is idle versus 50% for the 1+1) 0.60 0.50 0.40 Storage Time 0.30 (hours) 0 0.20 4 8 0.10 12 0.00 0.95 1 1.05 1.1 1.15 1.2 1.25 Return on Investment Key financial parameters: 30 year economic/loan life, 100% financing, 8% interest rate, Cinergy node, historical coal prices Key operating parameters: 80% availability, 35 bar pressure, above ground storage, 2000 hp compressor, 3 operating gasifiers and 1 spare gasifier (3+1), 4 GE 7FA turbines total with 2 turbines in baseload operation and 2 turbines operating with the diurnal storage scheme 20 Preliminary data. Do not cite or quote without permission of the authors.

  21. Preliminary Results ROI, 90% CI ….. NPV Sensitivity Analysis Scenario min mid max (million) (parameters most affecting ROI) Baseline Availability 0.89 0.92 0.96 -$80 Financing structure no storage † 0.86 0.88 0.91 -$127 Coal price no storage # Gasifier + cleanup capital costs Syngas Storage Availability 4 hours † 0.92 0.96 0.98 -$61 Financing structure 4 hours # 0.89 0.91 0.94 -$107 Coal price 8 hours † 1.00 1.03 1.07 $40 Gasifier + cleanup capital costs 8 hours # 0.97 0.99 1.03 -$7 Turbine capital costs 12 hours † 1.05 1.08 1.12 $101 12 hours # 1.02 1.04 1.07 $54 † 2005-06 historical coal price # modified 2007 EIA coal price forecast Key financial parameters: 30 year economic/loan life, 100% financing, 8% interest rate Key operating parameters: 80% availability, 35 bar pressure, above ground storage, 2000 hp compressor, 1 operating gasifier and 1 spare gasifier (1+1) 21 Preliminary data. Do not cite or quote without permission of the authors.

  22. High pressure storage in industry 22 Preliminary data. Do not cite or quote without permission of the authors.

  23. Wabash River 12 hours of storage adds <10 acres, or 25% ~250 net MW IGCC facility, ~40 acres 255m 23 Preliminary data. Do not cite or quote without permission of the authors.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend